Latest event on Burbo Bank Extension

In total 31 of the 32 MHI Vestas V164-8.0MW turbines have been commissioned at the site. Read more

Latest Update: 19 March 2017

Developers/Owners/Operators Database in Excel | Add Your Organisation
Project Details for Burbo Bank Extension Database in Excel
Name Burbo Bank Extension correct
Other names Burbo Bank 2 correct
Country name United Kingdom correct
Region England, North West correct
Comments This is the first offshore wind farm project to be built using energy yield calculations based on wind resource data collected from a floating lidar.

Ofgem's Tender Round 4 will select an OFTO for Burbo Bank Extension's offshore transmission assets, valued in the region of £230.2 million. Tender Round 4 has been described as a 'bridge' between Round 3 and Round 5, only consisting of a single project. The Round will commence in April 2016, as initial documentation becomes available, anticipating a preferred supplier to be announced in March 2017.
correct
Round (or category) Round 2.5 correct
Development status Partial Generation/Under Construction correct
Comments on the status correct
Notice any Errors? You can keep this an open resource by submitting corrections!
Project capacity 254.2 MW correct
Turbine model V164-8.0 MW (MHI Vestas Offshore Wind) correct
Turbine capacity 8 MW correct
Number of turbines 32 correct
Total turbine height 187 m correct
Hub height 105.00 m correct
Rotor diameter 164 m correct
Foundation Grounded: Monopile correct
10 year mean wind speed (2000-2009) Available online now
Stated project cost GBP(mill) 800.00 correct
Sea name Irish Sea correct
Centre latitude 53.484° correct
Centre longitude -3.273° correct
Area 40 km2 correct
Depth range (Chart Datum) 3 m - 14 m correct
Depth range stated by developer 4 m - 17 m correct
Distance from shore (reported) 6 km correct
Distance from shore (computed from centre) 11.5 km correct
Installation base Cammell Laird, Birkenhead, Liverpool correct
Ops and maintenance Seacombe (Future) correct
Converter/Collector platforms None correct
Offshore transformers Burbo Bank Extension Substation correct
Grid connection point NGET Bodelwyddan 400kV Substation correct
Cable landing point Between Rhyl and Prestatyn correct
Number of export cables 1 correct
Average length per cable 26 km correct
Transmission type (e.g. HVAC) HVAC correct
Nominal voltage 220 kV correct
Maximum voltage correct
Power rating correct
Number of cores 3 correct
Conductor type correct
Section area correct
Insulation XLPE correct
Number fibre optics correct
Export minimum bend radius (MBR) correct
Burial depth correct
Comments correct
Number of onshore cables 3 correct
Average length per cable 10.5 km correct
Comments 220kV correct
Array cable length 65 km correct
Estimated cable length LogIn
Transmission type (e.g. MVAC) MVAC correct
Nominal voltage 34 kV correct
Maximum voltage correct
Burial depth correct
Number of cores 3 correct
Conductor type Cu correct
Section correct
Insulation XLPE correct
Power rating correct
Number of fibre optics correct
Minimum bend radius (MBR) correct
Comments Will require eight array cable strings to connect the turbines to the offshore substation. correct
Homes powered annually 180039 correct
CO2 reduced per year 363858 tonnes correct
SO2 reduced per year 8462 tonnes correct
Expected life 25.0 years correct
Website Visit correct

Call +44 (0)1502 307 037 for more information

Keep on top of the market. Perform analysis. Make informed decisions.

CONTACT US

More information?

Receive monthly updates with our Offshore Windfarm Subscription and gain access to even more detailed information on; cabling, converters, costs, foundations, substations, turbines.

Filter :
123
StatusName
Decommissioned Beatrice Demonstration Beatrice Demonstration
Decommissioned Blyth Blyth
Fully Commissioned Barrow Barrow
Fully Commissioned Burbo Bank Burbo Bank
Fully Commissioned Greater Gabbard Greater Gabbard
Fully Commissioned Gunfleet Sands Gunfleet Sands
Fully Commissioned Gunfleet Sands 3 - Demonstration Project Gunfleet Sands 3 - Demonstration Project
Fully Commissioned Gwynt y Môr Gwynt y Môr
Fully Commissioned Humber Gateway Humber Gateway
Fully Commissioned Hunterston Test Centre - Mitsubishi 7MW (onshore) Hunterston Test Centre - Mitsubishi 7MW (onshore)
Fully Commissioned Hunterston Test Centre - Siemens 6MW (onshore) Hunterston Test Centre - Siemens 6MW (onshore)
Fully Commissioned Hunterston Test Centre (onshore) Hunterston Test Centre (onshore)
Fully Commissioned Inner Dowsing Inner Dowsing
Fully Commissioned Kentish Flats Kentish Flats
Fully Commissioned Kentish Flats Extension Kentish Flats Extension
Fully Commissioned Levenmouth demonstration turbine Levenmouth demonstration turbine
Fully Commissioned Lincs Lincs
Fully Commissioned London Array London Array
Fully Commissioned Lynn Lynn
Fully Commissioned North Hoyle North Hoyle
Fully Commissioned Ormonde Ormonde
Fully Commissioned Rhyl Flats Rhyl Flats
Fully Commissioned Robin Rigg Robin Rigg
Fully Commissioned Scroby Sands Scroby Sands
Fully Commissioned Sheringham Shoal Sheringham Shoal
Fully Commissioned Teesside Teesside
Fully Commissioned Thanet Thanet
Fully Commissioned Walney Phase 1 Walney Phase 1
Fully Commissioned Walney Phase 2 Walney Phase 2
Fully Commissioned Wave Hub Wave Hub
Fully Commissioned West of Duddon Sands West of Duddon Sands
Fully Commissioned Westermost Rough Westermost Rough
Partial Generation/Under Construction Burbo Bank Extension Burbo Bank Extension
Partial Generation/Under Construction Dudgeon Dudgeon
Under Construction Galloper Galloper
Under Construction Race Bank Race Bank
Under Construction Rampion Rampion
Pre-Construction Aberdeen Offshore Wind Farm (EOWDC) Aberdeen Offshore Wind Farm (EOWDC)
Pre-Construction Beatrice Beatrice
Pre-Construction Blyth Offshore Demonstrator Project - Array 2 Blyth Offshore Demonstrator Project - Array 2
Pre-Construction East Anglia ONE East Anglia ONE
Pre-Construction Hornsea Project One Hornsea Project One
Pre-Construction Hywind Scotland Pilot Park Hywind Scotland Pilot Park
Pre-Construction Walney Extension Walney Extension
Consent Authorised Blyth Offshore Demonstrator Project - Array 3A & 4 Blyth Offshore Demonstrator Project - Array 3A & 4
Consent Authorised Dogger Bank - Creyke Beck A Dogger Bank - Creyke Beck A
Consent Authorised Dogger Bank - Creyke Beck B Dogger Bank - Creyke Beck B
Consent Authorised Dogger Bank - Teesside A Dogger Bank - Teesside A
Consent Authorised Dogger Bank - Teesside B Dogger Bank - Teesside B
Consent Authorised Dounreay Trì Dounreay Trì
123
Please LogIn to follow projects
Find quick and easy project and company information with our online search tool

This page is intended to be viewed online and may not be printed without a valid subscription.

Please view this page at http://www.4coffshore.com/windfarms/windfarms.aspx?windfarmID=uk59.