Events on Borkum Riffgrund 1 Database in Excel
12
DateEventDescription 
LogIn Event Type: Operation - Service Agreement Expires
Service Agreement Expires The five-year OEM service agreement will expire.
Source: LogIn
correct
28-Jan-2016 Event Type: Planning - Grid Connection Agreed
Grid Connection Agreed BNetzA moved the 112MW of the assigned capacity Borkum Riffgrund I had on DolWin3 to join its 200MW of assigned capacity on DolWin1. Borkum Riffgrund I now has 312MW of assigned capacity on DolWin1.
Source: LogIn
correct
21-Jan-2016 Event Type: Other -
Other TenneT submitted a request to BNetzA to be able to move the allocated 112MW from DolWin3 to DolWin1.
Source: LogIn
correct
23-Dec-2015 Event Type: Incident - Loss of Asset
Loss of Asset The crew transfer vessel Umoe Ventus caught fire and sank 200m off the coast. The 4 crew members managed to evacuate safely.
Source: LogIn
correct
09-Oct-2015 Event Type: Operation - Fully Commissioned
Fully Commissioned Fully commissioned. His Royal Highness Prince Joachim of Denmark officially opened the site. Borkum Riffgrund 1 was built at a cost 5-10% below the initially announced FID budget.
Source: LogIn
correct
28-Jul-2015 Event Type: Installation - Grid Connection Available
Grid Connection Available DolWin1 was fully commissioned, meaning Borkum Riffgrund I has a complete connection to the grid.
Source: LogIn
correct
02-Jul-2015 Event Type: Installation - Other
Other DBB Jack-Up completes commissioning work on 50 turbines, using new WIND SERVER vessel, for Siemens.
Source: LogIn
correct
26-May-2015 Event Type: Installation - Turbine Installation
Turbine Installation Turbine installation is complete, just a few days after DONG Energy reached its 3,000MW installed capacity milestone. Over half of the turbines are commissioned and exporting energy to shore via the 54km cable.
Source: LogIn
correct
30-Apr-2015 Event Type: Installation - Turbine Installation
Turbine Installation 64 turbines have been installed.
Source: LogIn
correct
17-Mar-2015 Event Type: Installation - Turbine Installation
Turbine Installation 39 of the 78 turbines had been installed, the turbine and cable works are ongoing in tandem.
Source: LogIn
correct
17-Feb-2015 Event Type: Operation - Generating Power
Generating Power Borkum Riffgrund I has fed its first power into the German electricity grid. DolWin Alpha, the HVDC converter station responsible for exporting the power back to shore, will undergo full trial operations in April.
Source: LogIn
correct
02-Feb-2015 Event Type: Installation - Turbine Installation
Turbine Installation Direct communication shows installation is still underway as of 02/02/2015. Only 12 turbines were expected to be installed by the end of 2014.
Source: LogIn
correct
10-Dec-2014 Event Type: Installation - Array Cable Installation
Array Cable Installation CT Offshore installed a total of 44 inter-array cables using the Vessels MV SIA, VOS SYMPATHY and MV SANDER 2.
Source: LogIn
correct
25-Oct-2014 Event Type: Installation - Turbine Installation
Turbine Installation The first of 78 wind turbines was successfully installed at the wind farm on 25/10/2014. This is the very first turbine installed by DONG in German waters.
Source: LogIn
correct
23-Oct-2014 Event Type: Planning - Grid Connection Agreed
Grid Connection Agreed Bnetza released their offshore grid allocation. As DolWin 3 was not over subscribed no private auction as needed. Borkum Riffgrund I was awarded an extra 20.4MW capacity. This takes it up to 112MW on DolWin 3, and 200MW on DolWin 1, totaling its complete 312MW capacity.
Source: LogIn
correct
23-Oct-2014 Event Type: Installation - Turbine Installation
Turbine Installation A2SEA'S SEA INSTALLER arrived at the project site to commence turbine installation activities.
Source: LogIn
correct
15-Sep-2014 Event Type: Installation - Array Cable Installation
Array Cable Installation CT Offshore is scheduled to finish installing 43 array cables. Update 04/09/2014: AIS data shows CLV Sia is still operating within the wind farm.
Source: LogIn
correct
