Events on Changhua - Taipower Database in Excel
DateEventDescription 
LogIn Event Type: Operation - Fully Commissioned
Fully Commissioned Full commissioning expected by end of December LogIn, according to April LogIn schedule.
Source: LogIn
correct
LogIn Event Type: Operation - Generating Power
Generating Power Test operation of the equipment is targeted to start in the summer of LogIn, and the completion is scheduled for the end of December of the same year.
Source: LogIn
correct
LogIn Event Type: Installation - Offshore Construction Starts
Offshore Construction Starts Foundation installation is to commence early in LogIn, according to Jan De Nul Group and Hitachi, Ltd's April LogIn timetable.
Source: LogIn
correct
May-2018 Event Type: Engineering - Geotechnical Site Investigation
Geotechnical Site Investigation Seabed survey and geotechnical investigation commences in May 2018.
Source: LogIn
correct
29-Apr-2018 Event Type: Planning - Tender Process
Tender Process Jan De Nul Group and Hitachi, Ltd. announced that they have signed the contract with overall work for the manufacturing and installation of 21 5.2MW wind turbines (109.2MW). The work includes design, manufacturing and installation of all foundations and wind turbines as well as maintenance for a period of five years.
Under the Changhua Offshore Wind Farm Project Jan De Nul will be responsible for the foundation design, fabrication and installation, wind turbine installation, supply and installation of cables off- and onshore as well as for the upgrading of the electrical substation. Hitachi will be in charge of manufacturing, assembly, operation and maintenance (O&M), and other work related to the 21 offshore wind turbines with downwind rotor, each with a generation capacity of 5.2MW. Particular feature of the design is that the foundations are designed to withstand cyclonic waves and winds, and earthquake loads.

Source: LogIn
correct
31-Jan-2018 Event Type: Planning - Tender Process
Tender Process EPCI contract to be awarded, following contracting delays (was H1 2017). It is believed only one firm submitted a proposal, this follows three other attempts by Taipower to sign an EPC contractor. Previous attempts were unsuccessful, due to costs being outside budget. Taipower have since increased budget.
Source: LogIn
correct
19-Jan-2018 Event Type: Planning - Tender Process
Tender Process Jan de Nul and Hitachi partnership sign EPC contract, after four bidding rounds, theirs was the only bid. Jan de Nul will be responsible for installation, with Hitachi providing their 5.2 MW turbines. It is expected that official project award will be made on 14th February 2018, after contract review.
Source: LogIn
correct
07-Nov-2017 Event Type: Planning - Tender Process
Tender Process Taipower re-tendering for EPC contractor after previous attempts proved too costly. It has also bee announced that Taipower has increased budget for project .
Source: LogIn
correct
10-Apr-2017 Event Type: Planning - Tender Process
Tender Process Tender documents for EPCI contractor available to view between 10th and 14th of April 2017.
Source: LogIn
correct
20-Dec-2016 Event Type: Planning - Financing Agreement
Financing Agreement Taipower signed an agreement to invest NT$200 billion in solar and offshore wind farms, with Chuanghua County .
Source: LogIn
correct
25-Aug-2016 Event Type: Planning - Strategy or Policy Development
Strategy or Policy Development TAIWAN OFFSHORE WIND STRATEGY UPDATE
Analysis by Taiwan's Industrial Technology Research Institute (ITRI) estimates 1.2GW of wind is feasible in waters shallower than 20m, with a further 5GW in depths of 20m-50m. Supervised by the Bureau of Energy, Taiwan's Thousand Wind Turbine programme is a 3-phased approach to realising this potential via;
1. A short-term target of 4 demonstration offshore wind turbines by 2016
2. A mid-term target of 520MW by 2020 achieved through three demonstration wind farms
3. A long-term target of 3000MW by 2025 achieved through zonal development
In this nascent market, supply constraints are likely to be a challenge to delivering the required compound annual growth rate of installations of around 100%. Additionally, typical project development times of 6-9 years means some capacity will likely be delivered later.
The 2009 Renewable Energy Development act supports annually reviewed feed-in tariffs available as either NT$5.7405(€15.6c)/kWh for 20 years or NT$7.1085(€19.3c)/kWh for the first 10 years followed by NT$3.4586(€9.4c)/kWh for the next 10 years.
36 "Zones of Potential" off the shallower (<50m), resource endowed west coast were identified in July 2015 and are currently being investigated by applicants with the aim of obtaining EIA approval during 2017 for projects in excess of 100MW per zone.
A Strategic Environmental Assessment (SEA) has been completed and approved by the Environmental Protection Administration (EPA) in July 2016. The SEA, which will be used to identify sites for commercial scale wind farms, recognises the need to protect the critically-endangered white dolphin found in the shallow waters of the west coast. The capacity of the zones will be adjusted in accordance with the SEA findings. From 2017 zones will be announced for development, with up to 500-2000MW released every three years and awarded based on qualitative criteria including paid-in capital and financial conditions; consortium composition and capabilities; schedule of development and domestic supply chain benefits.
Strong fundamental forces are driving Taiwan's ambitions. Nuclear power is being phased out and high forest and mountain coverage is constraining onshore wind growth. High wind speeds, manageable distances to shore and water depth, plus strong political support with solid legal and financial institutions provide attractive conditions for investment.

