Gemini
600 MW Consent Authorised Netherlands

"We are using the reports extensively and have built an updated business plan."

Haico Halbesma, Oceanteam Shipping


Latest Windfarm News
Donald Trump invites Alex Salmond to play golf…
Aberdeen Press and Journal
US billionaire Donald Trump and the first minister have locked horns several times over the years, not least in a bitter row over controversial plans for an offshore windfarm at Aberdeen Bay. Earlier this year, Mr Trump halted work on a planned hotel and golf ...
Source: news.google.com
20/09/2014 09:39:44

Orbis cements German link
reNews
UK-based innovation centre OrbisEnergy has signed a memorandum of understanding with German wind energy agency WAB for collaborative working on North Sea offshore projects. The agreement was signed during a visit by an 11-strong delegation from ...
Source: news.google.com
19/09/2014 15:28:28

Research and Markets: Feasibility Study of Wind Power in India-2014: A Guide ...
Business Wire (press release)
... Types of Generators, Electrical Dynamics of Wind Turbine Model, Modern Trends in Wind Farms, Offshore Wind Turbine Development, Development of Off-shore Wind Equipment Technologies, Simplified Off-shore Wind Farm, A Study of Indian Wind Energy ...
Source: news.google.com
19/09/2014 14:47:34

Swire jack-up joins Gemini squad
reNews
Swire Blue Ocean has signed a deal to provide an installation vessel for Van Oord at the 600MW Gemini offshore wind farm off the Netherlands. The company operates Pacific Orca and Pacific Osprey (pictured) and will help tackle the 150 foundations and ...
Source: news.google.com
19/09/2014 14:16:33

Spanish wind turbine manufacturer issues new shares
Olive Press
The sale is estimated to be worth more than €250 million at current market prices, equivalent to 9.99% of the group's capital. Gamesa and France's Areva previously agreed a joint venture with the intention of getting 20% of Europe's offshore wind farm projects ...
Source: news.google.com
19/09/2014 13:15:40

More British wind energy capacity online
UPI.com
The U.K. Green Investment Bank in March acquired a 10 percent stake in the Gwynt y Mor offshore wind farm from Germany's RWE Innogy for $360 million. That project is the largest offshore wind farm under construction in Europe, with more than 500 MW of ...
Source: news.google.com
19/09/2014 11:12:07

Swedish steel for floating platforms
SteelGuru
Swedish steel specialist SSAB is entering into an agreement with Hexicon AB to develop far off shore wind farm platforms. The combined technology will offer advantages within the market for renewable energy. A first demonstration unit is planned for ...
Source: news.google.com
19/09/2014 05:25:04

Vattenfall to scrap Yttre Stengrund
reNews
Vattenfall has abandoned plans to repower its 10MW Yttre Stengrund offshore wind farm in the Kalmar Sound, Sweden. The company told local media in its home country that it is planning to decommission the project, which was broung online in 2001 and ...
Source: news.google.com
18/09/2014 17:30:53

Global Offshore Wind Market To Reach 40 GW By 2020
CleanTechnica
Offshore wind power is increasingly being explored for its high yield, due to stronger and more consistent winds compared to onshore, and the scope that this provides for the construction of large-scale projects,” said Swati Singh, GlobalData's Analyst ...
Source: news.google.com
18/09/2014 16:41:35

Isle of Man picks 1GW team
reNews
The Isle of Man says it has decided on preferred bidders for its proposed 1GW offshore wind farm and for more than one tidal energy project in its waters. However, Ken Milne, senior manager for energy policy at the Isle of Man Department for Economic ...
Source: news.google.com
18/09/2014 16:31:00




4C Offshore Ltd. has achieved certification to the ISO 9001, ISO 14001 and OHSAS 18001 standards for quality, environmental, and health & safety management.
map not available
Developers/Owners/Operators
RoleOrganisation 
Developer correct
Main Contractor-EPC correct
Operator
correct
Owner correct
Owner correct
Owner correct
Owner correct
Project Details for Gemini
General Information Name Gemini correct
Other names Buitengaats & ZeeEnergie, BARD-Nederland Offshore, GWS Offshore NL1, 64 (ID assigned by authority), correct
Country name Netherlands correct
Region Friesland correct
Comments Northland Power detailed that Gemini will be developed in two 300MW sites (Buitengaats & ZeeEnergie) in an investor presentation released on the 16th July 2014 for a total cost of 2.8 billion EUR. The capital will be covered by approximately 70% senior debt, 7% junior debt, 15-16% equity and 7-8% pre-completion revenues.

