Developers/Owners/Operators (12)

RoleOrganisation 
Developer
correct
Main Contractor-EPCI
THV Seawind (Dredging international and Fabricom GTI JV)
Client: LogIn
correct
Main Contractor-EPCI
ABB AS
Client: LogIn
correct
Main Contractor-EPCI
DEME NV
Client: LogIn
correct
Operator
correct
Owner correct
Owner
Societe Regionale d'Investissement de Wallonie
correct
Owner correct
Owner
EDF Energies Nouvelles Group (EDF SA)
correct
Owner correct
Owner correct
Owner correct

Turbines (11)

RoleOrganisation 
Contractor-Heavy Load Logistics(Turbine) correct
Contractor-Heavy Load Logistics(Turbine) correct
Installer-Turbine
Installation of 30 x 6M turbines
Number of turbines installed: LogIn
correct
Main Contractor-Turbine Supply and Installation correct
Maintenance-Turbine
CMI
Client: LogIn
correct
Maintenance-Turbine correct
Manufacturer-Turbine
Supply 30 x 6M turbines. Senvion (formally Repower) is responsible for the installation, the commissioning and the testing of the turbines. They are also responsible for Operation and Maintenance of the wind turbines during the first 10 years of exploitation (including a possible extension for 10 additional years).
Nominal Capacity (MW): LogIn
correct
Manufacturer-Turbine(Blades)
LM Wind Power supplied 90 blades for the 30 Senvion 6.2M126 turbines.
correct
Manufacturer-Turbine(Tower) correct
Supplier-Crane(Turbine)
Palfinger Marine- und Beteilungs-GmbH
correct
Supplier-Crane(Turbine)
Palfinger Marine- und Beteilungs-GmbH
correct

Substations (4)

RoleOrganisation 
Designer-Substation-Topside
Design, engineering, construction and pre-commissoning of the offshore high voltage station (EPC -contract)
correct
Installer-Substation
ABB AS
Client: LogIn
correct
Manufacturer-Substation-Topside correct
Supplier-Crane(Substation)
Palfinger Marine- und Beteilungs-GmbH
correct

Foundations (16)

RoleOrganisation 
Contractor-Grouting(turbines) correct
Designer(Detailed)-Foundation(Substation)
Responsible for the detailed design of the jacket foundation for the offshore transformer station
Number of substations: LogIn
correct
Designer(Detailed)-Foundation(Turbine)
OWEC Tower AS
correct
Installer(LEAD)-Foundation(substation) correct
Installer(LEAD)-Foundation(turbine) correct
Installer-Foundation(pre-piling) correct
Installer-Foundation(substation) correct
Installer-Foundation(turbine) correct
Manufacturer-Foundation(PinPiles)
120 pre-piles
Number of piles manufactured: LogIn
correct
Manufacturer-Foundation(pre-fabricated pipes)
Supplied 22.35 tonnes of pre-fabricated steel pipes for use in construction of jacket foundations
correct
Manufacturer-Foundation(substation)
Awarded the engineering and fabrication of one of the jackets. More information to follow.
Number of foundations: LogIn
correct
Manufacturer-Foundation(Template)
Production and supply of the piling frame for Thornton II installation of jackets
Number of templates: LogIn
correct
Manufacturer-Foundation(turbine) correct
Manufacturer-Foundation-Primary Steel(substation) correct
Supplier-Crane(Transition Piece)
Palfinger Marine- und Beteilungs-GmbH
correct
Supplier-Flanges
Supplied 30 x Ø5500 mm flanges for Jacket foundations
correct

Array Cabling (5)

RoleOrganisation 
Installer-Array Cabling
Installation and burial of 24 infield cables(25km) with CS Sovereign(lay) and Cable Innovator(burial)
Cable Length km: LogIn
correct
Installer-Array Cabling(burial)
Used Cable Innovator for burial of the 24 array cables(25km), as part of contract
Cable Length km: LogIn
correct
Installer-Array Cabling(cable lay)
Used CS Sovereign for installation of the 24 array cables(25km), as part of contract
Cable Length km: LogIn
correct
Manufacturer-Array Cabling correct
Supplier-Cable Protection Systems correct

Export Cabling (2)

Met Masts (0)

Consultants (4)

RoleOrganisation 
Consultant-Financial correct
Consultant-Financial correct
Consultant-Health & Safety
Offshore health and safety consultancy services and Shore-side health and safety consultancy services.
correct
Consultant-Other
Marine warranty surveyors.
correct

Others (13)

RoleOrganisation 
Contractor-Other correct
Contractor-Other correct
Contractor-Other correct
Maintenance-Other correct
Port correct
Supplier-Helicopter correct
Supplier-Hydraulic Hammer
S-800 Hydrohammer
Pile Diameter - 1.82m
Year - 2011
Substation and Turbine Jackets

Number of piles driven in - Not number of foundations: LogIn
correct
Supplier-Navigation Aids
Pharos Marine ltd
Client: LogIn
Manufactured navigation aids between 2008/2011
correct
Supplier-Other
Aluwind Danmark A/S
For the jacket foundations Aluwind supplied swing gates, hatches and mark plates.
correct
Supplier-Other correct
Surveyor-Geophysical
correct
Surveyor-Geotechnical
correct
Surveyor-Geotechnical correct

Call +44 (0)1502 307 037 for more information

Keep on top of the market. Perform analysis. Make informed decisions.

CONTACT US

More information?

Receive monthly updates with our Offshore Windfarm Subscription and gain access to even more detailed information on; cabling, converters, costs, foundations, substations, turbines.

Filter :
Please LogIn to follow projects
Find quick and easy project and company information with our online search tool

Keep on top of the market. Perform analysis. Make informed decisions.

This page is intended to be viewed online and may not be printed without a valid subscription.

Please view this page at https://www.4coffshore.com/windfarms/organisations.aspx?windfarmID=be09.