DateEventDescription 
LogIn Event Type: Operation - Service Agreement Expires
Service Agreement Expires The five-year OEM service agreement is set to expire.
Source: LogIn
correct
05-Dec-2016 Event Type: Inspection, Maintenance & Repair - Foundation
Foundation CWind has undertaken inspections of the monopiles, scour protection and cables at a number of locations at the wind farm. CWind used its V8 Ocean Modules Inspection Class ROV.
Source: LogIn
correct
23-Nov-2016 Event Type: Inspection, Maintenance & Repair - Turbine
Turbine MPI's vessel, MPI Resolution, has been contracted to carry out the first gearbox exchange on the wind farm. The scope of work includes the exchange of a single gearbox, accommodation and supporting crane duties. The MPI Resolution arrived on site on 23/11/2016 and left on 25/11/2016.
Source: LogIn
correct
04-Feb-2016 Event Type: Operation - Generating Power
Generating Power The full 302MW of capacity is now operational, including the additional 14MW harvested from a software upgrade of the Siemens turbines.
Source: LogIn
correct
02-Feb-2016 Event Type: Other -
Other E.ON announced it has upgraded the wind farm's capacity from 288MW to 302MW. A new software solution from Siemens allows the wind farm to harvest more energy when the wind is at its strongest.
Source: LogIn
correct
Feb-2016 Event Type: Decommissioning - Met Mast
Met Mast During February 2016 the met mast was dismantled at the project. The met mast provided 10 years of data on wind conditions, currents and waves.
Source: LogIn
correct
22-Oct-2015 Event Type: Operation - Fully Commissioned
Fully Commissioned All 80 turbines were connected to the grid. The project was completed on time and on schedule.
Source: LogIn
correct
10-Sep-2015 Event Type: Installation - Turbine Installation
Turbine Installation MPI Adventure installed the last blade at the wind farm earlier in the week.
Source: LogIn
correct
22-Jun-2015 Event Type: Installation - Grid Connection Available
Grid Connection Available HelWin 2 was completed meaning Amrumbank West has a fully operational grid connection. Amrumbank West has an available grid capacity of 303MW.
Source: LogIn
correct
15-Jun-2015 Event Type: Installation - Array Cable Installation
Array Cable Installation The remaining 65 submarine array cables will be completed by the end of Q2 2015.
Source: LogIn
correct
02-May-2015 Event Type: Inspection, Maintenance & Repair - Foundation
Foundation The MPI Enterprise entered the site to carry out works on two newly installed but damaged foundations making extensive repairs and modifications.
Source: LogIn
correct
29-Apr-2015 Event Type: Operation - Generating Power
Generating Power The first turbine is transmitting power to the substation, then on towards the Converter Platform HelWin2; this electricity then travels 85km to shore.
Source: LogIn
correct
10-Apr-2015 Event Type: Installation - Turbine Installation
Turbine Installation 17 turbines installed (Estimated).
Source: LogIn
correct
22-Mar-2015 Event Type: Installation - Foundation Installation
Foundation Installation The last foundation was installed as MPI Discovery left the site.
Source: LogIn
correct
11-Feb-2015 Event Type: Installation - Turbine Installation
Turbine Installation The first turbine at Amrumbank West was installed in early February 2015. Installation of turbines was initially scheduled for October 2014. Carrier vessels from the Port of Esbjerg transport the components for seven turbines at a time; E.ON has also chartered a hotel ship for employees to work for 14 day periods at the site and reduce transit times.
Immediately after the installation of the components, the turbines are prepared for operation. Commissioning work is still undergoing at the offshore transformer substation.

Source: LogIn
correct
20-Sep-2014 Event Type: Installation - Foundation Installation
Foundation Installation Svanen has now left the site allowing MPI Discovery to fully resume installation of the remaining foundations.
Source: LogIn
correct
06-Sep-2014 Event Type: Installation - Foundation Installation
Foundation Installation MPI Discovery returned to continue foundation and transition piece installation.
Source: LogIn
correct
26-Aug-2014 Event Type: Installation - Foundation Installation
Foundation Installation Ballast Nedam has been contracted to takeover foundation installation activities from MPI Offshore using the Svanen whilst the MPI Discovery contributes to installation activities at Humber Gateway. The Svanen was on site working.
Source: LogIn
correct
05-Jul-2014 Event Type: Installation - Other
Other Helwin2 was installed. The platform has a capacity of 690MW and currently Amrumbank West is the only project which will connect to it. According to Siemens the transmission project will be operational in 2015.
Source: LogIn
correct
02-Jun-2014 Event Type: Installation - Array Cable Installation
Array Cable Installation Siddis Mariner and Siem Moxie continue with array cable installation on the project, supported by two WFSVs, Bayard 4 and Windea One.
Source: LogIn
correct
24-May-2014 Event Type: Installation - Foundation Installation
Foundation Installation MPI Discovery left the site after completing the first phase of foundation installation.
Source: LogIn
correct
02-May-2014 Event Type: Installation - Offshore Substation
Offshore Substation The unmanned transformer station was installed. The transformer station is operated from the service station on Helgoland and monitored and controlled from E.ON’s Offshore Marine Coordination Center in Hamburg. The installation was put back 15 months due to TenneT not being able to install the grid connection on time.
Source: LogIn
correct
May-2014 Event Type: Planning - Other Approval
Other Approval BSH issue extension to May 2014 for construction start deadline.
Source: LogIn
correct
10-Apr-2014 Event Type: Installation - Offshore Substation
Offshore Substation Heavy lift vessel Rambiz arrived on site to begin installation of the substation foundation and topside. The work is expected to be completed by the end of April.
Source: LogIn
correct
Apr-2014 Event Type: Installation - Array Cable Installation
Array Cable Installation Array cable installation is scheduled to start in April 2014.
Source: LogIn
correct
04-Jan-2014 Event Type: Installation - Foundation Installation
Foundation Installation MPI Discovery was on site preparing for installation of the first foundation.
Source: LogIn
correct
Dec-2013 Event Type: Installation - Foundation Installation
Foundation Installation The monopiles are at the BOW Terminal and preparations for the first load out are underway.
Source: LogIn
correct
25-Nov-2013 Event Type: Installation - Other
Other Scour prevention sand bags have been placed by Peter Madsen Rederi A/S.
Source: LogIn
correct
26-Oct-2013 Event Type: Installation - Foundation Installation
Foundation Installation Installation vessel MPI Discovery has arrived in Vlissingen after completing the first phase of installation at UK development Humber Gateway. Foundation installation will commence at the start of November.
Source: LogIn
correct
30-Jul-2013 Event Type: Installation - Other
Other Scour prevention by Peter Madsen is currently ongoing and is expected to be completed at the end of September.
Source: LogIn
correct
12
Add new windfarm events, providing approximate date etc. Possible events include consent submission, approval, installation, generating power etc.

