Latest event on Burbo Bank

The Jack-up vessel Wind Server arrived on site to carry out component exchange at turbine positions BB16 and BB28. These two turbine positions were previously investigated using a bathymetric survey. Read more

Latest Update: 19 February 2017

Developers/Owners/Operators Database in Excel | Add Your Organisation
Project Details for Burbo Bank Database in Excel
Name Burbo Bank correct
Other names Crosby Flats correct
Country name United Kingdom correct
Region England, North West correct
Comments correct
Round (or category) Round 1 correct
Development status Fully Commissioned correct
Comments on the status correct
Notice any Errors? You can keep this an open resource by submitting corrections!
Project capacity 90 MW correct
Turbine model SWT-3.6-107 (Siemens) correct
Turbine capacity 3.6 MW correct
Number of turbines 25 correct
Total turbine height 137 m correct
Hub height 83.50 m correct
Rotor diameter 107 m correct
Foundation Grounded: Monopile correct
10 year mean wind speed (2000-2009) Available online now
Stated project cost EUR(mill) 181.00 correct
Sea name Irish Sea correct
Centre latitude 53.489° correct
Centre longitude -3.187° correct
Area 10 km2 correct
Depth range (Chart Datum) 0 m - 5 m correct
Depth range stated by developer 0 m - 8 m correct
Distance from shore (reported) 6.4 km correct
Distance from shore (computed from centre) 8 km correct
Installation base Mostyn correct
Ops and maintenance Liverpool harbour, Sercombe (Future) correct
Converter/Collector platforms None correct
Offshore transformers None correct
Grid connection point Wallasey correct
Cable landing point Wallasey correct
Number of export cables 3 correct
Average length per cable 8.4 km correct
Transmission type (e.g. HVAC) MVAC correct
Nominal voltage 33 kV correct
Maximum voltage 36 kV correct
Power rating correct
Number of cores 3 correct
Conductor type Cu correct
Section area correct
Insulation XLPE correct
Number fibre optics correct
Export minimum bend radius (MBR) correct
Burial depth correct
Comments XLPE armoured 36kV 3-core AC cable correct
Number of onshore cables 3 correct
Average length per cable 3.5 km correct
Comments 33kV correct
Array cable length 14.8 km correct
Estimated cable length LogIn
Transmission type (e.g. MVAC) MVAC correct
Nominal voltage 33 kV correct
Maximum voltage 36 kV correct
Burial depth up to 3 m correct
Number of cores 3 correct
Conductor type Cu correct
Section correct
Insulation XLPE correct
Power rating correct
Number of fibre optics correct
Minimum bend radius (MBR) correct
Comments XLPE(cross-linked polyethylene) armoured 36kV 3-core AC cable correct
Homes powered annually 63743 correct
CO2 reduced per year 128825 tonnes correct
SO2 reduced per year 2996 tonnes correct
Expected life 20.0 years correct
Website Visit correct

Call +44 (0)1502 307 037 for more information

Keep on top of the market. Perform analysis. Make informed decisions.

CONTACT US

More information?

Receive monthly updates with our Offshore Windfarm Subscription and gain access to even more detailed information on; cabling, converters, costs, foundations, substations, turbines.

Filter :
123
StatusName
Decommissioned Beatrice Demonstration Beatrice Demonstration
Decommissioned Blyth Blyth
Fully Commissioned Barrow Barrow
Fully Commissioned Burbo Bank Burbo Bank
Fully Commissioned Greater Gabbard Greater Gabbard
Fully Commissioned Gunfleet Sands Gunfleet Sands
Fully Commissioned Gunfleet Sands 3 - Demonstration Project Gunfleet Sands 3 - Demonstration Project
Fully Commissioned Gwynt y Môr Gwynt y Môr
Fully Commissioned Humber Gateway Humber Gateway
Fully Commissioned Hunterston Test Centre - Mitsubishi 7MW (onshore) Hunterston Test Centre - Mitsubishi 7MW (onshore)
Fully Commissioned Hunterston Test Centre - Siemens 6MW (onshore) Hunterston Test Centre - Siemens 6MW (onshore)
Fully Commissioned Hunterston Test Centre (onshore) Hunterston Test Centre (onshore)
Fully Commissioned Inner Dowsing Inner Dowsing
Fully Commissioned Kentish Flats Kentish Flats
Fully Commissioned Kentish Flats Extension Kentish Flats Extension
Fully Commissioned Levenmouth demonstration turbine Levenmouth demonstration turbine
Fully Commissioned Lincs Lincs
Fully Commissioned London Array London Array
Fully Commissioned Lynn Lynn
Fully Commissioned North Hoyle North Hoyle
Fully Commissioned Ormonde Ormonde
Fully Commissioned Rhyl Flats Rhyl Flats
Fully Commissioned Robin Rigg Robin Rigg
Fully Commissioned Scroby Sands Scroby Sands
Fully Commissioned Sheringham Shoal Sheringham Shoal
Fully Commissioned Teesside Teesside
Fully Commissioned Thanet Thanet
Fully Commissioned Walney Phase 1 Walney Phase 1
Fully Commissioned Walney Phase 2 Walney Phase 2
Fully Commissioned Wave Hub Wave Hub
Fully Commissioned West of Duddon Sands West of Duddon Sands
Fully Commissioned Westermost Rough Westermost Rough
Partial Generation/Under Construction Burbo Bank Extension Burbo Bank Extension
Partial Generation/Under Construction Dudgeon Dudgeon
Under Construction Galloper Galloper
Under Construction Race Bank Race Bank
Under Construction Rampion Rampion
Pre-Construction Aberdeen Offshore Wind Farm (EOWDC) Aberdeen Offshore Wind Farm (EOWDC)
Pre-Construction Beatrice Beatrice
Pre-Construction Blyth Offshore Demonstrator Project - Array 2 Blyth Offshore Demonstrator Project - Array 2
Pre-Construction East Anglia ONE East Anglia ONE
Pre-Construction Hornsea Project One Hornsea Project One
Pre-Construction Hywind Scotland Pilot Park Hywind Scotland Pilot Park
Pre-Construction Walney Extension Walney Extension
Consent Authorised Blyth Offshore Demonstrator Project - Array 3A & 4 Blyth Offshore Demonstrator Project - Array 3A & 4
Consent Authorised Dogger Bank - Creyke Beck A Dogger Bank - Creyke Beck A
Consent Authorised Dogger Bank - Creyke Beck B Dogger Bank - Creyke Beck B
Consent Authorised Dogger Bank - Teesside A Dogger Bank - Teesside A
Consent Authorised Dogger Bank - Teesside B Dogger Bank - Teesside B
Consent Authorised Dounreay Trì Dounreay Trì
123
Please LogIn to follow projects
Find quick and easy project and company information with our online search tool

This page is intended to be viewed online and may not be printed without a valid subscription.

Please view this page at http://www.4coffshore.com/windfarms/windfarms.aspx?windfarmID=uk02.