Triton Knoll reaches construction milestone

In: Windfarms
26/08/2020
RWE

RWE has completed the installation of all 90 turbine foundations and two 50-kilometre long export cables connecting
Triton Knoll's offshore and onshore electrical systems. The installation was achieved during one of the project’s most challenging times due to the impact of Covid-19, and has been completed within the planned summer delivery window.

With a commercial operation date expected in the first quarter 2022,
Triton Knoll will have an installed capacity of 857 MW, capable of supplying green electricity equivalent to the annual demand of over 800,000 UK homes. It is located over 32 kilometres off the Lincolnshire coast. It is jointly owned by RWE (59%), J-Power (25%) and Kansai Electric Power (16%), with RWE leading the wind farm’s construction and long-term operation and maintenance works, on behalf of the project partners. Total planned investment volume amounts to approximately £2 billion.

Triton Knoll was awarded a Contract for Difference (CfD) by the UK Department for Business, Energy & Industrial Strategy in September 2017. A Power Purchase Agreement (PPA) with Ørsted, under which the company will offtake 100% of the power produced by the wind farm, complements Triton Knoll’s CfD, mitigating any market price uncertainty for the first 15 years of the wind farm’s operation.

Tom Glover, RWE Renewables Chief Commercial Officer and RWE UK Country Chair, said: “The UK is one of the most important markets for RWE, where we have significant growth ambitions in offshore wind. Following in the footsteps of Triton Knoll will be our 1.4 GW Sofia offshore wind farm, which has a potential investment value of around £3 billion. We are also looking forward to developing a number of extension projects to our existing UK offshore wind farms, in connection with opportunities arising from The Crown Estate’s latest leasing round.”

Sven Utermöhlen, Chief Operating Officer Wind Offshore Global of RWE Renewables, said: “With the installation of all foundations and the export cables, we have successfully completed a key offshore construction phase at Triton Knoll. The Triton Knoll team and our suppliers have shown a great commitment to reach this milestone within schedule, whilst coping with the many challenges posed by the Corona pandemic. We now look forward to installing the first 9.5 MW offshore turbines in early 2021. Throughout, the safety and welfare of everyone working on the project remains our top priority.”


Copyright © 4C Offshore 2020

  • ISO 14001 173953 2015 AHSO GBR UKAS 2 | 4C Offshore
  • Achilles UVDB Supply Chain Community | 4C Offshore