Events on Belwind Database in Excel
DateEventDescription 
LogIn Event Type: Operation - Service Agreement Expires
Service Agreement Expires The 15-year OEM service and availability agreement expired.
Source: LogIn
correct
02-Feb-2017 Event Type: Other - Ownership Change
Ownership Change Parkwind NV became sole owners of Belwind NV in February 2017, after purchasing Summit Renewable Energy Belwind 1 Ltd's (Sumitomo Corporation) share holding in project.
Source: LogIn
correct
09-Dec-2010 Event Type: Operation - Fully Commissioned
Fully Commissioned Official start of operation.
Source: LogIn
correct
Oct-2010 Event Type: Installation - Export Cable Installation
Export Cable Installation Estimated finish for export cable lay.
Source: LogIn
correct
15-Sep-2010 Event Type: Installation - Turbine Installation
Turbine Installation The final turbine was installed during September 2010.
Source: LogIn
correct
Aug-2010 Event Type: Installation - Offshore Substation
Offshore Substation During August 2010 the offshore substation is likely to be installed.
Source: LogIn
correct
Aug-2010 Event Type: Installation - Export Cable Installation
Export Cable Installation Estimated start for export cable lay.
Source: LogIn
correct
26-Mar-2010 Event Type: Installation - Turbine Installation
Turbine Installation First turbine installed.
Source: LogIn
correct
16-Feb-2010 Event Type: Installation - Other
Other The final transition piece was installed.
Source: LogIn
correct
05-Feb-2010 Event Type: Installation - Foundation Installation
Foundation Installation Finished installing the 56 monopiles.
Source: LogIn
correct
2010 Event Type: Installation - Array Cable Installation
Array Cable Installation Array cable was installed during 2010.
Source: LogIn
correct
30-Aug-2009 Event Type: Installation - Foundation Installation
Foundation Installation Start installation of foundations.
Source: LogIn
correct
27-Jul-2009 Event Type: Planning - Financing Agreement
Financing Agreement The Environmental Investment Bank (EIB) to provide up to €300m of debt finance.
Source: LogIn
correct
24-Jul-2009 Event Type: Planning - Financial Close
Financial Close Financial Close.
Source: LogIn
correct
20-Feb-2008 Event Type: Planning - Consent Authorised
Consent Authorised Environmental permit granted by the Minister responsible for the marine environment.
Source: LogIn
correct
05-Jun-2007 Event Type: Planning - Other Approval
Other Approval Concession granted by the State Secretary of Energy.
Source: LogIn
correct
Jun-2006 Event Type: Planning - Consent Application Submitted
Consent Application Submitted Consent Application Submitted.
Source: LogIn
correct
Add new windfarm events, providing approximate date etc. Possible events include consent submission, approval, installation, generating power etc.

Call +44 (0)1502 307 037 for more information

Keep on top of the market. Perform analysis. Make informed decisions.

CONTACT US

More information?

Receive monthly updates with our Offshore Windfarm Subscription and gain access to even more detailed information on; cabling, converters, costs, foundations, substations, turbines.

Filter :
Please LogIn to follow projects
Find quick and easy project and company information with our online search tool

Keep on top of the market. Perform analysis. Make informed decisions.

This page is intended to be viewed online and may not be printed without a valid subscription.

Please view this page at https://www.4coffshore.com/windfarms/events.aspx?windfarmID=be03.