Developers/Owners/Operators (7)

RoleOrganisation 
Developer correct
Operator
After the Marubeni Corporation and the UK Green Investment Bank purchased stakes in the company they agreed that DONG would provide operations and maintenance at the site.
correct
Operator-Offshore Transmission correct
Owner correct
Owner
Corporation both purchased 25% stakes in the project. The project will then be run as a joint venture with each shareholder funding and sharing risk on a pro rata basis. The UK Green Investment Bank and the Marubeni corporation are expected to commit GBP 500 million to the construction of the project.
Value: LogIn
correct
Owner
The UK Green Investment Bank and the Marubeni Corporation both purchased 25% stakes in the project. The project will then be run as a joint venture with each shareholder funding and sharing risk on a pro rata basis. The UK Green Investment Bank and the Marubeni corporation are expected to commit GBP 500 million to the construction of the project.
Value: LogIn
correct
Owner-Offshore Transmission
TC Westermost Rough OFTO Limited
TC Westermost Rough OFTO Limited is the licensee entity incorporated by the consortium comprised of Transmission Capital Partners, who Ofgem appointed as the preferred bidder to own and operate the offshore transmission link of the wind farm for the next 20 years, and International Public Partnerships Limited. The transmission assets hold an asset value of £157 million and include the onshore substation, export cables and offshore substation.
Annual Revenue through Tender Revenue Stream (TRS) is £11.3m.

Percentage: LogIn
Value: LogIn
correct

Turbines (5)

RoleOrganisation 
Contractor-Heavy Load Logistics(Turbine) correct
Installer-Turbine correct
Maintenance-Turbine
Dawson Energy, part of the 3Sun Group, undertook the first 500 hour service of a number of Siemens wind turbines at the Westermost Rough Offshore Wind Farm.
correct
Maintenance-Turbine correct
Manufacturer-Turbine
Siemens will install the 6MW model based on the framework agreement with Dong Energy on 19/07/2012, which states it will supply 300 offshore turbines of 6 MW, giving a total capacity of 1800MW in the period 2014-2017
Nominal Capacity (MW): LogIn
correct

Substations (4)

Foundations (13)

RoleOrganisation 
Designer(Detailed)-Foundation(Substation) correct
Designer(Detailed)-Foundation(Turbine)
Ramboll provided detailed design for a total of 41 turbine location, although only 35 were required for the wind farm.
Number of turbines: LogIn
correct
Installer-Foundation(substation) correct
Installer-Foundation(turbine) correct
Installer-Transition Piece(turbine)
Responsible for installing transition piece elements.
Number of transition pieces installed: LogIn
correct
Manufacturer-Foundation(pre-fabricated pipes) correct
Manufacturer-Foundation(substation) correct
Manufacturer-Foundation(turbine) correct
Manufacturer-Foundation-Primary Steel(turbine) correct
Manufacturer-Foundation-Secondary Steel(substation) correct
Manufacturer-Transition Piece(turbine) correct
Manufacturer-Transition Piece-Primary Steel(turbine) correct
Manufacturer-Transition Piece-Secondary Steel(turbine)
2014 -
Transition Piece:
Length: ± 22m

Number of transition pieces: LogIn
correct

Array Cabling (5)

RoleOrganisation 
Installer-Array Cabling
Technip chartered the Normand Pioneer for the simultaneous lay, cutting and jetting burial of the array cables using the CBT1100 trencher from a carousel onboard the vessel..
Cable Length km: LogIn
correct
Installer-Cabling(pull-in) correct
Maintenance-Array Cable correct
Manufacturer-Array Cabling correct
Supplier-Cable Protection Systems correct

Export Cabling (3)

RoleOrganisation 
Installer-Export Cabling correct
Maintenance-Export Cable correct
Manufacturer-Export Cabling correct

Met Masts (1)

Consultants (9)

RoleOrganisation 
Consultant-EIA correct
Consultant-Financial correct
Consultant-Financial correct
Consultant-Financial correct
Consultant-Financial
SgurrEnergy Ltd
correct
Consultant-Other correct
Consultant-Other
OWC’s scope of work includes preparation of cable repair and maintenance strategies for six Transmission Capital Services (TCS) managed assets, development of contract strategies for future maintenance contracts and the preparation of specification and tender packages for the supply of services under the above mentioned maintenance contracts. The six TCS assets are TC Barrow OFTO Limited, TC Gunfleet Sands OFTO Limited, TC Ormonde OFTO Limited, TC Robin Rigg OFTO Limited, TC Lincs OFTO Limited, and TC Westermost Rough Limited.
correct
Consultant-Other correct
Consultant-Other
PMSS - See TÜV SÜD PMSS (Tuv Sud)
correct

Others (17)

RoleOrganisation 
Contractor-Other
Hughes SSE announced that after a successful tender submission with energy giants Dong Energy, the company has been awarded a subsea inspection framework covering Dong Energy’s European windfarms.
correct
Contractor-Route Clearance(PLGR)
Ecosse Subsea Systems
Client: LogIn
correct
Installer-Other correct
Maintenance-Other correct
Manufacturer-Other correct
Manufacturer-Other correct
Port Services correct
Supplier-Helicopter
UNI-FLY A/S
Client: LogIn
correct
Supplier-Hydraulic Hammer
S-2000 Hydrohammer
Pile Diameter - 5.75m
Year - 2014
Turbine Monopiles

