DateEventDescription 
LogIn Event Type: Operation - Fully Commissioned
Fully Commissioned The park will be made fully operational, following trial operations and testing, by October LogIn.
Source: LogIn
correct
LogIn Event Type: Operation - Generating Power
Generating Power Beatrice Offshore Wind Farm Limited will trigger its Contracts for Difference (CfD) agreement in two phases: the second totalling 336MW of capacity at an Allocation Strike Price of £140/MWh. The Target Commissioning Window (TCW) start date set by the CfD and signed with the Low Carbon Contracts Company (LCCC) is the 31st March LogIn. However, the generator has proposed a start date of the 15th April LogIn to trigger the fifteen year contract, in which it will be required to have commissioned 80% of its Installed Capacity Estimate (ICE) of 336MW.
Source: LogIn
correct
LogIn Event Type: Installation - Grid Connection Available
Grid Connection Available National Grid will provide the final 294MW of grid connection, which is expected to be available by April LogIn and bring the total connection capacity to 588MW.
Source: LogIn
correct
LogIn Event Type: Operation - Generating Power
Generating Power Beatrice Offshore Wind Farm Limited will trigger its Contracts for Difference (CfD) agreement in two phases: the first totalling 252MW of capacity at an Allocation Strike Price of £140/MWh. The Target Commissioning Window (TCW) start date set by the CfD and signed with the Low Carbon Contracts Company (LCCC) is the 31st March LogIn. However, the generator has proposed a start date of the 15th November LogIn to trigger the fifteen year contract, in which it will be required to have commissioned 80% of its Installed Capacity Estimate (ICE) of 252MW.
The TCW is open for a period of one year; commissioning after the final day results in an according reduction in the period of subsidy support. Furthermore, commissioning of at least 85% of the ICE is required by the 'long-stop' date two years after the close of the TCW, otherwise the counterparty body will terminate the CfD without compensation.

Source: LogIn
correct
LogIn Event Type: Installation - Turbine Installation
Turbine Installation Seaway Heavy Lifting will implement its heavy-lift vessels Stanislav Yudin and Oleg Strashnov to complete turbine installation activities from July LogIn to March LogIn, according to an indicative construction timetable.
Source: LogIn
correct
LogIn Event Type: Installation - Foundation Installation
Foundation Installation The second wave of jacket foundations will be placed from May LogIn, according to an indicative construction timetable. Foundation installation activities will wrap up by August LogIn.
Source: LogIn
correct
LogIn Event Type: Engineering - Production and Procurement
Production and Procurement Burntisland Fabrications will deliver the last 16 of its 26 jacket foundations by April LogIn.
Source: LogIn
correct
LogIn Event Type: Installation - Grid Connection Available
Grid Connection Available National Grid will provide the first 294MW of grid connection, which is expected to be available by April LogIn.
Source: LogIn
correct
LogIn Event Type: Installation - Cable installation
Cable installation Siem Offshore will commence installation of the inter-array cables from November LogIn, according to an indicative construction timetable. Works will continue until approximately September LogIn. The Aimery and Moxie Duo will be used.
Source: LogIn
correct
LogIn Event Type: Installation - Offshore Substation
Offshore Substation Installation of the new Siemens' Offshore Transformer Modules (OTMs) is expected to take place in Q4 LogIn according to an indicative construction timetable.
It will take around two days to install each of the Offshore Transformer Module (OTM) topsides, and 45hrs for each jacket.