27-Aug-2014 Event Type: Installation - Foundation Installation
Foundation Installation The prototype foundation, Suction Bucket Jacket was installed. DONG Energy cooperated with Carbon Trust Wind Accelerator (OWA) in order to test this foundation. The site was chosen for this due to its sandy seabed which is a challenging environment for this type of foundation.
Source: LogIn
correct
Aug-2014 Event Type: Installation - Turbine Installation
Turbine Installation The turbine installation will be delayed by a few weeks after press reports suggest that Siemens has experienced small delays during manufacturing.
Source: LogIn
correct
29-Jul-2014 Event Type: Installation - Foundation Installation
Foundation Installation The foundation installation was completed. The monopiles weighed between 495 and 684 tonnes, with a diameter of 5.9 and lengths up to 66m. The last foundation a Suction Bucket Jacket will be installed at a later date.
Source: LogIn
correct
07-Jun-2014 Event Type: Installation - Turbine Installation
Turbine Installation Turbine installation vessel SEA INSTALLER arrived at Frederikshavn for mobilisation. The vessel will be fitted with a helipad this month.
Source: LogIn
correct
16-May-2014 Event Type: Installation - Foundation Installation
Foundation Installation 39 foundations (consisting of monopiles and transition pieces) have been installed at the site, with 39 remaining.
Source: LogIn
correct
May-2014 Event Type: Planning - Other Approval
Other Approval BSH grant construction start deadline extension to May 2014.
Source: LogIn
correct
21-Apr-2014 Event Type: Installation - Array Cable Installation
Array Cable Installation Array cable installation began, with the first cable being laid between the substation and first foundation. A total of about 80km of array cable was installed. CT Offshore installed the array cables.
Source: LogIn
correct
14-Mar-2014 Event Type: Installation - Other
Other DONG announced an upgrade in the turbine capacity to 4MW - the rotor diameter remains unchanged. An additional 78th turbine will also be installed testing the new suction bucket foundation.
Source: LogIn
correct
10-Mar-2014 Event Type: Installation - Foundation Installation
Foundation Installation Pacific Orca is on site continuing with foundation installation. All 77 monopiles are scheduled to be installed by the end of May 2014.
Source: LogIn
correct
03-Mar-2014 Event Type: Installation - Foundation Installation
Foundation Installation The first transition piece was installed in mild and calm weather conditions.
Source: LogIn
correct
21-Jan-2014 Event Type: Installation - Foundation Installation
Foundation Installation The first of 77 foundations was installed. The monopiles are 6m in diameter and weigh 750 tonnes. During the installation the noise is reduced by using a double walled system with an internal bubble curtain. The foundations were originally planned for installation in Spring/Summer of 2014, but rescheduled to start in early Winter through a change of installation sequence at the project. The fabrication of the foundations and transition pieces saw major delays (they were originally planned for completion by the end of the 2013) leaving a complex installation sequence with installation being undertaken as they were fabricated.
Source: LogIn
correct
2014 Event Type: Installation - Foundation Installation
Foundation Installation A new demonstration foundation, a Suction Bucket Jacket, will be deployed on one of the turbines. This is part of a deal with the UK Carbon Trust to test new foundations and look to reduce the cost of offshore wind farms.
Source: LogIn
correct
26-Dec-2013 Event Type: Installation - Foundation Installation
Foundation Installation The first load out of the foundations took place and were shipped to Eemshaven which will act as the installation base. The last of the foundations is expected to be shipped by August 2014.
Source: LogIn
correct
12
Add new windfarm events, providing approximate date etc. Possible events include consent submission, approval, installation, generating power etc.

