BOEM completes environmental review for Vineyard Wind

4C Offshore | Tom Russell
By: Tom Russell 08/03/2021 BOEM

The Bureau of Ocean Energy Management (BOEM) has completed the environmental analysis of the proposed
Vineyard Wind 1 offshore wind project.

Vineyard Wind 1, an 800 MW offshore wind farm to be located 15 miles off the coast of Martha’s Vineyard, is slated to be the first commercial scale offshore wind farm in the United States. It will consist of 84 turbines, each with a 9.5 MW capacity, and is expected meet the energy needs of over 400,000 homes and businesses.

Vineyard is aiming to have the project operational by 2024. The project is being developed by Vineyard Wind LLC based in New Bedford, Massachusetts. The company is 50 percent owned by Copenhagen Infrastructure Partners (CIP) and 50 percent by Avangrid Renewables.


“Offshore energy development provides an opportunity for us to work with Tribal nations, communities, and other ocean users to ensure all decisions are transparent and utilize the best available science,”
said BOEM Director Amanda Lefton. “We appreciate everyone’s participation in the process and look forward to continuing to work with stakeholders on the future analysis of offshore wind projects.”


Later this week, BOEM will publish a Notice of Availability for the Final Environmental Impact Statement (EIS) in the Federal Register, which analyses the potential environmental impacts of making a decision on Vineyard Wind’s Construction and Operation Plan.  


On June 12, 2020, as a result of comments received during the National Environmental Policy Act process and in coordination with cooperating agencies, the Draft EIS was supplemented with additional analysis. Additional areas of analysis included reasonably foreseeable effects from an expanded cumulative activities scenario for offshore wind development, previously unavailable fishing data, a new transit lane alternative, and changes since publication of the Draft EIS to the proposed project.


Following a 45-day comment period and five virtual public meetings, BOEM incorporated comments received on the Draft EIS and the supplemental analysis into the Final EIS.  


BOEM is working with the appropriate parties to finalise the Section 106 process, consistent with the National Historic Preservation Act, and to issue a record of decision whether to approve, disapprove, or approve with modifications the proposed project.


The U.S. Army Corps of Engineers and the National Marine Fisheries Service will sign this joint record of decision for their respective authorization decisions.


For more information on offshore wind farms worldwide, click here. You can also view projects worldwide on 4C Offshore's interactive map.