DateEventDescription 
LogIn Event Type: Operation - Service Agreement Expires
Service Agreement Expires The five-year OEM service agreement will expire.
Source: LogIn
correct
12-Jan-2017 Event Type: Inspection, Maintenance & Repair - Turbine
Turbine The transformer retrofit campaign headed by Siemens added a flange between the sensors in the transformers and the oil expansion tank within the turbines. This resolved the issue of air pockets developing in the transformer tanks tripping the oil level sensors. Around a third of the turbines were retrofitted in 2016 with the rest to be retrofitted in the opening months of 2017.
Siemens stated: "The retrofit does not require a jack-up vessel and addresses a specific and limited design issue for this transformer. There are no implications for the 6/7MW turbine configuration in general."

Source: LogIn
correct
Nov-2016 Event Type: Inspection, Maintenance & Repair - Turbine
Turbine A transformer retrofit campaign headed by Siemens commenced around November, following the results of an investigation that was undertaken in the summer. The retrofit consists of fitting an expansion tank to better regulate oil levels across variable temperatures within the turbines.
Source: LogIn
correct
21-Sep-2016 Event Type: Installation - Other
Other SmartWind Technologies have installed an advanced radar system that will collect three-dimensional data on the wind flow at the project. The project is the first of its kind in the world. The BEACon project was awarded to SmartWind Technologies in February 2015.
Source: LogIn
correct
2016 Event Type: Operation - Environmental and Seabed Monitoring
Environmental and Seabed Monitoring During 2016, two of SmartWind Technologies' dual-Doppler radar systems will be installed at the wind farm. They will produce high-resolution dynamic maps of the wind flow through and around the wind farm. The radars will be in operation for approximately 18 months.
Source: LogIn
correct
Jul-2015 Event Type: Other -
Other The official inauguration took place. The guest of honour was Lord Haskins.
Source: LogIn
correct
26-May-2015 Event Type: Operation - Fully Commissioned
Fully Commissioned Full power output was achieved at the wind farm. Westermost Rough was built at a cost 15-20% below the initially announced FID budget.
Source: LogIn
correct
29-Apr-2015 Event Type: Installation - Final Testing
Final Testing Over half of the turbines were generating electricity to the grid.
Source: LogIn
correct
27-Mar-2015 Event Type: Installation - Turbine Installation
Turbine Installation The last of the 35 turbines was lifted into position by the specialist jack-up vessel SEA CHALLENGER on 27th March 2015.
Source: LogIn
correct
09-Mar-2015 Event Type: Other -
Other The MMO approved an operational Marine Licence that allows for the recovery and repair of up to ten inter array cables. The duration of an individual repair is likely to be outlined as follows:
1. Onshore mobilisation: one month
2. Execution of repair work scope: one month
3. Cable reburial and survey: one month.

