4C Offshore Empowering Intelligence

EDS HV scores contracts for three Danish project

4C Offshore | Tom Russell
By: Tom Russell 10/07/2020 EDS HV
EDS HV Group has secured two new contracts with Vattenfall for high voltage network commissioning and safety management at three Danish wind farms: Kriegers Flak and Vesterhav Nord and Syd.

EDS HV Group will also be offering full management of all Senior Authorised Persons (SAPs) on-site at all three wind farms. In addition to the commissioning scope, EDS HV Group will be offering full High Voltage safety management. Work commenced in June 2020, with
Kriegers Flak scheduled to be in operation by the end of 2021 at the latest, and Vesterhav Nord and Syd scheduled to be in operation by the end of 2023 at the latest.

The 605 MW
Kriegers Flak project will be Denmark’s largest offshore wind farm and is located in the Baltic sea. It will become a part of the new 400 MW interconnector between Denmark and Germany, with a capacity to cover the annual electricity consumption of approximately 600,000 Danish households. It will see the installation of 72 turbines in total, each with a height of up to 188 metres and a weight up to 800 tonnes.

Vesterhav Nord and Syd will have a combined capacity of 344 MW and will supply electricity to the grid in the West Jutland region. Vattenfall secured permits for the two Vesterhav wind areas in 2016 for 47.5 øre/kWh (€63.8/MWh). They are expected to be commissioned in 20203.

David Orr, Operations Manager, EDS HV Group, said: "It’s a rarity in our industry for a contract to be directly awarded but it is testament to the good relationship we have with Vattenfall and their confidence in us. We’re on the critical path of getting the wind farm energised and commissioned and if that’s delayed by even one or two days this can incur huge costs. I believe we offer a commissioning service over and above everyone else in the industry, we bring in experienced SAPs, we bring in HV engineers, we manage the whole process end to end across the HV grid from the first energization of turbines to offshore substations getting the wind farm operational quickly and safely. It means the responsibility is on us and the commissioning manager is reducing risk by having us in their corner. It’s why Vattenfall turned to us for this work. We’ve delivered for them before and we will do it again.”


Morten Jochimsen, Commissioning Manager, Vattenfall, said: “The good relationship Vattenfall have had with EDS over the last couple of projects was key when deciding to continue with them on our next three Danish wind farms. The support and guidance from EDS has really been valuable for Vattenfall in Commissioning our wind farms safely. The service we receive from EDS is hard to find anywhere else in the industry and the fact that they can supply the “whole” package and be flexible, both regarding electrical safety and commissioning, has really been a key factor for Vattenfall in choosing EDS to supply us with SAPs for Kriegers Flak and the Vesterhav Projects.”

Ryan Henderson, Managing Director of EDS HV Group added: “Experienced SAPs can be hard to get hold of, so having an extensive pool of SAPs means that we can get people on site quickly.  Combining that with superb project management means that we can be agile and adapt to the project schedule, helping the commissioning managers to avoid delays, avoid penalties, and ultimately bring an asset online and get it generating energy and income. Vattenfall can rely on EDS, it’s why they trust us with such a critical phase of the wind farm lifecycle.”