Source: LogIn
correct
LogIn Event Type: Installation - Cable installation
Cable installation Nexans will commence installation of the export cable system from September LogIn, according to an indicative construction timetable. Works will continue until approximately May LogIn.
Source: LogIn
correct
LogIn Event Type: Engineering - Production and Procurement
Production and Procurement The first of Bladt's jacket foundations are expected to be delivered in Q3 LogIn.
Source: LogIn
correct
LogIn Event Type: Engineering - Production and Procurement
Production and Procurement Burntisland Fabrications will deliver the first 10 of its 26 jacket foundations by August LogIn.
Source: LogIn
correct
LogIn Event Type: Installation - Foundation Installation
Foundation Installation Installation of the foundation piles is anticipated for April LogIn and will last through until the end of January LogIn. The first wave of jacket foundations will be placed from August LogIn through to December LogIn, according to an indicative construction timetable. Piled foundations will be installed in the seabed followed by installation of the jackets. The process will take approximately 45hrs at each location. Pile drilling may also be used if the seabed structure requires it.
Source: LogIn
correct
11-Mar-2017 Event Type: Pre-Construction - Seabed Preparation
Construction - Seabed Preparation For a duration of 7 days the Siem Ruby will perform boulder clearance operations with the SCAR plough on the wind farm.
Source: LogIn
correct
18-Jan-2017 Event Type: Pre-Construction - Seabed Preparation
Construction - Seabed Preparation SSE and the Navy disposed of a 1,000lb explosive device that was discovered at the site. Through the Unexploded Ordnance Survey a total of three items were found. Two were returned to shore for safe disposal and one was handed over to the Navy.
Source: LogIn
correct
2017 Event Type: Installation - Other
Other Work on the Operations and Maintenance (O&M) site based in two historic Thomas Telford buildings in Wick will start in January 2017, subject to planning consent (as of October 2016). A recent event held at Wick's local community saw residents welcome the idea of restoring the buildings to their originally intended maritime use.
Source: LogIn
correct
02-Dec-2016 Event Type: Engineering - Production and Procurement
Production and Procurement Smulders completed the first section for the 28 jacket foundations it will be constructing.
Source: LogIn
correct
30-Nov-2016 Event Type: Engineering - Production and Procurement
Production and Procurement Burntisland Fabrications has begun fabrication of the jacket foundations at its Arnish facility.
Source: LogIn
correct
06-Oct-2016 Event Type: Installation - ONSHORE Construction Starts
ONSHORE Construction Starts An important milestone was reached as onshore construction began with the breaking of ground near Portgordon in Moray. Enabling works are now underway at the main onshore construction compound near the cable landfall point for the route to Blackhillock.
Source: LogIn
correct
Sep-2016 Event Type: Planning - Site Investigation
Site Investigation The vessel Fugro Helmet, Fugro Frontier and Meridian commenced an UXO survey. The survey is expected to last a minimum of 8 weeks.
Source: LogIn
correct
19-Aug-2016 Event Type: Planning - Other Approval
Other Approval Low Carbon Contracts Company (LCCC) announced that all CFDs and Investment Contracts under LCCC management have now passed the milestone requirement. The projects must have demonstrated that contracts are in place to buy all material equipment for the generation and export of electricity or by spending 10% of the expected development and construction costs.
Source: LogIn
correct
27-Jul-2016 Event Type: Planning - Site Investigation
Site Investigation An unexploded ordnance survey along the export cable route began. The work was carried out by Clinton Marine Survey (on behalf of Nexans). The survey was expected to take 4 weeks.
Source: LogIn
correct
24-May-2016 Event Type: Planning - Financing Agreement
Financing Agreement As part of reaching financial close, the European Investment Bank (EIB) has approved a £525 million 19 year long-term loan supported by new European Fund for Strategic Investments (ESFI), the heart of the Investment Plan for Europe, and is the single largest offered in offshore wind by the EIB.
Source: LogIn
correct
23-May-2016 Event Type: Planning - Financial Close
Financial Close The £2.6 billion Beatrice Offshore Windfarm Ltd (BOWL) project has been given the green light for construction by owners SSE (40%), Copenhagen Infrastructure Partners (CIP) (35%) and SDIC Power (25%) after the project reached Financial Close. The project will be one of the largest private investments ever made in Scottish infrastructure.
Source: LogIn
correct
25-Feb-2016 Event Type: Other - Ownership Change
Ownership Change Repsol sold their 25% stake in Beatrice to SDIC Power of China. They also sold 100% of their shares in the Inch Cape project to the same company. The total value of these transactions was €238m.
Source: LogIn
correct
2016 Event Type: Installation - ONSHORE Construction Starts
ONSHORE Construction Starts Onshore transmission contract is expected to start in 2016 subject to a positive Final Investment Decision.
Source: LogIn
correct
02-Nov-2015 Event Type: Planning - Other Approval
Other Approval Beatrice Offshore Windfarm Ltd has been granted permission to develop the onshore transmission works. The onshore transmission works associated with the wind farm will comprise of approximately 20km of underground cable from a landfall point to the west of Portgordon and a new substation which the cable will connect to, located adjacent to the existing substation at Blackhillock near Keith.
Source: LogIn
correct
Sep-2015 Event Type: Other -
Other Draft decommissioning prepared for informal consultation; eventually the decommissioning programme will require approval by the Secretary of State, Department of Energy and Climate Change.
Source: LogIn
correct
03-Aug-2015 Event Type: Planning - Site Investigation
Site Investigation The vessels FV ANTARIES and FV PLEIADES carried out marine survey operations. The survey will last for eight weeks.
Source: LogIn
correct
12
Add new windfarm events, providing approximate date etc. Possible events include consent submission, approval, installation, generating power etc.

