Maryland
Thornton Bank phase III
110.7 MW Under Construction Belgium
Updated weekly to include the latest news, your feedback and other data.
38 Countries, 1317 Windfarms, 9090 Stakeholders, 4282 Events, 824 Vessels, 153 Turbines NEW, 42 Ports,
Filter Projects by Country
Featured Ports
Featured Port
Lyness - Fendercare Marine , United Kingdom Image of <%# Eval("PortName") %> Maximum Trenched Depth: 7 m
Entrance Width:
Spring Tidal Range:
Quay Length: 190 m
Quay Loading Capability:
Land for Development: 3 ha
More details...



Who is generating power
Who's Generating Power?
1.  United Kingdom - 3321.2000 MW
2.  Denmark - 871.4800 MW
3.  China - 559.5000 MW
More...
Whose Turbines are Generating?
Whose Turbines are Generating?
1.  Siemens Wind Power A/S (Siemens AG) - 3084.8000 MW
2.  Vestas Offshore A/S (Vestas Wind Systems A/S) - 1401.1200 MW
3.  REpower Systems AG (Suzlon Energy Limited) - 434.5000 MW
Loading Map
Equipment Available for Charter
Statistics for Thornton Bank phase III
General Information Name Thornton Bank phase III correct
Other names Zone 1, C-Power 2 correct
Country name Belgium correct
Region Vlaanderen correct
Comments Phase 3 comprises 18 turbines in Area A only (SW Part)
Phases 2 and 3 will install one export cable and one offshore substation.
The project cost reflects all 3 phases.
correct
Round (or category) correct
Development status Under Construction correct
Comments on the status See events table for latest status correct
Power & Turbines Notice any Errors? You can keep this an open resource by submitting corrections!
Project Capacity 110.7 MW correct
Turbine Model 6M (REpower) correct
Turbine Capacity 6.15 MW correct
Number of Turbines 18 correct
Total Turbine Height correct
Hub Height correct
Rotor Diameter 126 m correct
Foundation Grounded: Jacket correct
Windspeed 10 Year Mean Wind Speed (2000-2009) Available online now
Detailed wind speed data 6 hr/day/month historic data
Costs Stated Project Cost EUR(mill) 487.50 correct
Location & Environment Sea name North Sea correct
Centre latitude 51.540° correct
Centre longitude 2.921° correct
Area 7 km2 correct
Depth range (Chart Datum) 11 m - 20 m correct
Depth range stated by developer 12 m - 28 m correct
Distance From Shore (reported) 26 km correct
Distance From Shore (computed from centre) 28.1 km correct
Ports Installation base Oostende correct
Ops and maintenance Oostende correct
Grid Converter platforms None correct
Offshore transformers 1 correct
Grid connection point 'Slijkens' Bredene correct
Cable landing point Bredene correct
Export Cables
Please note that export cables connect the offshore transformer (substation) to either; shore or an offshore HVAC-HVDC converter station for onward transmission via HVDC cabling. Please see the converters page for planned converter stations and transmission cables.

The export cable length does not generally include the onshore component. The exception is when the onshore substation is close to shore.
Number of Export Cables correct
Average length per cable correct
Transmission type (e.g. HVAC) HVAC correct
Nominal voltage 150 kV correct
Maximum voltage 170 kV correct
Power rating correct
Number of cores 3 correct
Conductor type Cu correct
Section correct
Insulation correct
Number fibre optics correct
Minimum bend radius (MBR) correct
Burial depth correct
Comments 3-phase 150kV submarine cable correct
Onshore Cables (new) Number of onshore cables 2 correct
Average length per cable 3 km correct
Comments 170kV correct
Array Cables Array cable length 34 km correct
Estimated cable length In purchased database
Transmission type (e.g. MVAC) MVAC correct
Nominal voltage 33 kV correct
Maximum voltage 36 kV correct
Burial depth correct
Number of cores 3 correct
Conductor type Cu correct
Section correct
Insulation correct
Power rating correct
Number of fibre optics correct
Minimum bend radius (MBR) correct
Comments correct
Benefits Homes powered annually 61898 correct
CO2 reduced per year 125095 tonnes correct
SO2 reduced per year 2909 tonnes correct
Expected life correct
Other Website Visit correct

Events on Thornton Bank phase III
12
DateTypeDescriptionSourceCorrect
Subscribe
Event Type: Operation - Generating Power                                                                                                                                                                                                                                   Operation - Generating Power
The project could be in production from Q3 Subscribe Subscribe correct
Mar-2013
Event Type: Installation - Turbine Installation                                                                                                                                                                                                                            Installation - Turbine Installation
Installation of the remaining 18 turbines is scheduled to begin in March 2013. Visit correct
17-Sep-2012
Event Type: Installation - Cable installation                                                                                                                                                                                                                              Installation - Cable installation
Array cable installation for Area A is complete. The burial of these cables started on 9/08/2012 and all the cable strings between the offshore transformer station and the wind turbines got a first burial pass. The surveys of the burial depths are complete and where necessary some remedial burial works will be executed. Visit correct
28-Jun-2012
Event Type: Installation - Cable installation                                                                                                                                                                                                                              Installation - Cable installation
Array cable installation for Area A started on 28/06/2012. Visit correct
16-Jun-2012
Event Type: Installation - Cable installation                                                                                                                                                                                                                              Installation - Cable installation
All infield cables for area A are loaded on the ship in Karlskrona ready for shipment to Zeebruge Visit correct
29-May-2012
Event Type: Installation - Foundation Installation                                                                                                                                                                                                                         Installation - Foundation Installation
All foundations in Area A successfully installed and grouted. All 24 jackets in area A were installed in 3 months with the completion date 2 months ahead of the master schedule. Visit correct
02-Mar-2012
Event Type: Installation - Foundation Installation                                                                                                                                                                                                                         Installation - Foundation Installation
The Rambiz started installation of foundations in Area A. Visit correct
21-Aug-2011
Event Type: Installation - Foundation Installation                                                                                                                                                                                                                         Installation - Foundation Installation
All pin-piling for the jacket foundations completed. 196 piles driven into the sea bed in 4 and a half months. Visit correct
Apr-2011
Event Type: Installation - Offshore Construction Starts                                                                                                                                                                                                                    Installation - Offshore Construction Starts
Foundation piling started in April in area A. Steel piles of 40-50m were driven into the seabed by a hammer installation mounted on the jack up platform Buzzard. Visit correct
23-Dec-2010
Event Type: Planning - Financing Agreement                                                                                                                                                                                                                                 Planning - Financing Agreement
Eneco signed power purchase agreement for the generated electricity. Visit correct
12

Please click to add windfarm events via this link, providing approximate date etc. Possible events include consent submission, approval, installation, generating power etc.
Be the first to comment on Thornton Bank phase III offshore wind farm Please note, your comment will take 1 hour to appear.

Your Name * :  
Web Site (optional) : http://  
Comment * :  
* required