Ørsted commissions Borssele 1&2

4C Offshore | Tom Russell
By: Tom Russell 27/11/2020 Ørsted
Ørsted has fully commissioned the Borssele 1&2 offshore wind farm. The wind farm has a capacity of 752 MW, making it the largest offshore wind farm in the Netherlands.

Ørsted won rights to the
Borssele 1&2 site in July 2016, with an average bid strike price, excluding transmission costs, of EUR 72.70/MWh for the first 15 years of the project's operation. The project consists of 94 Siemens Gamesa Renewable Energy SG 8.0-167 DD turbines,. It is located 23 km off the coast of Zeeland (Westkappele), and is expected to provide power to over 500,000 households annually.

Henrik Poulsen, CEO and President of Ørsted, says: "This is an important milestone for the green transformation and for Ørsted. We're proud that we've commissioned our first offshore wind farm in the Netherlands, who is among the global front runners in the energy transition. With Borssele 1 & 2 as the first step, we wish to make a significant contribution to the Dutch transition from fossil to renewable energy. We're proud that we completed this large-scale clean energy project on time and within budget during the COVID-19 pandemic, while maintaining our focus on health and safety."

Steven Engels, General Manager Benelux at Ørsted, says: "It's great that we now can deliver enough green electricity to power one million Dutch households. Ørsted has delivered what it promised back in 2016, when we won the tender with a ground-breaking bid price. Realising the first project of the large-scale offshore wind roll out programme in the Netherlands is an important milestone for the Dutch energy transition. I'd like to thank the Dutch national and regional governments and so many other stakeholders who have helped us achieve this result. Zeeland has welcomed us with open arms, which provides an excellent starting point for our operations out of Vlissingen for many years to come. Moreover, it's a good basis for future projects around industry decarbonization in the region, such as the renewable hydrogen project that we announced with Yara."


Flemming Thomsen, Ørsted's Senior Programme Director for Borssele 1 & 2 says: "Together with our suppliers, our construction team has successfully installed this wind farm at high quality in less than nine months. By introducing additional health and safety measures offshore as well as onshore, we were able to continue construction during a global pandemic. We're grateful and proud of the result delivered and pleased to witness the commissioning of Borssele 1 & 2."


For more information on offshore wind farms worldwide, click here.