Events on EnBW He Dreiht Database in Excel
DateEventDescription 
LogIn Event Type: Operation - Fully Commissioned
Fully Commissioned EnBW stated that commissioning is currently staged for LogIn, the same year the grid connection (NOR-7-1, BorWin 5) is scheduled to be operational.
Source: LogIn
correct
LogIn Event Type: Installation - Offshore Construction Starts
Offshore Construction Starts Offshore construction start is probable for LogIn based on the current target commissioning date.
Source: LogIn
correct
2018 Event Type: Installation - Other
Other Construction is due to start in 2018 for the Emden service base which will service EnBW's Hohe See, Albatros and He Dreiht wind farms. EnBW plans to build a two story building outfitted with office, social space and a warehouse to store equipment and spare parts. EnBW expects 60 new jobs will be created at the base to oversee the operations and maintenance of the projects.
Source: LogIn
correct
20-Apr-2017 Event Type: Planning - Tender Process
Tender Process Analyst Update:
Results of the April 2017 auction resulted in a significantly lower than expected weighted average award price of €4.40/MWh. The lowest price was zero and the highest €60 MWh. Four bids were accepted totalling 1490MW meaning that the remaining 60MW will carry over to the 1 April 2018 auction for 1610MW.
Winners receive a grid connection, support as bid for 20 years and a permit for 25 years of operation (with the option to extend once by five years). DONG secured three connections in total (240MW on NOR-1-1 for Borkum Borkum Riffgrund West II, 240MW on NOR-1-1 for OWP West and 110MW on NOR-3-3 for Gode Wind 3), with zero-subsidy bids for the projects connecting to NOR-1-1 (Dolwin5) and €60/MWh for Gode Wind 03 which has less economies of scale and connects a year earlier and therefore is considered to have less time to leverage new innovations. It is possible that the €60/MWh bid for Gode Wind 03 was strategically priced, made with the knowledge that there was an opportunity for a top-up project to fill any remaining auction volume that would be exceeded by the lower-priced, larger projects.
EnBW’s 900MW “He Dreiht” also secured a win with zero subsidy, also claiming the advantages of late-commissioning and scale economies. EnBW called for a review of Germany’s offshore wind goals.
DONG has clarified the following details about its transitional auction bids:
- Cluster 1 project (Borkum Riffgrund West II and OWP West) will be built as a single 480MW project using much larger turbines than available (“13-15MW turbines”).
- The transmission assets being out of scope has made a zero-bid possible.
- Cluster 1 has wind speeds in excess of 10m/s and extensive operational synergies with adjacent DONG projects.
- They expect extensive improvement and cost reduction opportunities across the balance of plant between now and 2024 including installation methods, foundations, cables, O&M lifetime etc.
- The allowance of an operational life of 30 years provides further opportunities for cost reduction.
- CAPEX per MW will be significantly lower than DKK 22-24m/MW guide price given in 2016.
- They have used a conservative estimate of German future wholesale price estimates, and added 250 basis points to WACC to account for market exposure.
- The main drivers of long-term energy prices are considered to be EU policy on CO2 prices, phase-out of coal and nuclear and the build-out of renewables. They consider national initiatives rather than regional policy as driving renewables growth. They assume a fast build-out of PV, onshore and offshore wind, all of which exert downward price pressure.
Phase-out of thermal capacity in accordance with national plans is assumed.DONG are also considering the option to lock-in prices through market-base contracts. E.g. corporate PPAs. Also hedging would be used.
- They consider winning the projects as an ‘option’ [albeit at significant cost] to build the windfarm. They may well add to the volume in next year’s tender. They are prepared to not-build the project if it appears to not create value nearer at FID. The cost of this would be €59m.
- The bid was based on a lowest price with no-regrets decision.
- Regarding the subsidy required for Gode Wind 3, it was considered to be built too early for the new turbine platform, and the site has slightly less attractive conditions.

