U.S. firm to fabricate South Fork substation

4C Offshore | Tom Russell
By: Tom Russell 26/08/2021 Ørsted
South Fork Wind project partners Ørsted and Eversource have selected Kiewit Offshore Services, Ltd. (Kiewit), one of the largest offshore fabricators in the U.S., to design and build the substation for the project.

The 1,500-ton, 60-foot-tall substation will be built at Kiewit's facility in Ingleside, Texas, near Corpus Christi. The substation will collect the power produced by wind turbines and connect the clean energy to the grid. It will consist of a topside resting on a mono-pile foundation.

According to the project partners, more than 350 workers across three states will support this
South Fork Wind structure. The fabrication workers in Ingleside will be supported by teams in Houston and Kansas. In addition, union workers in the Northeast will support the South Fork Wind project and additional initiatives in the region.

"We're helping to build a new U.S. manufacturing industry that will create thousands of good-paying jobs not just in the Northeast but in communities across the United States,"
said David Hardy, Chief Executive Officer of Ørsted Offshore North America. "We're proud to partner with Kiewit to deliver the first American-made offshore wind substation. This initiative is part of our commitment to deliver for our long-term partners, combining international experience with local expertise in communities across the country."

"Achieving our nation's clean energy goals will be largely dependent on U.S.-based companies like Kiewit, and we are excited to partner with them to deliver the first U.S.-made offshore wind substation,"
Joe Nolan, Chief Executive Officer and President of Eversource Energy, said. "Our partnership with Kiewit marks another significant milestone for the U.S. offshore wind industry and signals the growth of the next great maritime industry throughout the country. We are committed to creating a clean energy future and fostering opportunities for all Americans."


"The production of clean energy is at a pivotal stage in the U.S., and offshore wind, such as the South Fork Wind project, plays a very important role,"
said Paul Geldmeier, who leads Kiewit's offshore wind power work as Executive Vice President, Kiewit Energy. "We are proud to contribute our engineering and construction expertise and experience to this industry-first project."


Kiewit expects to begin construction on the substation in November and complete the work by spring 2023, before transiting the substation across the Gulf of Mexico and up the East Coast for installation at the
South Fork Wind site in the summer of 2023.

South Fork Wind continues to advance through the federal permitting process, with the Bureau of Ocean Energy Management issuing the project's final Environmental Impact Statement on August 16. South Fork Wind remains on-track to be fully permitted in early 2022, with construction activities ramping up soon after and the project expected to produce energy by the end of 2023.

For more information on offshore wind farms worldwide, click here.

Premium

4C Offshore Premium, our most popular subscription, gives you full access to use the 4C Offshore WebApp which includes exclusive offshore wind, transmission and vessel reports, news and downloads.

Request a 30 minute Demo

Trending News!