Anholt

399.6 MW Fully Commissioned Denmark

"The 4C database is an incredibly useful tool to help understand the industry, the trends and where to give future focus. The volume of data is impressive and gives a comprehensive view on the entire market."

James Reynolds, Wärtsilä Deutschland GmbH


  • All Projects
  • Followed Projects



map not available
Latest Update: 24 March 2015
After four weeks and two days the cable was repaired and power was being transmitted back to shore. Read More
Developers/Owners/Operators
Project Details for Anholt
General Information Name Anholt correct
Other names Djursland Anholt correct
Country name Denmark correct
Region Nørre Djurs correct
Comments DONG Energy was the only bidder to develop Anholt wind farm. Energinet.dk was responsible for the financing and construction of the offshore substation and connecting the wind farm to the national grid. correct
Round (or category) Tender (DK) correct
Development status Fully Commissioned correct
Comments on the status correct
Power & Turbines Notice any Errors? You can keep this an open resource by submitting corrections!
Project Capacity 399.6 MW correct
Turbine Model SWT-3.6-120 (Siemens) correct
Turbine Capacity 3.6 MW correct
Number of Turbines 111 correct
Total Turbine Height 141.6 m correct
Hub Height 81.60 m correct
Rotor Diameter 120 m correct
Foundation Grounded: Monopile (Diameter of 5.4m.) correct
Windspeed 10 Year Mean Wind Speed (2000-2009) Available online now
Detailed wind speed data 6 hr/day/month historic data
Costs Stated Project Cost DKK(mill) 10000.00 correct
Location & Environment Sea name Kattegat correct
Centre latitude 56.598° correct
Centre longitude 11.208° correct
Area 116 km2 correct
Depth range (Chart Datum) 12 m - 19 m correct
Depth range stated by developer 15 m - 19 m correct
Distance From Shore (reported) 15 km correct
Distance From Shore (computed from centre) 22.6 km correct
Ports Installation base Grenaa Harbour correct
Ops and maintenance Grenaa Harbour correct
Grid Converter/Collector platforms None correct
Offshore transformers Anholt Substation correct
Grid connection point Trige correct
Cable landing point Saltbækken, Grenaa correct
Export Cables
Please note that export cables connect the offshore transformer (substation) to either; shore or an offshore HVAC-HVDC converter station for onward transmission via HVDC cabling. Please see the converters page for planned converter stations and transmission cables.

The export cable length does not generally include the onshore component. The exception is when the onshore substation is close to shore.
Number of Export Cables 1 correct
Average length per cable 24.5 km correct
Transmission type (e.g. HVAC) HVAC correct
Nominal voltage 220 kV correct
Maximum voltage 245 kV correct
Power rating correct
Number of cores 3 correct
Conductor type Al correct
Section Area 1600 mm2 correct
Insulation correct
Number fibre optics correct
Export minimum bend radius (MBR) correct
Burial depth correct
Comments correct
Onshore Cables Number of onshore cables correct
Average length per cable 56 km correct
Comments correct
Array Cables Array cable length 160 km correct
Estimated cable length LogIn
Transmission type (e.g. MVAC) MVAC correct
Nominal voltage 36 kV correct
Maximum voltage correct
Burial depth correct
Number of cores correct
Conductor type correct
Section 500 mm2 correct
Insulation correct
Power rating correct
Number of fibre optics correct
Minimum bend radius (MBR) correct
Comments correct
Benefits Homes powered annually 283019 correct
CO2 reduced per year 571981 tonnes correct
SO2 reduced per year 13302 tonnes correct
Expected life correct
Other Website Visit correct

This page is intended to be viewed online and may not be printed without a valid subscription.

Please view this page at http://www.4coffshore.com/windfarms/windfarms.aspx?windfarmID=dk13.