South Fork Wind secures final approval

4C Offshore | Tom Russell
By: Tom Russell 20/01/2022 South Fork Wind

South Fork Wind
, New York’s first offshore wind farm, has received approval of the project’s Construction and Operations Plan (COP) from the U.S. Department of the Interior’s Bureau of Ocean Energy Management (BOEM). It was the final decision needed from the agency to move the project towards the start of construction.  

South Fork Wind will be located about 35 miles east of Montauk Point. With a capacity of 132 MW, the offshore wind farm is expected to begin operations at the end of 2023.

The COP approval outlines the project’s one nautical mile turbine spacing, the requirements on the construction methodology for all work occurring in federal ocean waters, and mitigation measures to protect marine habitats and species. BOEM’s final approval of the COP follows the agency’s November 2021 issuance of its Record of Decision, which concluded the thorough BOEM-led environmental review of the project.

“This milestone underscores the tremendous opportunity we have to create a new industry from the ground up to drive our green energy economy, deliver clean power to millions of homes and create good jobs across the state,”
said Governor Kathy Hochul. “As we tackle climate change head on and transition to a clean economy, these are the projects that will power our future.”


“We're excited to reach this critical point and receive BOEM’s final approval of our Construction and Operations Plan,”
said David Hardy, Chief Executive Officer of Ørsted Offshore North America. “As New York’s first offshore wind farm, South Fork Wind is already contributing to a new statewide and U.S. manufacturing era and maritime industry, including good-paying union jobs through our labor partnerships and vision for the industry. I want to thank Secretary Haaland, Governor Hochul, BOEM Director Lefton, NYSERDA CEO Harris, the NY State Legislature, the Long Island Power Authority, East Hampton’s elected leaders and other partners who are championing offshore wind energy.”


“Today, after years of careful planning, we are on the cusp of making history as South Fork Wind, New York’s first-ever offshore wind farm, will soon become a reality,”
said Joe Nolan, Chief Executive Officer and President of Eversource Energy. “With onshore construction expected in the coming days, New Yorkers are closer than ever to realizing the benefits of clean energy as we continue to deliver on our promise of creating jobs, providing economic investment, and fighting climate change.”

Ørsted and Eversource are now entering the construction phase for
South Fork Wind, which will be built under labour agreements and specific partnerships with local union organisations, aiming to ensure local union labour’s participation in all phases of construction on the project. Site preparation and onshore activities for the project’s underground duct bank system and interconnection facility will be the first to begin, and will source construction labour from local union hiring halls.  

Fabrication of the project’s offshore substation is already in process. Ørsted and Eversource recently announced the selection of Kiewit Offshore Services, Ltd. (Kiewit), a U.S. based offshore fabricator, to design and build the substation for the project. The 1,500-ton, 60-foot-tall substation will be built at Kiewit’s facility in Ingleside, Texas, near Corpus Christi.

Long Island-based contractor Haugland Energy Group LLC (an affiliate of Haugland Group LLC) was recently selected to install the duct bank system for the project’s underground onshore transmission line and lead the construction of the onshore interconnection facility located in East Hampton, New York.

Offshore installation of the project’s monopile foundations and
11 MW Siemens Gamesa wind turbines is expected to begin in Summer 2023.  

For more information on offshore wind farms worldwide, click here.  Alternatively, you can view projects across the globe using 4C Offshore's Interactive Map.

Premium

4C Offshore Premium, our most popular subscription, gives you full access to use the 4C Offshore WebApp which includes exclusive offshore wind, transmission and vessel reports, news and downloads.

Request a 30 minute Demo

Trending News!