DateEventDescription 
LogIn Event Type: Operation - Service Agreement Expires
Service Agreement Expires The five-year OEM service agreement with Vestas will expire.
Source: LogIn
correct
07-Sep-2016 Event Type: Other -
Other E.ON announced the sale of the transmission assets to a consortium of Balfour Beatty Investments and Equitix. The companies were selected by Ofgem in September 2015 as the preferred bidder. The final sale price for the transmission assets is £162.9m.
Source: LogIn
correct
31-May-2016 Event Type: Operation - Performance Monitoring
Performance Monitoring The first full year of generation saw Humber Gateway generate almost 854,400MWh of electricity by the end of May 2016.
Source: LogIn
correct
27-Dec-2015 Event Type: Decommissioning - Met Mast
Met Mast The MPI Adventure removed the met mast foundation. The monopile was removed using an internal high pressure water jet cutter to 2m below seabed level.
Source: LogIn
correct
30-Sep-2015 Event Type: Other -
Other E.ON officially opened the wind farm today as the Minister of State for Energy and Climate Change, Andrea Leadsom launched the project.
Source: LogIn
correct
09-Aug-2015 Event Type: Inspection, Maintenance & Repair - Turbine
Turbine DBB Wind Server was on site in the first week of August to replace the gearbox of turbine D10.
Source: LogIn
correct
30-Jun-2015 Event Type: Installation - Other
Other Fugro's vessel Saltire placed rock bags on multiple array cable ends. Primary locations were C06, C07, C08, C09, C10, Secondary locations were D10, E10, F09, G08,
H07. This operation lasted for approximately 31 days.

Source: LogIn
correct
31-May-2015 Event Type: Operation - Fully Commissioned
Fully Commissioned Humber Gateway was fully energised, two months ahead of schedule. The entire wind farm is generating electricity.
Source: LogIn
correct
23-Apr-2015 Event Type: Installation - Turbine Installation
Turbine Installation E.On had installed the final turbine at the site and has 44 of the 73 turbines generating power.
Source: LogIn
correct
07-Apr-2015 Event Type: Installation - Cable installation
Cable installation Osiris completes Cougar-XT ROV inspections and transition piece cable pull-in work.
Source: LogIn
correct
24-Feb-2015 Event Type: Installation - Turbine Installation
Turbine Installation A total of 58 turbines have been installed, with 6 producing power.
Source: LogIn
correct
24-Feb-2015 Event Type: Installation - Cable installation
Cable installation Cable installations were completed before this date.
Source: LogIn
correct
16-Feb-2015 Event Type: Operation - Generating Power
Generating Power During the week starting 16/02/2015 Humber Gateway produced power for the first time.
Source: LogIn
correct
Feb-2015 Event Type: Other -
Other Work is progressing to commission the first of the two substation transformers and circuits and is expected to finish in February.
Source: LogIn
correct
23-Jan-2015 Event Type: Installation - Turbine Installation
Turbine Installation As of this week 52 turbines have been installed.
Source: LogIn
correct
27-Oct-2014 Event Type: Installation - Turbine Installation
Turbine Installation A representative at E.ON confirmed they are working on installing the project's 36th turbine.
Source: LogIn
correct
15-Oct-2014 Event Type: Installation - Offshore Substation
Offshore Substation The offshore substation was ready to install in Q1 2014, though the substation was finally installed mid October 2014 by the vessel MPI Adventure.
Source: LogIn
correct
Sep-2014 Event Type: Installation - Foundation Installation
Foundation Installation All of the foundations and transition pieces were installed in September 2014.
Source: LogIn
correct
20-Aug-2014 Event Type: Planning - Tender Process
Tender Process A short list of 4 bidders to own and operate the transmission links at Humber Gateway and Westermost Rough, has been announced. The winning OFTO for each project will be announced in 2015. The shortlist consists of Balfour Beatty Equitix, Blue Transmission Consortium, Mari energy Transmission and Transmission Capital Partners.
Source: LogIn
correct
04-Aug-2014 Event Type: Installation - Foundation Installation
Foundation Installation The remaining 12 monopiles will leave TAG Energy's fabrication yard by the end of August.
Source: LogIn
correct
Aug-2014 Event Type: Installation - Foundation Installation
Foundation Installation 61 of 73 foundations had been installed.
Source: LogIn
correct
Aug-2014 Event Type: Installation - Turbine Installation
Turbine Installation two turbines had been installed.
Source: LogIn
correct
19-Jul-2014 Event Type: Installation - Cable installation
Cable installation Array cable installation has started.
Source: LogIn
correct
Jul-2014 Event Type: Installation - Foundation Installation
Foundation Installation The second phase of foundation and transition piece installation is under full swing with the MPI Discovery and MPI Resolution on site.
Source: LogIn
correct
22-May-2014 Event Type: Installation - Cable installation
Cable installation Array cable installation vessel on site undergoing trials. Initial start date was 03/2014.
Source: LogIn
correct
16-May-2014 Event Type: Installation - Foundation Installation
Foundation Installation Problems have been encountered with MPI Resolution's jacking system, which will impact the foundation installation schedule. The MPI Resolution left Humber Gateway on this date and did not return to the site until the 3rd July 2014.
Source: LogIn
correct
21-Apr-2014 Event Type: Installation - Foundation Installation
Foundation Installation The second phase of the foundation installation started with the MPI Resolution beginning to load the foundations and start installation when weather permits. The remaining 49 foundations will be installed in this phase.
Source: LogIn
correct
Apr-2014 Event Type: Installation - Grid Connection Available
Grid Connection Available 220 MW of Transmission Entry Capacity allocated into National Grid is set for completion (originally expected 31st October 2013).
Source: LogIn
correct
26-Feb-2014 Event Type: Planning - Tender Process
Tender Process Ofgem launched new tender Round for transmission system at Humber Gateway. The transmission system will include an offshore substation platform, offshore and onshore AC export cables and an onshore substation.
Source: LogIn
correct
Feb-2014 Event Type: Installation - Other
Other Ofgem will launch Tender Round Three (TR3), which will include the sale of Humber Gateway's transmission assets. Westermost Rough will also see the sale of its transmission assets for a combined worth of up to £400 million.
Source: LogIn
correct
12
Add new windfarm events, providing approximate date etc. Possible events include consent submission, approval, installation, generating power etc.

