Last week, Engie Fabricom and Iemnants completed the load out of the 1180t offshore substation topside and associated 985t jacket foundation. Both structures will head to the site for installation by the Stanislav Yudin this month. A total of 32 MHI Vestas 8MW turbines will be installed at the Burbo Bank extension site, significantly boosting the capacity of the existing 90MW Burbo Bank project in Liverpool Bay. The extension project will cover an area of 40km2 and will be the first large-scale wind farm to deploy the new MHI Vestas 8.0 MW turbine.
For more information, please follow the links provided. Alternatively you can view the project on our interactive map.
Premium
4C Offshore Premium, our most popular subscription, gives you full access to use the 4C Offshore WebApp which includes exclusive offshore wind, transmission and vessel reports, news and downloads.