Source: LogIn
correct
29-Jan-2015 Event Type: Installation - Turbine Installation
Turbine Installation SEA CHALLENGER installed the 18th turbine.
Source: LogIn
correct
14-Jan-2015 Event Type: Installation - Other
Other Ecosse Subsea Systems completed a 72 day campaign for boulder clearance and seabed preparation. The subsea engineering specialist cleared almost 50,000 boulders and other obstructions from 33 routes spread over a distance of 40km.
Source: LogIn
correct
27-Dec-2014 Event Type: Installation - Turbine Installation
Turbine Installation After a month's pause, SEA CHALLENGER will now resume installation of the final 25 turbines and has returned to the project site with turbines 11-15.
Source: LogIn
correct
22-Dec-2014 Event Type: Installation - Turbine Installation
Turbine Installation The SEA CHALLENGER completed its third load out of turbines 11 to 15 in Esbjerg. It was also announced DONG will use a helicopter to help bolster O&M at this wind farm: this is the first wind farm that DONG will be using a helicopter strategy. Four of the ten installed turbines are now producing power.
Source: LogIn
correct
27-Nov-2014 Event Type: Installation - Cable installation
Cable installation Installation of the array cables has been completed.
Source: LogIn
correct
25-Nov-2014 Event Type: Installation - Turbine Installation
Turbine Installation A total of ten turbines were installed by this date.
Source: LogIn
correct
19-Oct-2014 Event Type: Installation - Turbine Installation
Turbine Installation SEA CHALLENGER returned to the project site to continue installation of the next batch of turbines.
Source: LogIn
correct
08-Sep-2014 Event Type: Operation - Generating Power
Generating Power The project produced power for the first time. This is the first time a Siemens 6MW turbine has produced power commercially.
Source: LogIn
correct
23-Aug-2014 Event Type: Installation - Turbine Installation
Turbine Installation SEA CHALLENGER has left the project site for a period of approximately two months after installing the first five Siemens 6MW turbines. A two-month build pause was forced to iron out any teething problems with the new turbine technology. Originally all 35 turbines were to be installed by the end of November, yet this date will now be pushed back.
Source: LogIn
correct
20-Aug-2014 Event Type: Planning - Tender Process
Tender Process A short list of 4 bidders to own and operate the transmission links at Humber Gateway and Westermost Rough, has been announced. The winning OFTO for each project will be announced in 2015. The shortlist consists of Balfour Beatty Equitix, Blue Transmission Consortium, Mari energy Transmission and Transmission Capital Partners.
Source: LogIn
correct
15-Aug-2014 Event Type: Installation - Turbine Installation
Turbine Installation The first Siemens 6MW turbine was installed.
Source: LogIn
correct
11-Aug-2014 Event Type: Other -
Other The Green Investment Bank (GIB) and Marubeni Corporation have refinanced their 50% stake (they own 25% each). They originally purchased the stake for £500m and in this refinancing they secured £370m in limited recourse senior debt with a consortium of lenders.
Source: LogIn
correct
08-Aug-2014 Event Type: Installation - Turbine Installation
Turbine Installation A2SEA's SEA CHALLENGER arrives on site to commence turbine installation.
Source: LogIn
correct
04-Aug-2014 Event Type: Installation - Turbine Installation
Turbine Installation Installation of the 35x 6MW Siemens turbines is soon to be underway as A2SEA's SEA CHALLENGER leaves Esbjerg in Denmark loaded with the first batch of turbine components.
Source: LogIn
correct
Jul-2014 Event Type: Installation - Grid Connection Available
Grid Connection Available 205MW Grid connection available according to the National Grid (was originally 02-Apr-14).
Source: LogIn
correct
12-Jun-2014 Event Type: Installation - Cable installation
Cable installation The Normand Pioneer and Toisa Voyager have arrived on site to begin the array cable installation, following delays from original scheduling for April 2014.
Source: LogIn
correct
03-Jun-2014 Event Type: Installation - Offshore Substation
Offshore Substation The offshore substation was installed.
Source: LogIn
correct
25-May-2014 Event Type: Installation - Foundation Installation
Foundation Installation GeoSea completed the installation of the foundations. Installation vessel INNOVATION was loaded in Aalborg (Denmark) with 5 sets of monopiles and transition pieces which it then transported across the North Sea to be installed immediately at the off shore site, a distance of 500 nautical miles. The foundations weighed between 500T and 810T with a diameter of 6.5m, and the transition pieces weighed 367T.
Source: LogIn
correct
22-May-2014 Event Type: Installation - Offshore Substation
Offshore Substation Seaway Heavy Lifting vessel Stanislav Yudin arrived on site to install the offshore substation.
Source: LogIn
correct
27-Mar-2014 Event Type: Installation - Offshore Substation
Offshore Substation The completed substation topside was moved from its pre- assembly site to an area where it will be loaded onto a barge.
Source: LogIn
correct
12
Add new windfarm events, providing approximate date etc. Possible events include consent submission, approval, installation, generating power etc.

Call +44 (0)1502 307 037 for more information

Keep on top of the market. Perform analysis. Make informed decisions.

