Developers/Owners/Operators (5)

RoleOrganisation 
Developer
correct
Operator

Value: LogIn
correct
Operator-Offshore Transmission correct
Owner correct
Owner-Offshore Transmission correct

Turbines (5)

RoleOrganisation 
Contractor-Heavy Load Logistics(Turbine) correct
Installer-Turbine
MPI Offshore installed the 73 turbines at the site using the MPI Resolution. Installation of the turbines took place in five steps - tower, nacelle and the three rotor blades.
Number of turbines installed: LogIn
correct
Maintenance-Turbine correct
Maintenance-Turbine correct
Manufacturer-Turbine correct

Substations (8)

RoleOrganisation 
Installer-Substation-Topside
The MPI vessel MPI Adventure installed the substation topside at the start of October 2014.
correct
Main Contractor-Onshore Substation
CG Holdings Belgium NV (CG Power Systems Belgium NV)
correct
Main Contractor-Substation
CG Holdings Belgium NV (CG Power Systems Belgium NV)
correct
Maintenance-Substation correct
Manufacturer-Substation-Electrical
CG Holdings Belgium NV (CG Power Systems Belgium NV)
correct
Manufacturer-Substation-Topside
Cofely Fabricom GDF Suez
Client: LogIn
correct
Manufacturer-Substation-Topside correct
Supplier-Crane(Substation)
Palfinger Marine- und Beteilungs-GmbH
correct

Foundations (17)

RoleOrganisation 
Contractor-Grouting(turbines)
Non-Structural foundation skirt grouting.
Number of foundations grouted: LogIn
correct
Designer(Detailed)-Foundation(Substation) correct
Designer(Detailed)-Foundation(Turbine) correct
Installer-Foundation(substation) correct
Installer-Foundation(turbine) correct
Installer-Transition Piece(turbine)
Installation of monopiles and transition pieces
Number of transition pieces installed: LogIn
correct
Manufacturer-Foundation(substation) correct
Manufacturer-Foundation(turbine) correct
Manufacturer-Foundation(turbine) correct
Manufacturer-Foundation-Primary Steel(turbine) correct
Manufacturer-Transition Piece(turbine) correct
Manufacturer-Transition Piece(turbine) correct
Manufacturer-Transition Piece-Primary Steel(turbine) correct
Manufacturer-Transition Piece-Secondary Steel(turbine) correct
Manufacturer-Transition Piece-Secondary Steel(turbine)
Finishing of transition pieces
Number of transition pieces: LogIn
correct
Supplier-Crane(Transition Piece) correct
Supplier-Flanges
Supply of 219 flanges for the transition pieces and monopiles - 73 x (ø4500/4046 x150 mm) plus 73 x (ø4780/3820 x 310 mm) for Transition pieces and 73x (ø4500/3820 x 212 mm) for monopiles. Clients Sif and TAG
correct

Array Cabling (8)

RoleOrganisation 
Installer(LEAD)-Array Cabling
E.ON are installing the array cable directly, using the vessel Atlantic Carrier.
correct
Installer-Array Cabling
Ecosse Subsea Systems
correct
Installer-Array Cabling correct
Installer-Array Cabling correct
Installer-Array Cabling(components) correct
Installer-Cabling(pull-in)
Osiris Marine Services Ltd, part of James Fisher and Sons plc, delivered ROV and cable pull-in solutions.
correct
Manufacturer-Array Cabling correct
Supplier-Cable Protection Systems
Provided M12 and M8 Super Duplex Bolting for the cable protection system. The contract period began in July 2013 and continued until November 2014.
correct

Export Cabling (3)

Met Masts (9)

RoleOrganisation 
Installer(LEAD)-Met Mast correct
Installer-Foundation(met mast) correct
Installer-Met Mast(Equipment install)
Project management and provision of crew for Met Mast installation.
correct
Installer-Tower(met mast) correct
Installer-Transition Piece(met mast) correct
Main Contractor-Met Mast correct
Main Contractor-Met Mast correct
Manufacturer-Met Mast(Tower)
Manufactured 72m Series MET steel lattice Met Mast tower supplied via RADTech.
Value: LogIn
correct
Supplier-MetOcean Equipment
Providing instrumentation, communication, data acquisition, navigation support system, PV-power system, oceanographic system, etc
Value: LogIn
correct

Consultants (9)

RoleOrganisation 
Consultant-EIA correct
Consultant-Legal correct
Consultant-Other correct
Consultant-Other
PMSS - See TÜV SÜD PMSS (Tuv Sud)
correct
Consultant-Other correct
Consultant-Other correct
Consultant-Other
DHI Group
Client: LogIn
correct
Consultant-Other
ICS (Installations) Ltd
Client: LogIn
ICS applied Cable installation equipment concept design, vessel back deck concept and cable installation consultancy between 2011 and 2015.
correct
Consultant-Other correct

Others (28)