Number of piles driven in - Not number of foundations: LogIn
correct
Supplier-Other
Supply of Safety Equipment, PPE, SOLAS Transits Suits, SOLAS Life Jackets, Personal Locating Beacons, Working at Height Equipment. PPE Inspection and Servicing of Equipment.
correct
Supplier-Other
Grontmij
Client: LogIn
correct
Supplier-Other
Scaffolding Access & Encapsulated Enclosures for Cable Pulling & Cable Jointing Works with a work period of May 2014 to August 2015.
Value: LogIn
correct
Surveyor-Geophysical correct
Surveyor-Geophysical
Performed geophysical survey.
correct
Surveyor-Geotechnical correct
Surveyor-Geotechnical
MMT AB
Client: LogIn
MMT will begin geotechnical surveys at the end of November 2012, lasting approximately 3 months
correct
Surveyor-Maritime Traffic and Navigation Risk
Maritime Traffic Surveys and Navigation Risk Assessment
correct

Call +44 (0)1502 307 037 for more information

Keep on top of the market. Perform analysis. Make informed decisions.

CONTACT US

Did you know?

You get monthly updates with our Offshore Windfarm Subscription and receive even more detailed information about: turbines costs foundations substations converters cabling

Filter :
123
StatusName
Decommissioned Beatrice Demonstration Beatrice Demonstration
Decommissioned Blyth Blyth
Fully Commissioned Barrow Barrow
Fully Commissioned Burbo Bank Burbo Bank
Fully Commissioned Greater Gabbard Greater Gabbard
Fully Commissioned Gunfleet Sands Gunfleet Sands
Fully Commissioned Gunfleet Sands 3 - Demonstration Project Gunfleet Sands 3 - Demonstration Project
Fully Commissioned Gwynt y Môr Gwynt y Môr
Fully Commissioned Humber Gateway Humber Gateway
Fully Commissioned Hunterston Test Centre - Mitsubishi 7MW (onshore) Hunterston Test Centre - Mitsubishi 7MW (onshore)
Fully Commissioned Hunterston Test Centre - Siemens 6MW (onshore) Hunterston Test Centre - Siemens 6MW (onshore)
Fully Commissioned Hunterston Test Centre (onshore) Hunterston Test Centre (onshore)
Fully Commissioned Inner Dowsing Inner Dowsing
Fully Commissioned Kentish Flats Kentish Flats
Fully Commissioned Kentish Flats Extension Kentish Flats Extension
Fully Commissioned Levenmouth demonstration turbine Levenmouth demonstration turbine
Fully Commissioned Lincs Lincs
Fully Commissioned London Array London Array
Fully Commissioned Lynn Lynn
Fully Commissioned North Hoyle North Hoyle
Fully Commissioned Ormonde Ormonde
Fully Commissioned Rhyl Flats Rhyl Flats
Fully Commissioned Robin Rigg Robin Rigg
Fully Commissioned Scroby Sands Scroby Sands
Fully Commissioned Sheringham Shoal Sheringham Shoal
Fully Commissioned Teesside Teesside
Fully Commissioned Thanet Thanet
Fully Commissioned Walney Phase 1 Walney Phase 1
Fully Commissioned Walney Phase 2 Walney Phase 2
Fully Commissioned Wave Hub Wave Hub
Fully Commissioned West of Duddon Sands West of Duddon Sands
Fully Commissioned Westermost Rough Westermost Rough
Partial Generation/Under Construction Burbo Bank Extension Burbo Bank Extension
Partial Generation/Under Construction Dudgeon Dudgeon
Under Construction Galloper Galloper
Under Construction Race Bank Race Bank
Under Construction Rampion Rampion
Pre-Construction Aberdeen Offshore Wind Farm (EOWDC) Aberdeen Offshore Wind Farm (EOWDC)
Pre-Construction Beatrice Beatrice
Pre-Construction Blyth Offshore Demonstrator Project - Array 2 Blyth Offshore Demonstrator Project - Array 2
Pre-Construction East Anglia ONE East Anglia ONE
Pre-Construction Hornsea Project One Hornsea Project One
Pre-Construction Hywind Scotland Pilot Park Hywind Scotland Pilot Park
Pre-Construction Walney Extension Walney Extension
Consent Authorised Blyth Offshore Demonstrator Project - Array 3A & 4 Blyth Offshore Demonstrator Project - Array 3A & 4
Consent Authorised Dogger Bank - Creyke Beck A Dogger Bank - Creyke Beck A
Consent Authorised Dogger Bank - Creyke Beck B Dogger Bank - Creyke Beck B
Consent Authorised Dogger Bank - Teesside A Dogger Bank - Teesside A
Consent Authorised Dogger Bank - Teesside B Dogger Bank - Teesside B
Consent Authorised Dounreay Trì Dounreay Trì
123
Please LogIn to follow projects
Find quick and easy project and company information with our online search tool

This page is intended to be viewed online and may not be printed without a valid subscription.

Please view this page at http://www.4coffshore.com/windfarms/organisations.aspx?windfarmID=uk34.