Cadeler to replace Wind Osprey crane

4C Offshore | Tom Russell
By: Tom Russell 17/06/2021 Cadeler A/S
Cadeler A/S has exercised an option to replace the main crane on its jack-up wind turbine installation vessel Wind Osprey by Q1/2024. It will be conducted in conjunction with the crane replacement on Wind Orca.

In December last year, Cadeler A/S contracted NOV to upgrade Wind Orca with a new and improved crane that meets future offshore market demands for installation vessels. Within this contract Cadeler A/S had an option to replace the main crane of
Wind Ospreywhich has now been called.

The crane replacement on
Wind Ospreyis scheduled to be initiated in Q4 2023, and will be completed in conjunction with the crane replacement on Wind Orca, benefitting from the synergies of both projects. The replacement is scheduled for completion in Q1/2024 and will be ready in time for the next generation of wind turbines.

Mikkel Gleerup, CEO of Cadeler A/S, said: “We are pleased to confirm that we have called the option to replace the crane on Wind Osprey, which was included in the contract made with NOV in December of last year. We will thus deliver on our promise to keep our current fleet of vessels ready for future demands that call for even larger cranes with higher specifications, which will ultimately benefit both our clients and the transition to renewable energy.”


For more information on installation and maintenance of major offshore wind farm components, click here.

Premium

4C Offshore Premium, our most popular subscription, gives you full access to use the 4C Offshore WebApp which includes exclusive offshore wind, transmission and vessel reports, news and downloads.

Request a 30 minute Demo

Trending News!