Call +44 (0)1502 307 037 for more information

Keep on top of the market. Perform analysis. Make informed decisions.

CONTACT US

More information?

Receive monthly updates with our Offshore Windfarm Subscription and gain access to even more detailed information on; cabling, converters, costs, foundations, substations, turbines.

Filter :
1234
StatusName
Decommissioned Hooksiel Hooksiel
Fully Commissioned Alpha Ventus Alpha Ventus
Fully Commissioned Amrumbank West Amrumbank West
Fully Commissioned BARD Offshore 1 BARD Offshore 1
Fully Commissioned Borkum Riffgrund 1 Borkum Riffgrund 1
Fully Commissioned Breitling Breitling
Fully Commissioned Butendiek Butendiek
Fully Commissioned DanTysk DanTysk
Fully Commissioned EnBW Baltic 1 EnBW Baltic 1
Fully Commissioned EnBW Baltic 2 EnBW Baltic 2
Fully Commissioned ENOVA Offshore Project Ems Emden ENOVA Offshore Project Ems Emden
Fully Commissioned Global Tech I Global Tech I
Fully Commissioned Gode Wind 1 and 2 Gode Wind 1 and 2
Fully Commissioned Meerwind Süd/Ost Meerwind Süd/Ost
Fully Commissioned Nordergründe Nordergründe
Fully Commissioned Nordsee One Nordsee One
Fully Commissioned Nordsee Ost Nordsee Ost
Fully Commissioned Riffgat Riffgat
Fully Commissioned Sandbank Sandbank
Fully Commissioned Trianel Windpark Borkum I Trianel Windpark Borkum I
Fully Commissioned Veja Mate Veja Mate
Fully Commissioned Wikinger Wikinger
Under Construction Arkona Arkona
Under Construction Borkum Riffgrund 2 Borkum Riffgrund 2
Under Construction Hohe See Hohe See
Under Construction Merkur Merkur
Under Construction OWP Albatros OWP Albatros
Pre-Construction Deutsche Bucht Deutsche Bucht
Pre-Construction GICON Schwimmendes Offshore Fundament (SOF) Pilot GICON Schwimmendes Offshore Fundament (SOF) Pilot
Pre-Construction Trianel Windpark Borkum II Trianel Windpark Borkum II
Consent Authorised Arcadis Ost 1 Arcadis Ost 1
Consent Authorised Baltic Eagle Baltic Eagle
Consent Authorised Borkum Riffgrund West 2 Borkum Riffgrund West 2
Consent Authorised Borkum Riffgrund West I Borkum Riffgrund West I
Consent Authorised Deutsche Bucht Pilot Park Deutsche Bucht Pilot Park
Consent Authorised EnBW He Dreiht EnBW He Dreiht
Consent Authorised Gode Wind 3 Gode Wind 3
Consent Authorised Gode Wind 4 Gode Wind 4
Consent Authorised Kaskasi Kaskasi
Consent Authorised OWP West OWP West
Consent Authorised Wikinger Süd Wikinger Süd
Consent Application Submitted Gennaker Gennaker
Concept/Early Planning GICON® SOF 6-8MW Test Turbine GICON® SOF 6-8MW Test Turbine
Concept/Early Planning ReaLCoE (Robust, Reliable and Large Offshore Wind Energy Converters for Clean, Low Cost and Competitive Electricity) ReaLCoE (Robust, Reliable and Large Offshore Wind Energy Converters for Clean, Low Cost and Competitive Electricity)
Development Zone Darß - priority area for wind energy Darß - priority area for wind energy
Development Zone German Central Tender 2022 (Assumed North Sea) German Central Tender 2022 (Assumed North Sea)
Development Zone German Central Tender 2023 (Assumed Baltic Sea) German Central Tender 2023 (Assumed Baltic Sea)
Development Zone German Central Tender 2024 (Assumed North Sea) German Central Tender 2024 (Assumed North Sea)
Development Zone German Central Tender 2025 (Assumed North Sea) German Central Tender 2025 (Assumed North Sea)
Development Zone German Central Tender 2026 (Assumed North Sea) German Central Tender 2026 (Assumed North Sea)
1234
Please LogIn to follow projects
Find quick and easy project and company information with our online search tool

Keep on top of the market. Perform analysis. Make informed decisions.

This page is intended to be viewed online and may not be printed without a valid subscription.

Please view this page at http://www.4coffshore.com/windfarms/events.aspx?windfarmID=de05.