Source: LogIn
correct
31-Dec-2015 Event Type: Planning - Site Investigation
Site Investigation General consulting Contract to be awarded.
Source: LogIn
correct
12-Nov-2015 Event Type: Installation - Met Mast
Met Mast Completion of met mast installation.
Source: LogIn
correct
12-Nov-2015 Event Type: Engineering - Geotechnical Site Investigation
Geotechnical Site Investigation Completion of Met Mast installation.
Source: LogIn
correct
20-Sep-2015 Event Type: Installation - Met Mast
Met Mast Start of Met Mast installation.
Source: LogIn
correct
31-Dec-2014 Event Type: Planning - Other Approval
Other Approval Consent authorised and Environmental Impact Assessment approved. Construction permits still required, but considered a formality, due to project qualifying as a demonstration project
Source: LogIn
correct
06-Sep-2014 Event Type: Planning - Other Approval
Other Approval EIA committee members have passed judgement on EIA, but due to lack of assessment of local fisheries, dolphins and marine ecological impacts, the Panel requires additional documents within three months, for EIA to be reassessed.
Source: LogIn
correct
14-Jan-2013 Event Type: Planning - Financing Agreement
Financing Agreement Runner up in the Offshore Wind Grant scheme by the Bureau of Energy, Taiwan. The grant will provide financial support to a 2 turbine project and 100-200MW project(s).
Source: LogIn
correct
Add new windfarm events, providing approximate date etc. Possible events include consent submission, approval, installation, generating power etc.

Call +44 (0)1502 307 037 for more information

Keep on top of the market. Perform analysis. Make informed decisions.

CONTACT US

More information?

Receive monthly updates with our Offshore Windfarm Subscription and gain access to even more detailed information on; cabling, converters, costs, foundations, substations, turbines.