CONTACT US

Did you know?

You get monthly updates with our Offshore Windfarm Subscription and receive even more detailed information about: turbines costs foundations substations converters cabling

Filter :
123
StatusName
Decommissioned Beatrice Demonstration Beatrice Demonstration
Decommissioned Blyth Blyth
Fully Commissioned Barrow Barrow
Fully Commissioned Burbo Bank Burbo Bank
Fully Commissioned Greater Gabbard Greater Gabbard
Fully Commissioned Gunfleet Sands Gunfleet Sands
Fully Commissioned Gunfleet Sands 3 - Demonstration Project Gunfleet Sands 3 - Demonstration Project
Fully Commissioned Gwynt y Môr Gwynt y Môr
Fully Commissioned Humber Gateway Humber Gateway
Fully Commissioned Hunterston Test Centre - Mitsubishi 7MW (onshore) Hunterston Test Centre - Mitsubishi 7MW (onshore)
Fully Commissioned Hunterston Test Centre - Siemens 6MW (onshore) Hunterston Test Centre - Siemens 6MW (onshore)
Fully Commissioned Hunterston Test Centre (onshore) Hunterston Test Centre (onshore)
Fully Commissioned Inner Dowsing Inner Dowsing
Fully Commissioned Kentish Flats Kentish Flats
Fully Commissioned Kentish Flats Extension Kentish Flats Extension
Fully Commissioned Levenmouth demonstration turbine Levenmouth demonstration turbine
Fully Commissioned Lincs Lincs
Fully Commissioned London Array London Array
Fully Commissioned Lynn Lynn
Fully Commissioned North Hoyle North Hoyle
Fully Commissioned Ormonde Ormonde
Fully Commissioned Rhyl Flats Rhyl Flats
Fully Commissioned Robin Rigg Robin Rigg
Fully Commissioned Scroby Sands Scroby Sands
Fully Commissioned Sheringham Shoal Sheringham Shoal
Fully Commissioned Teesside Teesside
Fully Commissioned Thanet Thanet
Fully Commissioned Walney Phase 1 Walney Phase 1
Fully Commissioned Walney Phase 2 Walney Phase 2
Fully Commissioned Wave Hub Wave Hub
Fully Commissioned West of Duddon Sands West of Duddon Sands
Fully Commissioned Westermost Rough Westermost Rough
Partial Generation/Under Construction Burbo Bank Extension Burbo Bank Extension
Partial Generation/Under Construction Dudgeon Dudgeon
Under Construction Galloper Galloper
Under Construction Race Bank Race Bank
Under Construction Rampion Rampion
Pre-Construction Aberdeen Offshore Wind Farm (EOWDC) Aberdeen Offshore Wind Farm (EOWDC)
Pre-Construction Beatrice Beatrice
Pre-Construction Blyth Offshore Demonstrator Project - Array 2 Blyth Offshore Demonstrator Project - Array 2
Pre-Construction East Anglia ONE East Anglia ONE
Pre-Construction Hornsea Project One Hornsea Project One
Pre-Construction Hywind Scotland Pilot Park Hywind Scotland Pilot Park
Pre-Construction Walney Extension Walney Extension
Consent Authorised Blyth Offshore Demonstrator Project - Array 3A & 4 Blyth Offshore Demonstrator Project - Array 3A & 4
Consent Authorised Dogger Bank - Creyke Beck A Dogger Bank - Creyke Beck A
Consent Authorised Dogger Bank - Creyke Beck B Dogger Bank - Creyke Beck B
Consent Authorised Dogger Bank - Teesside A Dogger Bank - Teesside A
Consent Authorised Dogger Bank - Teesside B Dogger Bank - Teesside B
Consent Authorised Dounreay Trì Dounreay Trì
123
Please LogIn to follow projects
Find quick and easy project and company information with our online search tool

This page is intended to be viewed online and may not be printed without a valid subscription.

Please view this page at http://www.4coffshore.com/windfarms/events.aspx?windfarmID=uk34.