Call +44 (0)1502 307 037 for more information

Keep on top of the market. Perform analysis. Make informed decisions.

CONTACT US

More information?

Receive monthly updates with our Offshore Windfarm Subscription and gain access to even more detailed information on; cabling, converters, costs, foundations, substations, turbines.

Filter :
1234
StatusName
Decommissioned Hooksiel Hooksiel
Fully Commissioned Alpha Ventus Alpha Ventus
Fully Commissioned Amrumbank West Amrumbank West
Fully Commissioned BARD Offshore 1 BARD Offshore 1
Fully Commissioned Borkum Riffgrund 1 Borkum Riffgrund 1
Fully Commissioned Breitling Breitling
Fully Commissioned Butendiek Butendiek
Fully Commissioned DanTysk DanTysk
Fully Commissioned EnBW Baltic 1 EnBW Baltic 1
Fully Commissioned EnBW Baltic 2 EnBW Baltic 2
Fully Commissioned ENOVA Offshore Project Ems Emden ENOVA Offshore Project Ems Emden
Fully Commissioned Global Tech I Global Tech I
Fully Commissioned Gode Wind 1 and 2 Gode Wind 1 and 2
Fully Commissioned Meerwind Süd/Ost Meerwind Süd/Ost
Fully Commissioned Nordergründe Nordergründe
Fully Commissioned Nordsee One Nordsee One
Fully Commissioned Nordsee Ost Nordsee Ost
Fully Commissioned Riffgat Riffgat
Fully Commissioned Sandbank Sandbank
Fully Commissioned Trianel Windpark Borkum I Trianel Windpark Borkum I
Fully Commissioned Veja Mate Veja Mate
Fully Commissioned Wikinger Wikinger
Partial Generation/Under Construction Merkur Merkur
Under Construction Arkona Arkona
Under Construction Borkum Riffgrund 2 Borkum Riffgrund 2
Under Construction Hohe See Hohe See
Under Construction OWP Albatros OWP Albatros
Pre-Construction Deutsche Bucht Deutsche Bucht
Pre-Construction GICON Schwimmendes Offshore Fundament (SOF) Pilot GICON Schwimmendes Offshore Fundament (SOF) Pilot
Pre-Construction Trianel Windpark Borkum II Trianel Windpark Borkum II
Consent Authorised Arcadis Ost 1 Arcadis Ost 1
Consent Authorised Baltic Eagle Baltic Eagle
Consent Authorised Borkum Riffgrund West 2 Borkum Riffgrund West 2
Consent Authorised Borkum Riffgrund West I Borkum Riffgrund West I
Consent Authorised Deutsche Bucht Pilot Park Deutsche Bucht Pilot Park
Consent Authorised EnBW He Dreiht EnBW He Dreiht
Consent Authorised Gode Wind 3 Gode Wind 3
Consent Authorised Gode Wind 4 Gode Wind 4
Consent Authorised Kaskasi Kaskasi
Consent Authorised OWP West OWP West
Consent Authorised Wikinger Süd Wikinger Süd
Consent Application Submitted Gennaker Gennaker
Concept/Early Planning GICON® SOF 6-8MW Test Turbine GICON® SOF 6-8MW Test Turbine
Concept/Early Planning ReaLCoE (Robust, Reliable and Large Offshore Wind Energy Converters for Clean, Low Cost and Competitive Electricity) ReaLCoE (Robust, Reliable and Large Offshore Wind Energy Converters for Clean, Low Cost and Competitive Electricity)
Development Zone Darß - priority area for wind energy Darß - priority area for wind energy
Development Zone German Central Tender 2022 (Assumed North Sea) German Central Tender 2022 (Assumed North Sea)
Development Zone German Central Tender 2023 (Assumed Baltic Sea) German Central Tender 2023 (Assumed Baltic Sea)
Development Zone German Central Tender 2024 (Assumed North Sea) German Central Tender 2024 (Assumed North Sea)
Development Zone German Central Tender 2025 (Assumed North Sea) German Central Tender 2025 (Assumed North Sea)
Development Zone German Central Tender 2026 (Assumed North Sea) German Central Tender 2026 (Assumed North Sea)
1234
Please LogIn to follow projects
Find quick and easy project and company information with our online search tool

Keep on top of the market. Perform analysis. Make informed decisions.

This page is intended to be viewed online and may not be printed without a valid subscription.

Please view this page at https://www.4coffshore.com/windfarms/events.aspx?windfarmID=de04.