Filter :
12
StatusName
Fully Commissioned Formosa 1 OWF Phase 1 Formosa 1 OWF Phase 1
Pre-Construction Formosa 1 OWF Phase 2 Formosa 1 OWF Phase 2
Consent Application Submitted Changhua - Taipower Changhua - Taipower
Concept/Early Planning Changfang - (ZoP 27) - CIP Changfang - (ZoP 27) - CIP
Concept/Early Planning Changhua - (ZoP 26) - Taipower Changhua - (ZoP 26) - Taipower
Concept/Early Planning Changhua - (ZoP 28) - Strait Wind Power Changhua - (ZoP 28) - Strait Wind Power
Concept/Early Planning Changhua - South - Taipower Changhua - South - Taipower
Concept/Early Planning Future Zones 1 Future Zones 1
Concept/Early Planning Future Zones 2 Future Zones 2
Concept/Early Planning Future Zones 3 Future Zones 3
Concept/Early Planning Future Zones 4 Future Zones 4
Concept/Early Planning Future Zones 5 Future Zones 5
Concept/Early Planning Greater Changhua North East (ZoP 13) - Ørsted Greater Changhua North East (ZoP 13) - Ørsted
Concept/Early Planning Greater Changhua North West (ZoP 12) - Ørsted Greater Changhua North West (ZoP 12) - Ørsted
Concept/Early Planning Greater Changhua South East (ZoP 15) - Ørsted Greater Changhua South East (ZoP 15) - Ørsted
Concept/Early Planning Greater Changhua South West (ZoP 14) - Ørsted Greater Changhua South West (ZoP 14) - Ørsted
Concept/Early Planning Guanyin (ZoP 2) - wpd Guanyin (ZoP 2) - wpd
Concept/Early Planning Hai Long II - (ZoP 19) - Yushan Energy/Northland Power Hai Long II - (ZoP 19) - Yushan Energy/Northland Power
Concept/Early Planning Hai Long III - (ZoP 18) - Yushan Energy/Northland Power Hai Long III - (ZoP 18) - Yushan Energy/Northland Power
Concept/Early Planning Haiding 1 - (ZoP 11) - Formosa IIII Haiding 1 - (ZoP 11) - Formosa IIII
Concept/Early Planning Haiding 2 - (ZoP 16) - Formosa IIII Haiding 2 - (ZoP 16) - Formosa IIII
Concept/Early Planning Haiding 3 - (ZoP 17) - Formosa IIII Haiding 3 - (ZoP 17) - Formosa IIII
Concept/Early Planning Ideol/CSC - Floating Project Ideol/CSC - Floating Project
Concept/Early Planning Miaoli - (ZoP 5+6) - Formosa II Miaoli - (ZoP 5+6) - Formosa II
Concept/Early Planning Penghu - Taipower Penghu - Taipower
Concept/Early Planning W1S - EOLFI W1S - EOLFI
Concept/Early Planning W2N - EOLFI W2N - EOLFI
Concept/Early Planning W2S - EOLFI W2S - EOLFI
Concept/Early Planning W3 - EOLFI W3 - EOLFI
Concept/Early Planning Xidao - CIP Xidao - CIP
Concept/Early Planning Xinzhu Shi - (ZoP 4) - Asia Cement Corporation Xinzhu Shi - (ZoP 4) - Asia Cement Corporation
Concept/Early Planning Yunlin - wpd Yunlin - wpd
Concept/Early Planning Zhongneng - (ZoP 29) - CSC/CIP/Diamond Generating Asia Zhongneng - (ZoP 29) - CSC/CIP/Diamond Generating Asia
Development Zone Zone of Potential - 33 Zone of Potential - 33
Development Zone Zone of Potential - 34 Zone of Potential - 34
Development Zone Zone of Potential - 35 Zone of Potential - 35
Development Zone Zone of Potential - 36 Zone of Potential - 36
Development Zone Zone of Potential - 7 Zone of Potential - 7
Development Zone Zone of Potential - 8 Zone of Potential - 8
Cancelled Changhua - (ZoP 27) - Strait Wind Power Changhua - (ZoP 27) - Strait Wind Power
Cancelled Changhua - North - Taipower Changhua - North - Taipower
Cancelled Changhua North - wpd Changhua North - wpd
Cancelled Changhua Offshore Pilot Project (COPP) - TGC Changhua Offshore Pilot Project (COPP) - TGC
Cancelled Chiayi - Star Energy Chiayi - Star Energy
Cancelled Fufang - (ZoP 28) - CIP Fufang - (ZoP 28) - CIP
Cancelled Fuhai Offshore Windfarm - TGC Fuhai Offshore Windfarm - TGC
Cancelled Fuhai Phase III - TGC Fuhai Phase III - TGC
Cancelled Hanbao - TGC Hanbao - TGC
Cancelled Offshore Wind Demonstration Penghu Island Offshore Wind Demonstration Penghu Island
Cancelled Penghu - TGC Penghu - TGC
12
Please LogIn to follow projects
Find quick and easy project and company information with our online search tool

Keep on top of the market. Perform analysis. Make informed decisions.

This page is intended to be viewed online and may not be printed without a valid subscription.

Please view this page at https://www.4coffshore.com/windfarms/events.aspx?windfarmID=tw24.