First monopile installed at Borkum Riffgrund 2

4C Offshore | Tom Russell
By: Tom Russell 07/03/2018 Jan de Nul
Jan de NulJan De Nul's jack-up installation vessel Vole au Venthas installed the first monopile foundation at the Borkum Riffgrund 2 offshore wind farm.

A total of 36 monopiles foundations will be installed at the site, each consisting of a monopile, transition piece and anode cage. Manufactured by Steelwind in Nordenham, the components are being shipped to Eemshaven by Wagenborg.

Borkum Riffgrund 2 will also include 20 jacket foundations featuring suction bucket technology. During installation, the vessel will lower the foundations onto the seabed, where the buckets are used to create negative pressure and attach the foundation to the ground.

The suction buckets are designed to reduce noise emissions and help protect the surrounding sea life. The technology was first tested by Ørsted at the Borkum Riffgrund 1 site, situated nearby Borkum Riffgrund 2.

Borkum Riffgrund 2 is owned by Ørsted and Global Infrastructure Partners and will feature 56 MHI Vestas V164-8.0 MW turbines with full commissioning expected by the end of 2019.

The wind turbine array will be one of the largest in Germany with a capacity of 450MW. it is expected to supply electricity to up to 460,000 households per year.

For more information please follow the links provided. Alternatively you can
click here for 4C Offshore's interactive map.

Premium

4C Offshore Premium, our most popular subscription, gives you full access to use the 4C Offshore WebApp which includes exclusive offshore wind, transmission and vessel reports, news and downloads.

Request a 30 minute Demo

Trending News!