Add new windfarm events, providing approximate date etc. Possible events include consent submission, approval, installation, generating power etc.
Events on DanTysk Database in Excel
12
DateEventDescription 
LogIn Event Type: Operation - Service Agreement Expires
Service Agreement Expires The five-year OEM service agreement will expire.
Source: LogIn
correct
07-Jun-2016 Event Type: Installation - Other
Other The 2500 tonne topside of the accommodation platform was installed. The vessel Stanislav Yudin placed the topside on the foundation. The accommodation platform will also be used at the Sandbank wind farm.
Source: LogIn
correct
26-May-2016 Event Type: Installation - Other
Other The 1300 tonne jacket for the accommodation platform arrived at the site. The vessel Stanislav Yudin will install the jacket.
Source: LogIn
correct
05-Feb-2016 Event Type: Other -
Other Fitting out of accommodation platform continues with electrics and interior.
Source: LogIn
correct
12-Oct-2015 Event Type: Engineering - Production and Procurement
Production and Procurement The accommodation platform completed its journey from Kiel to Emden.
Source: LogIn
correct
30-Apr-2015 Event Type: Operation - Fully Commissioned
Fully Commissioned Official commissioning occured. The ceremony was attended by German Federal Minister for Economic Affairs Sigmar Gabriel, Swedish Minister for Enterprise and Innovation Mikael Damberg, Hamburg Mayor Olaf Scholz and Torsten Albig, Prime Minister of the State of Schleswig-Holstein, joined Magnus Hall, President and CEO of Vattenfall, and Dr Florian Bieberbach, CEO of SWM.
Source: LogIn
correct
07-Apr-2015 Event Type: Operation - Generating Power
Generating Power It is believed that project is running at full capacity but official commissioning will not be until end of April.
Source: LogIn
correct
12-Dec-2014 Event Type: Operation - Generating Power
Generating Power Trial operations for exporting 288MW of power to shore via SylWin1 began on this date and are expected to last for ten weeks.
Source: LogIn
correct
03-Dec-2014 Event Type: Operation - Generating Power
Generating Power Vattenfall reported that DanTysk is successfully generating power to shore for the first time. This indicates that the SylWin1 station is sending small amounts of electricity to shore during it's commissioning phase.
Source: LogIn
correct
26-Nov-2014 Event Type: Operation - Generating Power
Generating Power DanTysk was ready to undergo trial operations; the wind farm would export power via HVDC converter SylWin1 which required further work before the trial operations could begin.
Source: LogIn
correct
27-Aug-2014 Event Type: Installation - Turbine Installation
Turbine Installation Turbine installation has been completed with the 80th 3.6MW turbine being installed. The installation of the turbines was completed in around four months, to which Vattenfall credited the good weather conditions on the North Sea.
Source: LogIn
correct
25-Jul-2014 Event Type: Installation - Turbine Installation
Turbine Installation The 56th turbine was installed at the project. This is Vattenfall's 1000th turbine to be installed across all projects.
Source: LogIn
correct
30-Jun-2014 Event Type: Operation - Generating Power
Generating Power By this point around 140MW of power had been connected to the grid.
Source: LogIn
correct
30-Jun-2014 Event Type: Installation - Turbine Installation
Turbine Installation Turbine installation reached the halfway mark. Each turbine takes approximately 19 hours to install, with all 80 expected to be installed by Autumn.
Source: LogIn
correct
28-May-2014 Event Type: Installation - Array Cable Installation
Array Cable Installation Over half of the array cables were installed. This area corresponds to the southern half of the development site and around 40 turbines have had their array cables connected.
Source: LogIn
correct
25-Apr-2014 Event Type: Installation - Turbine Installation
Turbine Installation Three turbines were installed at locations DT69, DT76 and DT79.
Source: LogIn
correct
17-Apr-2014 Event Type: Installation - Offshore Substation
Offshore Substation The offshore substation is at the end of its commissioning just as turbine installation has started.
Source: LogIn
correct
10-Apr-2014 Event Type: Installation - Turbine Installation
Turbine Installation The first turbine, of 80, was installed.
Source: LogIn
correct
Apr-2014 Event Type: Installation - Turbine Installation
Turbine Installation After some delays the turbine installation started, 11 months after the first foundation was installed.
Source: LogIn
correct
Apr-2014 Event Type: Installation - Array Cable Installation
Array Cable Installation Installation of the remaining array cables commenced by VSMC.
Source: LogIn
correct
Apr-2014 Event Type: Installation - Turbine Installation
Turbine Installation Turbine installation started with the first tower and nacelle being installed at position DT01. Turbine installation was delayed due to delays in grid connection and won't start until the spring. Consecutive commissioning will be utilised - each turbine will immediately supply to the grid as it is installed.
Source: LogIn
correct
17-Feb-2014 Event Type: Installation - Array Cable Installation
Array Cable Installation VSMC has now stepped in to take over array cable installation. VSMC will complete the termination of cables that have already been installed starting this month.
Source: LogIn
correct
21-Jan-2014 Event Type: Installation - Other
Other No vessels have entered the site since 13/12/2013. The slow down in operations is due to the delay in turbine installation.
Source: LogIn
correct
19-Dec-2013 Event Type: Installation - Other
Other Turbine delivery and preassembly increased in December 2013. All of the towers have been delivered and assembly has started. Half of the nacelles had been delivered.
Source: LogIn
correct
19-Dec-2013 Event Type: Installation - Turbine Installation
Turbine Installation On this date Project Director Ole Bigum-Nielsen stated "due to the delay in connecting to the grid, we have postponed the installation of the turbines until spring 2014".
Source: LogIn
correct
18-Dec-2013 Event Type: Installation - Array Cable Installation
Array Cable Installation Installation on the array cables took longer than originally scheduled, lasting into mid-2014.
Source: LogIn
correct
13-Dec-2013 Event Type: Installation - Foundation Installation
Foundation Installation Monopile installation was completed with all 80 monopiles installed in depths of up to 32m.
Source: LogIn
correct
Nov-2013 Event Type: Installation - Turbine Installation
Turbine Installation Turbine installation was initially scheduled to begin in July 2013, however this was postponed to April of the following year.
Source: LogIn
correct
30-Oct-2013 Event Type: Installation - Foundation Installation
Foundation Installation Approximately 70 foundations had been installed, leaving 10 remaining.
Source: LogIn
correct
19-Sep-2013 Event Type: Installation - Array Cable Installation
Array Cable Installation Van Oord array cable installation vessels Jan Steen and HAM 602 leave the project, putting lay and burial activities on hold.
Source: LogIn
correct
12
Add new windfarm events, providing approximate date etc. Possible events include consent submission, approval, installation, generating power etc.

