Add new windfarm events, providing approximate date etc. Possible events include consent submission, approval, installation, generating power etc.
Events on BARD Offshore 1 Database in Excel
12
DateEventDescription 
12-Mar-2018 Event Type: Other -
Other Bloomberg reports that Ocean Breeze Energy GmbH & Co. is putting 100% of the BARD wind farm up for sale. Upon direct communication with UniCredit Bank AG who own Ocean Breeze, the UniCredit spokesperson refused to comment.
Source: LogIn
correct
11-Sep-2017 Event Type: Inspection, Maintenance & Repair - Offshore Substation
Offshore Substation NDE Offshore AB completed a Topside IRM campaign for Ocean Breeze on BARD I using the vessel Ocean Zephyr. In June 2017 NDE signed a two year inspection, repair and maintenance contract for the wind farm.
Source: LogIn
correct
30-Sep-2016 Event Type: Operation - Performance Monitoring
Performance Monitoring Up to November 2016 the wind farm had produced 3.5TWh of electricity.
Source: LogIn
correct
31-May-2016 Event Type: Operation - Performance Monitoring
Performance Monitoring By the end of May, BARD Offshore 1 had generated 3TWh of electricity.
Source: LogIn
correct
05-Oct-2015 Event Type: Operation - Generating Power
Generating Power After 18 months of problems BARD Offshore 1 is finally stable again and transmitting at full capacity.
Source: LogIn
correct
Oct-2015 Event Type: Operation - Performance Monitoring
Performance Monitoring BARD Offshore is the first German offshore wind farm to generate over 2TWh. Nearly 700GWh was produced between January and October 2015.
Source: LogIn
correct
18-Jul-2015 Event Type: Failure - Array Cable
Array Cable Output from BARD 1 was limited to 310MW from 18/07/2015 until 24/07/2015, due to a problem with cable AC102 and AC103.
Source: LogIn
correct
Sep-2014 Event Type: Operation - Generating Power
Generating Power There have been a number of technical faults at BorWin1 that have resulted in unplanned shutdowns. There have been investigations into the causes and countermeasures to these faults. The faults were expected to be fixed and the wind farm will be connected in August, but it was delayed until the last week in September. The Project is connected.
Source: LogIn
correct
28-Apr-2014 Event Type: Incident - Health and Safety
Health and Safety A worker was seriously injured and transported back to shore.
Source: LogIn
correct
2014 Event Type: Other -
Other Due to TenneT's delay in supplying the grid connection, BARD Offshore 1 are claiming compensation due to a loss of earnings under § 17e Paragraph 2 of the Energy Act claims.
Source: LogIn
correct
26-Aug-2013 Event Type: Operation - Fully Commissioned
Fully Commissioned All 80 turbines were connected to the grid as the project was officially inaugurated.
Source: LogIn
correct
10-Aug-2013 Event Type: Installation - Array Cable Installation
Array Cable Installation Array cable installation completed.
Source: LogIn
correct
Aug-2013 Event Type: Installation - Turbine Installation
Turbine Installation The final turbine has been installed. A total of 65 of the 80 turbines have been connected to the grid with the remaining 15 likely to be connected during September.
Source: LogIn
correct
Aug-2013 Event Type: Operation - Generating Power
Generating Power 65 of the 80 turbines have been connected to the grid, the remaining 15 were connected by mid-September.
Source: LogIn
correct
20-Jun-2013 Event Type: Installation - Turbine Installation
Turbine Installation Estimated 71 turbines installed, with Fred. Olsen Windcarrier's Brave tern working on the remaining 9.
Source: LogIn
correct
10-May-2013 Event Type: Installation - Turbine Installation
Turbine Installation Brave Tern arrived on site to install nacelles and hubs with blades attached.
Source: LogIn
correct
12-Mar-2013 Event Type: Installation - Foundation Installation
Foundation Installation A total of 72 foundations have been installed.
Source: LogIn
correct
12-Mar-2013 Event Type: Installation - Turbine Installation
Turbine Installation 40 of the 80 turbines are now installed and producing power to the grid. Currently, only a total of 59 nacelles have been fabricated.
Source: LogIn
correct
11-Dec-2012 Event Type: Installation - Turbine Installation
Turbine Installation Construction Update: Fred. Olsen Windcarrier has been awarded a contract to install the remaining turbines and associated equipment. The contract commences in March 2013 and is expected to take 150 days.
Source: LogIn
correct
20-Nov-2012 Event Type: Other -
Other SüdWestStrom Windpark GmbH & Co. KG pulled out of purchasing 70% of the project blaming construction delays and unforeseeable future risks.
Source: LogIn
correct
16-Nov-2012 Event Type: Operation - Generating Power
Generating Power The project is now producing 100MW of power more than a year before completion. Note: this conflicts with earlier reports of 24 of 80 turbines generating.
Source: LogIn
correct
Jun-2012 Event Type: Operation - Generating Power
Generating Power 24 of 80 turbines were generating power.
Source: LogIn
correct
20-Mar-2012 Event Type: Installation - Foundation Installation
Foundation Installation 50 out of 80 foundations are now installed at the project, 30 have a tower and nacelle in place and 16 of the 5MW turbines are generating electricity.
Source: LogIn
correct
27-Jan-2012 Event Type: Installation - Turbine Installation
Turbine Installation 30 of the 80 turbines have been installed.
Source: LogIn
correct
2011 Event Type: Installation - Array Cable Installation
Array Cable Installation The first phase of array cable installation was finished in 2011.
Source: LogIn
correct
07-Dec-2010 Event Type: Installation - Turbine Installation
Turbine Installation Fifteen Bard 5.0 turbines are now installed; the wind farm exported its first power to BorWin 1 last weekend.
Source: LogIn
correct
03-Dec-2010 Event Type: Operation - Generating Power
Generating Power Turbine 'S-5-4' is the first to feed power to BorWin 1 at 11.35pm.
Source: LogIn
correct
02-Dec-2010 Event Type: Installation - Export Cable Installation
Export Cable Installation The cables have been installed connecting the wind farm to the BorWin Alpha substation.
Source: LogIn
correct
May-2010 Event Type: Installation - Array Cable Installation
Array Cable Installation The array cable installation started in May 2010.
Source: LogIn
correct
May-2010 Event Type: Installation - Offshore Substation
Offshore Substation The offshore substation was installed.
Source: LogIn
correct
12
Add new windfarm events, providing approximate date etc. Possible events include consent submission, approval, installation, generating power etc.

