SSEN completes Pentland Firth East cable replacement

4C Offshore | Tom Russell
By: Tom Russell 06/11/2020 SSEN

A project to replace one of the two submarine electricity distribution cables connecting Orkney to mainland Scotland is now complete. Teams from Scottish and Southern Electricity Networks (SSEN) connected the new 37km subsea cable to the main electricity network on Thursday 5 November.


The £30 million cable replacement project involved offshore works using specialist marine vessels – the
Normand Clipper and Global Symphony – working with principal contractor, Global Offshore, to install and bury the 33 kilovolt (kV) cable between Murkle Bay, near Thurso and Rackwick Bay on the island of Hoy.

Working in partnership with Aviemore-based McGowan Environmental Engineering Ltd, the installation of the new subsea cable also allowed for the removal of approximately 7km of existing overhead power lines in Rackwick, Hoy, which have now been replaced by underground cable. The existing overhead line will be dismantled in the coming weeks.


Local firms Pentland Ferries and storage and distribution specialists McAdie and Reeves supported the delivery of the land cable works, with a bulk cargo vessel chartered to deliver 5,000 tonnes of high specification sand to Lyness harbour, and almost 30 large items of equipment and vehicles shipped from Gills Bay to Lyness under specialist charter on Pentland Ferries’ MV Pentalina.

Mark Rough, Director of Customer Operations at SSEN, said: “The Pentland Firth East project is one of the biggest standalone projects we’ve completed in the north of Scotland and we’d like to thank our contract partners, archaeological and ecological experts, engineering teams and local suppliers for their professionalism and dedication to ensure the successful delivery of the subsea cable installation and land-based works on Hoy.


“Ensuring a safe, secure and reliable supply of electricity to our customers is our main priority at SSEN. We’d like to take this opportunity to thank the local community for their ongoing support as we worked to deliver this significant investment which will strengthen resilience of supplies to the Orkney Islands for years to come.”


James Stockan, Leader of Orkney Islands Council, said: “The new cable will secure Orkney’s electricity supply well into the future and I am delighted this crucially important work has been completed successfully.
 

“In addition, I am pleased that the onshore work at Rackwick and beyond had been carried out to a very high standard in an area renowned for its wildlife and natural beauty – a challenging task undertaken with great skill and sensitivity.”


SSEN is undertaking a programme of investment to replace around 90km of submarine cables connecting Scotland’s island communities by 2023 – a fifth of the total number currently in operation.


The Pentland Firth East cable was identified for replacement after routine inspections found it was coming to the end of its operational life. In July 2019, SSEN completed repairs to the cable in Rackwick Bay following a cable fault.


For more information on subsea cables interconnector projects worldwide, click here. You can also view projects worldwide on 4C Offshore's interactive map.