Call +44 (0)1502 307 037 for more information

Keep on top of the market. Perform analysis. Make informed decisions.

CONTACT US

More information?

Receive monthly updates with our Offshore Windfarm Subscription and gain access to even more detailed information on; cabling, converters, costs, foundations, substations, turbines.

Filter :
1234
StatusName
Decommissioned Hooksiel Hooksiel
Fully Commissioned Alpha Ventus Alpha Ventus
Fully Commissioned Amrumbank West Amrumbank West
Fully Commissioned BARD Offshore 1 BARD Offshore 1
Fully Commissioned Borkum Riffgrund 1 Borkum Riffgrund 1
Fully Commissioned Breitling Breitling
Fully Commissioned Butendiek Butendiek
Fully Commissioned DanTysk DanTysk
Fully Commissioned EnBW Baltic 1 EnBW Baltic 1
Fully Commissioned EnBW Baltic 2 EnBW Baltic 2
Fully Commissioned ENOVA Offshore Project Ems Emden ENOVA Offshore Project Ems Emden
Fully Commissioned Global Tech I Global Tech I
Fully Commissioned Gode Wind 1 and 2 Gode Wind 1 and 2
Fully Commissioned Meerwind Süd/Ost Meerwind Süd/Ost
Fully Commissioned Nordergründe Nordergründe
Fully Commissioned Nordsee One Nordsee One
Fully Commissioned Nordsee Ost Nordsee Ost
Fully Commissioned Riffgat Riffgat
Fully Commissioned Sandbank Sandbank
Fully Commissioned Trianel Windpark Borkum I Trianel Windpark Borkum I
Fully Commissioned Veja Mate Veja Mate
Fully Commissioned Wikinger Wikinger
Under Construction Arkona Arkona
Under Construction Borkum Riffgrund 2 Borkum Riffgrund 2
Under Construction Hohe See Hohe See
Under Construction Merkur Merkur
Under Construction OWP Albatros OWP Albatros
Pre-Construction Deutsche Bucht Deutsche Bucht
Pre-Construction GICON Schwimmendes Offshore Fundament (SOF) Pilot GICON Schwimmendes Offshore Fundament (SOF) Pilot
Pre-Construction Trianel Windpark Borkum II Trianel Windpark Borkum II
Consent Authorised Arcadis Ost 1 Arcadis Ost 1
Consent Authorised Baltic Eagle Baltic Eagle
Consent Authorised Borkum Riffgrund West 2 Borkum Riffgrund West 2
Consent Authorised Borkum Riffgrund West I Borkum Riffgrund West I
Consent Authorised Deutsche Bucht Pilot Park Deutsche Bucht Pilot Park
Consent Authorised EnBW He Dreiht EnBW He Dreiht
Consent Authorised Gode Wind 3 Gode Wind 3
Consent Authorised Gode Wind 4 Gode Wind 4
Consent Authorised Kaskasi Kaskasi
Consent Authorised OWP West OWP West
Consent Authorised Wikinger Süd Wikinger Süd
Consent Application Submitted Gennaker Gennaker
Concept/Early Planning GICON® SOF 6-8MW Test Turbine GICON® SOF 6-8MW Test Turbine
Concept/Early Planning ReaLCoE (Robust, Reliable and Large Offshore Wind Energy Converters for Clean, Low Cost and Competitive Electricity) ReaLCoE (Robust, Reliable and Large Offshore Wind Energy Converters for Clean, Low Cost and Competitive Electricity)
Development Zone Darß - priority area for wind energy Darß - priority area for wind energy
Development Zone German Central Tender 2022 (Assumed North Sea) German Central Tender 2022 (Assumed North Sea)
Development Zone German Central Tender 2023 (Assumed Baltic Sea) German Central Tender 2023 (Assumed Baltic Sea)
Development Zone German Central Tender 2024 (Assumed North Sea) German Central Tender 2024 (Assumed North Sea)
Development Zone German Central Tender 2025 (Assumed North Sea) German Central Tender 2025 (Assumed North Sea)
Development Zone German Central Tender 2026 (Assumed North Sea) German Central Tender 2026 (Assumed North Sea)
1234
Please LogIn to follow projects
Find quick and easy project and company information with our online search tool

Keep on top of the market. Perform analysis. Make informed decisions.

This page is intended to be viewed online and may not be printed without a valid subscription.

Please view this page at http://www.4coffshore.com/windfarms/events.aspx?windfarmID=de02.