Call +44 (0)1502 307 037 for more information

Keep on top of the market. Perform analysis. Make informed decisions.

CONTACT US

Did you know?

You get monthly updates with our Offshore Windfarm Subscription and receive even more detailed information about: turbines costs foundations substations converters cabling

Filter :
123
StatusName
Decommissioned Beatrice Demonstration Beatrice Demonstration
Decommissioned Blyth Blyth
Fully Commissioned Barrow Barrow
Fully Commissioned Burbo Bank Burbo Bank
Fully Commissioned Greater Gabbard Greater Gabbard
Fully Commissioned Gunfleet Sands Gunfleet Sands
Fully Commissioned Gunfleet Sands 3 - Demonstration Project Gunfleet Sands 3 - Demonstration Project
Fully Commissioned Gwynt y Môr Gwynt y Môr
Fully Commissioned Humber Gateway Humber Gateway
Fully Commissioned Hunterston Test Centre - Mitsubishi 7MW (onshore) Hunterston Test Centre - Mitsubishi 7MW (onshore)
Fully Commissioned Hunterston Test Centre - Siemens 6MW (onshore) Hunterston Test Centre - Siemens 6MW (onshore)
Fully Commissioned Hunterston Test Centre (onshore) Hunterston Test Centre (onshore)
Fully Commissioned Inner Dowsing Inner Dowsing
Fully Commissioned Kentish Flats Kentish Flats
Fully Commissioned Kentish Flats Extension Kentish Flats Extension
Fully Commissioned Levenmouth demonstration turbine Levenmouth demonstration turbine
Fully Commissioned Lincs Lincs
Fully Commissioned London Array London Array
Fully Commissioned Lynn Lynn
Fully Commissioned North Hoyle North Hoyle
Fully Commissioned Ormonde Ormonde
Fully Commissioned Rhyl Flats Rhyl Flats
Fully Commissioned Robin Rigg Robin Rigg
Fully Commissioned Scroby Sands Scroby Sands
Fully Commissioned Sheringham Shoal Sheringham Shoal
Fully Commissioned Teesside Teesside
Fully Commissioned Thanet Thanet
Fully Commissioned Walney Phase 1 Walney Phase 1
Fully Commissioned Walney Phase 2 Walney Phase 2
Fully Commissioned Wave Hub Wave Hub
Fully Commissioned West of Duddon Sands West of Duddon Sands
Fully Commissioned Westermost Rough Westermost Rough
Partial Generation/Under Construction Burbo Bank Extension Burbo Bank Extension
Partial Generation/Under Construction Dudgeon Dudgeon
Under Construction Galloper Galloper
Under Construction Race Bank Race Bank
Under Construction Rampion Rampion
Pre-Construction Aberdeen Offshore Wind Farm (EOWDC) Aberdeen Offshore Wind Farm (EOWDC)
Pre-Construction Beatrice Beatrice
Pre-Construction Blyth Offshore Demonstrator Project - Array 2 Blyth Offshore Demonstrator Project - Array 2
Pre-Construction East Anglia ONE East Anglia ONE
Pre-Construction Hornsea Project One Hornsea Project One
Pre-Construction Hywind Scotland Pilot Park Hywind Scotland Pilot Park
Pre-Construction Walney Extension Walney Extension
Consent Authorised Blyth Offshore Demonstrator Project - Array 3A & 4 Blyth Offshore Demonstrator Project - Array 3A & 4
Consent Authorised Dogger Bank - Creyke Beck A Dogger Bank - Creyke Beck A
Consent Authorised Dogger Bank - Creyke Beck B Dogger Bank - Creyke Beck B
Consent Authorised Dogger Bank - Teesside A Dogger Bank - Teesside A
Consent Authorised Dogger Bank - Teesside B Dogger Bank - Teesside B
Consent Authorised Dounreay Trì Dounreay Trì
123
Please LogIn to follow projects
Find quick and easy project and company information with our online search tool

This page is intended to be viewed online and may not be printed without a valid subscription.

Please view this page at http://www.4coffshore.com/windfarms/events.aspx?windfarmID=uk53.