A separate grid company will own, maintain and operate the offshore transformer station(s), export cabling and all other grid related assets, except for the infield cabling.

Financing breakdown total financing is around EUR 2.8 billion. EUR 500 million - shareholders: Northland Power, Siemens, Van Oord & HVC. EUR 200 million - subordinated loans: Northland Power, Canada & PKA, Denmark. EUR 2 billion - bank loans: ABN AMRO Bank, the Netherlands, Bank Nederlandse Gemeenten, the Netherlands, Banco Santander, Spain, Bank of Montreal, Canada, Bank of Tokyo-Mitsubishi UFJ, Japan, BNP Paribas, France, CaixaBank, Spain, CIBC World Markets, Canada, Deutsche Bank, Germany, EIB. Europese Investeringsbank, Luxembourg, Natixis, France, Sumitomo Mitsui Banking Corporation, Japan, EKF, Denmark, Euler Hermes, Germany, Export Development Canada & Delcredeire|Ducroire, Belgium.
correct
Round (or category) Round 2 (NL) correct
Development status Consent Authorised correct
Comments on the status Awarded SDE subsidies from the Dutch government, in total EUR 4.4 billion. correct
Power & Turbines Notice any Errors? You can keep this an open resource by submitting corrections!
Project Capacity 600 MW correct
Turbine Model SWT-4.0-130 (Siemens) correct
Turbine Capacity 4 MW correct
Number of Turbines 150 correct
Total Turbine Height 155 m correct
Hub Height 90.00 m correct
Rotor Diameter 130 m correct
Foundation Grounded: Monopile correct
Windspeed 10 Year Mean Wind Speed (2000-2009) Available online now
Detailed wind speed data 6 hr/day/month historic data
Costs Stated Project Cost EUR(mill) 2700.00 correct
Location & Environment Sea name North Sea correct
Centre latitude 54.036° correct
Centre longitude 5.963° correct
Area 68 km2 correct
Depth range (Chart Datum) 32 m - 34 m correct
Depth range stated by developer 28 m - 36 m correct
Distance From Shore (reported) 85 km correct
Distance From Shore (computed from centre) 70.2 km correct
Ports Installation base Eemshaven, BOW Terminal - Vlissingen (storage and transfers of foundations) correct
Ops and maintenance Eemshaven correct
Grid Converter platforms None correct
Offshore transformers Gemini Substation 1, Gemini Substation 2 correct
Grid connection point Oude Schild correct
Cable landing point Oude Schild correct
Export Cables
Please note that export cables connect the offshore transformer (substation) to either; shore or an offshore HVAC-HVDC converter station for onward transmission via HVDC cabling. Please see the converters page for planned converter stations and transmission cables.

The export cable length does not generally include the onshore component. The exception is when the onshore substation is close to shore.
Number of Export Cables 2 correct
Average length per cable 110 km correct
Transmission type (e.g. HVAC) HVAC correct
Nominal voltage 220 kV correct
Maximum voltage correct
Power rating correct
Number of cores correct
Conductor type Al correct
Section Area correct
Insulation correct
Number fibre optics correct
Export minimum bend radius (MBR) correct
Burial depth correct
Comments Export voltage 250-300kV correct
Onshore Cables Number of onshore cables 6 correct
Average length per cable 0.3 km correct
Comments 250kV-300kV, assumed 2x3 in one trench correct
Array Cables Array cable length 105 km correct
Estimated cable length LogIn
Transmission type (e.g. MVAC) correct
Nominal voltage 33 kV correct
Maximum voltage correct
Burial depth correct
Number of cores correct
Conductor type correct
Section correct
Insulation correct
Power rating correct
Number of fibre optics correct
Minimum bend radius (MBR) correct
Comments Over 100km of array cable correct
Benefits Homes powered annually 391404 correct
CO2 reduced per year 791028 tonnes correct
SO2 reduced per year 18396 tonnes correct
Expected life 20.0 years correct
Other Website Visit correct