DEME Offshore lays DolWin6 cable

4C Offshore | Tom Russell
By: Tom Russell 13/07/2021 DEME Group
DEME Offshore has installed the DolWin6 High Voltage DC (HVDC) cable in the North Sea, deploying its DP3 vessel Living Stone. This is the first time a cable laying vessel has installed cables while powered on LNG, reducing emissions.

Living Stonepicked up the cables directly from the Nexans manufacturing facility in Halden, Norway at the beginning of June and transported them to the offshore site in the German Bight. The vessel has two turntables so it is ideally suited for installing bundled HVDC cables. The HVDC cable pair was bundled together with the fibre optic cable on board Living Stone and seamlessly installed.

DolWin6 has a transmission capacity of 900 MW and is owned and operated by transmission system operator TenneT. The HVDC cable runs from several offshore wind farms in Germany via Norderney to German mainland.

Bart De Poorter, General Manager DEME Offshore Renewables, commented: “We are pleased to see another campaign successfully concluded by our cable installation vessel ‘Living Stone’. Carrying out the project on LNG is another major milestone, highlighting once more the unrivalled technical capabilities of ‘Living Stone’ and its crew.”

The project's offshore converter platform, DolWin kappa, is currently being built in a shipyard in Cárdiz (Spain). It will be shipped to the North Sea in 2022. It will be used to transmit energy generated by nearby offshore wind farms to the onshore grid.


For more information on offshore wind farms worldwide, click here.