RoleOrganisation 
Contractor-Other
Janz Power Services Limited
Client: LogIn
Janz provided senior authorised personnel for the HV Operation between January 2014 - Present (22/01/2015).
correct
Contractor-Other
3sun Ltd
Client: LogIn
correct
Contractor-Route Clearance(ordnance)
Red7Marine Ltd. (Ceased Trading)
Gray Mammoth used for ordnance clearance
correct
Contractor-Route Clearance(PLGR)
Ecosse Subsea Systems
correct
Designer-Other
ABB AS
Client: LogIn
correct
Investor correct
Manufacturer-Other correct
Manufacturer-Other
Fabrication and mobilisation/demobilisation of the MPI Resolution for topside work scopes as well as the installation of Vestas blade racks. Work took place between June 2014 and April 2015.
correct
Port
Port of Sunderland is presently executing a contract to support the cable-lay operation on Eon’s Humber Gateway Windfarm. Port of Sunderland is providing services for the mobilisation of vessels as well as the tran-spooling of cable between vessels
correct
Port correct
Port
Operations and maintenance port.
correct
Port Services correct
Supplier-Hydraulic Hammer
60T IHC Hydrohammer for met mast monopile installation
Number of piles driven in - Not number of foundations: LogIn
correct
Supplier-Other
Supplied foundation ring studs (C&T M72) to the project.
correct
Supplier-Other
MME supplied the cathodic protection by means of sacrificial anodes of the monopiles.
correct
Supplier-Other correct
Supplier-Other
Provision of RTK Navigation Systems used onboard SIDDIS MARINER.
correct
Supplier-Other
Installation and support of Kongsberg HiPAP system onboard ATLANTIC CARRIER.
correct
Supplier-Other correct
Supplier-Other
Ecosse Subsea Systems
Client: LogIn
correct
Supplier-Other
Supplier PPE equipment and consumables
correct
Surveyor-Bird
Seabird Surveys, Marine Mammal Mitigation, Subsea Noise Monitoring, Herring Spawning Monitoring and Suspended Sediment Monitoring. Also Little Tern surveys and land radar surveys. Gardline will provide seabird surveyors, marine mammal observers, passive acoustic monitoring operators, acoustic scientists and metocean scientist.
correct
Surveyor-Geophysical correct
Surveyor-Geophysical
Provided a full geophysical survey.
Value: LogIn
correct
Surveyor-Geophysical correct
Surveyor-Maritime Traffic and Navigation Risk correct
Surveyor-Other correct
Surveyor-UXO correct

Call +44 (0)1502 307 037 for more information

Keep on top of the market. Perform analysis. Make informed decisions.

CONTACT US

Did you know?

You get monthly updates with our Offshore Windfarm Subscription and receive even more detailed information about: turbines costs foundations substations converters cabling

Filter :
123
StatusName
Decommissioned Beatrice Demonstration Beatrice Demonstration
Decommissioned Blyth Blyth
Fully Commissioned Barrow Barrow
Fully Commissioned Burbo Bank Burbo Bank
Fully Commissioned Greater Gabbard Greater Gabbard
Fully Commissioned Gunfleet Sands Gunfleet Sands
Fully Commissioned Gunfleet Sands 3 - Demonstration Project Gunfleet Sands 3 - Demonstration Project
Fully Commissioned Gwynt y Môr Gwynt y Môr
Fully Commissioned Humber Gateway Humber Gateway
Fully Commissioned Hunterston Test Centre - Mitsubishi 7MW (onshore) Hunterston Test Centre - Mitsubishi 7MW (onshore)
Fully Commissioned Hunterston Test Centre - Siemens 6MW (onshore) Hunterston Test Centre - Siemens 6MW (onshore)
Fully Commissioned Hunterston Test Centre (onshore) Hunterston Test Centre (onshore)
Fully Commissioned Inner Dowsing Inner Dowsing
Fully Commissioned Kentish Flats Kentish Flats
Fully Commissioned Kentish Flats Extension Kentish Flats Extension
Fully Commissioned Levenmouth demonstration turbine Levenmouth demonstration turbine
Fully Commissioned Lincs Lincs
Fully Commissioned London Array London Array
Fully Commissioned Lynn Lynn
Fully Commissioned North Hoyle North Hoyle
Fully Commissioned Ormonde Ormonde
Fully Commissioned Rhyl Flats Rhyl Flats
Fully Commissioned Robin Rigg Robin Rigg
Fully Commissioned Scroby Sands Scroby Sands
Fully Commissioned Sheringham Shoal Sheringham Shoal
Fully Commissioned Teesside Teesside
Fully Commissioned Thanet Thanet
Fully Commissioned Walney Phase 1 Walney Phase 1
Fully Commissioned Walney Phase 2 Walney Phase 2
Fully Commissioned Wave Hub Wave Hub
Fully Commissioned West of Duddon Sands West of Duddon Sands
Fully Commissioned Westermost Rough Westermost Rough
Partial Generation/Under Construction Burbo Bank Extension Burbo Bank Extension
Partial Generation/Under Construction Dudgeon Dudgeon
Under Construction Galloper Galloper
Under Construction Race Bank Race Bank
Under Construction Rampion Rampion
Pre-Construction Aberdeen Offshore Wind Farm (EOWDC) Aberdeen Offshore Wind Farm (EOWDC)
Pre-Construction Beatrice Beatrice
Pre-Construction Blyth Offshore Demonstrator Project - Array 2 Blyth Offshore Demonstrator Project - Array 2
Pre-Construction East Anglia ONE East Anglia ONE
Pre-Construction Hornsea Project One Hornsea Project One
Pre-Construction Hywind Scotland Pilot Park Hywind Scotland Pilot Park
Pre-Construction Walney Extension Walney Extension
Consent Authorised Blyth Offshore Demonstrator Project - Array 3A & 4 Blyth Offshore Demonstrator Project - Array 3A & 4
Consent Authorised Dogger Bank - Creyke Beck A Dogger Bank - Creyke Beck A
Consent Authorised Dogger Bank - Creyke Beck B Dogger Bank - Creyke Beck B
Consent Authorised Dogger Bank - Teesside A Dogger Bank - Teesside A
Consent Authorised Dogger Bank - Teesside B Dogger Bank - Teesside B
Consent Authorised Dounreay Trì Dounreay Trì
123
Please LogIn to follow projects
Find quick and easy project and company information with our online search tool

This page is intended to be viewed online and may not be printed without a valid subscription.

Please view this page at http://www.4coffshore.com/windfarms/organisations.aspx?windfarmID=uk10.