Call +44 (0)1502 307 037 for more information

Keep on top of the market. Perform analysis. Make informed decisions.

CONTACT US

More information?

Receive monthly updates with our Offshore Windfarm Subscription and gain access to even more detailed information on; cabling, converters, costs, foundations, substations, turbines.

Filter :
1234
StatusName
Decommissioned Hooksiel Hooksiel
Fully Commissioned Alpha Ventus Alpha Ventus
Fully Commissioned Amrumbank West Amrumbank West
Fully Commissioned BARD Offshore 1 BARD Offshore 1
Fully Commissioned Borkum Riffgrund 1 Borkum Riffgrund 1
Fully Commissioned Breitling Breitling
Fully Commissioned Butendiek Butendiek
Fully Commissioned DanTysk DanTysk
Fully Commissioned EnBW Baltic 1 EnBW Baltic 1
Fully Commissioned EnBW Baltic 2 EnBW Baltic 2
Fully Commissioned ENOVA Offshore Project Ems Emden ENOVA Offshore Project Ems Emden
Fully Commissioned Global Tech I Global Tech I
Fully Commissioned Gode Wind 1 and 2 Gode Wind 1 and 2
Fully Commissioned Meerwind Süd/Ost Meerwind Süd/Ost
Fully Commissioned Nordergründe Nordergründe
Fully Commissioned Nordsee One Nordsee One
Fully Commissioned Nordsee Ost Nordsee Ost
Fully Commissioned Riffgat Riffgat
Fully Commissioned Sandbank Sandbank
Fully Commissioned Trianel Windpark Borkum I Trianel Windpark Borkum I
Fully Commissioned Veja Mate Veja Mate
Fully Commissioned Wikinger Wikinger
Under Construction Arkona Arkona
Under Construction Borkum Riffgrund 2 Borkum Riffgrund 2
Under Construction Hohe See Hohe See
Under Construction Merkur Merkur
Under Construction OWP Albatros OWP Albatros
Pre-Construction Deutsche Bucht Deutsche Bucht
Pre-Construction GICON Schwimmendes Offshore Fundament (SOF) Pilot GICON Schwimmendes Offshore Fundament (SOF) Pilot
Pre-Construction Trianel Windpark Borkum II Trianel Windpark Borkum II
Consent Authorised Arcadis Ost 1 Arcadis Ost 1
Consent Authorised Baltic Eagle Baltic Eagle
Consent Authorised Borkum Riffgrund West 2 Borkum Riffgrund West 2
Consent Authorised Borkum Riffgrund West I Borkum Riffgrund West I
Consent Authorised Deutsche Bucht Pilot Park Deutsche Bucht Pilot Park
Consent Authorised EnBW He Dreiht EnBW He Dreiht
Consent Authorised Gode Wind 3 Gode Wind 3
Consent Authorised Gode Wind 4 Gode Wind 4
Consent Authorised Kaskasi Kaskasi
Consent Authorised OWP West OWP West
Consent Authorised Wikinger Süd Wikinger Süd
Consent Application Submitted Gennaker Gennaker
Concept/Early Planning GICON® SOF 6-8MW Test Turbine GICON® SOF 6-8MW Test Turbine
Concept/Early Planning ReaLCoE (Robust, Reliable and Large Offshore Wind Energy Converters for Clean, Low Cost and Competitive Electricity) ReaLCoE (Robust, Reliable and Large Offshore Wind Energy Converters for Clean, Low Cost and Competitive Electricity)
Development Zone Darß - priority area for wind energy Darß - priority area for wind energy
Development Zone German Central Tender 2022 (Assumed North Sea) German Central Tender 2022 (Assumed North Sea)
Development Zone German Central Tender 2023 (Assumed Baltic Sea) German Central Tender 2023 (Assumed Baltic Sea)
Development Zone German Central Tender 2024 (Assumed North Sea) German Central Tender 2024 (Assumed North Sea)
Development Zone German Central Tender 2025 (Assumed North Sea) German Central Tender 2025 (Assumed North Sea)
Development Zone German Central Tender 2026 (Assumed North Sea) German Central Tender 2026 (Assumed North Sea)
1234
Please LogIn to follow projects
Find quick and easy project and company information with our online search tool

Keep on top of the market. Perform analysis. Make informed decisions.

This page is intended to be viewed online and may not be printed without a valid subscription.

Please view this page at http://www.4coffshore.com/windfarms/events.aspx?windfarmID=de23.