Call +44 (0)1502 307 037 for more information

Keep on top of the market. Perform analysis. Make informed decisions.

CONTACT US

Did you know?

You get monthly updates with our Offshore Windfarm Subscription and receive even more detailed information about: turbines costs foundations substations converters cabling

Filter :
123
StatusName
Decommissioned Beatrice Demonstration Beatrice Demonstration
Decommissioned Blyth Blyth
Fully Commissioned Barrow Barrow
Fully Commissioned Burbo Bank Burbo Bank
Fully Commissioned Greater Gabbard Greater Gabbard
Fully Commissioned Gunfleet Sands Gunfleet Sands
Fully Commissioned Gunfleet Sands 3 - Demonstration Project Gunfleet Sands 3 - Demonstration Project
Fully Commissioned Gwynt y Môr Gwynt y Môr
Fully Commissioned Humber Gateway Humber Gateway
Fully Commissioned Hunterston Test Centre - Mitsubishi 7MW (onshore) Hunterston Test Centre - Mitsubishi 7MW (onshore)
Fully Commissioned Hunterston Test Centre - Siemens 6MW (onshore) Hunterston Test Centre - Siemens 6MW (onshore)
Fully Commissioned Hunterston Test Centre (onshore) Hunterston Test Centre (onshore)
Fully Commissioned Inner Dowsing Inner Dowsing
Fully Commissioned Kentish Flats Kentish Flats
Fully Commissioned Kentish Flats Extension Kentish Flats Extension
Fully Commissioned Levenmouth demonstration turbine Levenmouth demonstration turbine
Fully Commissioned Lincs Lincs
Fully Commissioned London Array London Array
Fully Commissioned Lynn Lynn
Fully Commissioned North Hoyle North Hoyle
Fully Commissioned Ormonde Ormonde
Fully Commissioned Rhyl Flats Rhyl Flats
Fully Commissioned Robin Rigg Robin Rigg
Fully Commissioned Scroby Sands Scroby Sands
Fully Commissioned Sheringham Shoal Sheringham Shoal
Fully Commissioned Teesside Teesside
Fully Commissioned Thanet Thanet
Fully Commissioned Walney Phase 1 Walney Phase 1
Fully Commissioned Walney Phase 2 Walney Phase 2
Fully Commissioned Wave Hub Wave Hub
Fully Commissioned West of Duddon Sands West of Duddon Sands
Fully Commissioned Westermost Rough Westermost Rough
Partial Generation/Under Construction Burbo Bank Extension Burbo Bank Extension
Partial Generation/Under Construction Dudgeon Dudgeon
Under Construction Galloper Galloper
Under Construction Race Bank Race Bank
Under Construction Rampion Rampion
Pre-Construction Aberdeen Offshore Wind Farm (EOWDC) Aberdeen Offshore Wind Farm (EOWDC)
Pre-Construction Beatrice Beatrice
Pre-Construction Blyth Offshore Demonstrator Project - Array 2 Blyth Offshore Demonstrator Project - Array 2
Pre-Construction East Anglia ONE East Anglia ONE
Pre-Construction Hornsea Project One Hornsea Project One
Pre-Construction Hywind Scotland Pilot Park Hywind Scotland Pilot Park
Pre-Construction Walney Extension Walney Extension
Consent Authorised Blyth Offshore Demonstrator Project - Array 3A & 4 Blyth Offshore Demonstrator Project - Array 3A & 4
Consent Authorised Dogger Bank - Creyke Beck A Dogger Bank - Creyke Beck A
Consent Authorised Dogger Bank - Creyke Beck B Dogger Bank - Creyke Beck B
Consent Authorised Dogger Bank - Teesside A Dogger Bank - Teesside A
Consent Authorised Dogger Bank - Teesside B Dogger Bank - Teesside B
Consent Authorised Dounreay Trì Dounreay Trì
123
Please LogIn to follow projects
Find quick and easy project and company information with our online search tool

This page is intended to be viewed online and may not be printed without a valid subscription.

Please view this page at http://www.4coffshore.com/windfarms/events.aspx?windfarmID=uk10.