Source: LogIn
correct
13-Apr-2017 Event Type: Planning - Tender Process
Tender Process The Federal Network Agency (Bundesnetzagentur) announced four winners totalling 1490MW as a product of the first WindSeeG tender. EnBW has been successful in its zero-subsidy bid for the 900MW He Dreiht, providing the basis for EnBW's growth beyond 2020. He Dreiht was the largest project to compete in first WindSeeG tender, with its zero-subsidy bid enabled by rapidly advancing technology and due to the project being operated in close proximity to two further EnBW parks. Hohe See, Albatros and He Dreiht, collectively around 1.5GW of offshore capacity, will be realised and operated as one complete unit.
Source: LogIn
correct
30-Jan-2017 Event Type: Planning - Tender Process
Tender Process The Federal Network Agency(Bundesnetzagentur) announce terms of first tender -
- Bids must be below 12 cents(EU) per kilowatt hour. 
- Projects with the lowest bids will win tender award. 
- The network connection capacities for the offshore wind parks will result, among other things, from the offshore network development plan 2025(Offshore-Netzentwicklungsplan 2025), which has been confirmed by the Federal Network Agency.
The first call for tenders covers 1550MWs. It will take place on 1st April 2017 and will apply to projects which are put into operation after 3st1 December 2020. All offshore wind projects which were approved before August 2016 or have an advanced approval permit may participate in the tender. Further requirements concern the location of offshore wind parks within the North Sea and Baltic Sea.
The second tender for offshore wind turbines will take place on 1st April 2018. The tender volume will then also be 1550MWs. The total volume of the tender therefore amounts to 3,100 megawatts, of which at least 500MWs will be built in the Baltic Sea.
The bids must be submitted in writing to the Federal Network Agency in Bonn by 3rd April. 

Source: LogIn
correct
Nov-2016 Event Type: Planning - Tender Process
Tender Process EnBW He Dreiht was one of 31 projects on the BSH's list of identified projects as fulfilling the pre-requisites for upcoming tenders.
Source: LogIn
correct
23-Oct-2014 Event Type: Planning - Grid Connection Other
Grid Connection Other BNetzA confirmed that EnBW He Dreiht have failed to acquire a grid connection in this allocation round. Bnetza rejected the Wind Farm on the basis that it lies in cluster 8 twhere there is no capacity up for auction. The capacity of the project also got increased to 737.8MW.
Source: LogIn
correct
22-Feb-2012 Event Type: Planning - Tender Process
Tender Process Contracting for supply and maintenance of wind turbines removed from initial notice. He Dreiht will now be retendered at a later time.
Source: LogIn
correct
22-Feb-2010 Event Type: Planning - Consent Authorised
Consent Authorised Extension of 39 turbines approved (north part of site).
Source: LogIn
correct
20-Dec-2007 Event Type: Planning - Other Approval
Other Approval Consent authorisation of the original 80 turbines (southern site) was given by the Federal Maritime and Hydrographic Agency of Germany (BSH).
Source: LogIn
correct
11-Feb-2004 Event Type: Planning - Other Application Submitted
Other Application Submitted Ecological compatibility study (UVS) submitted. Project originally expected to be approved in Summer 2004
Source: LogIn
correct
24-Jan-2002 Event Type: Planning - Consent Application Submitted
Consent Application Submitted Date of application.
Source: LogIn
correct
Add new windfarm events, providing approximate date etc. Possible events include consent submission, approval, installation, generating power etc.

Call +44 (0)1502 307 037 for more information

Keep on top of the market. Perform analysis. Make informed decisions.

CONTACT US

More information?

Receive monthly updates with our Offshore Windfarm Subscription and gain access to even more detailed information on; cabling, converters, costs, foundations, substations, turbines.

Filter :
1234
StatusName
Decommissioned Hooksiel Hooksiel
Fully Commissioned Alpha Ventus Alpha Ventus
Fully Commissioned Amrumbank West Amrumbank West
Fully Commissioned BARD Offshore 1 BARD Offshore 1
Fully Commissioned Borkum Riffgrund 1 Borkum Riffgrund 1
Fully Commissioned Breitling Breitling
Fully Commissioned Butendiek Butendiek
Fully Commissioned DanTysk DanTysk
Fully Commissioned EnBW Baltic 1 EnBW Baltic 1
Fully Commissioned EnBW Baltic 2 EnBW Baltic 2
Fully Commissioned ENOVA Offshore Project Ems Emden ENOVA Offshore Project Ems Emden
Fully Commissioned Global Tech I Global Tech I
Fully Commissioned Gode Wind 1 and 2 Gode Wind 1 and 2
Fully Commissioned Meerwind Süd/Ost Meerwind Süd/Ost
Fully Commissioned Nordergründe Nordergründe
Fully Commissioned Nordsee One Nordsee One
Fully Commissioned Nordsee Ost Nordsee Ost
Fully Commissioned Riffgat Riffgat
Fully Commissioned Sandbank Sandbank
Fully Commissioned Trianel Windpark Borkum I Trianel Windpark Borkum I
Fully Commissioned Veja Mate Veja Mate
Fully Commissioned Wikinger Wikinger
Partial Generation/Under Construction Merkur Merkur
Under Construction Arkona Arkona
Under Construction Borkum Riffgrund 2 Borkum Riffgrund 2
Under Construction Hohe See Hohe See
Under Construction OWP Albatros OWP Albatros
Under Construction Trianel Windpark Borkum II Trianel Windpark Borkum II
Pre-Construction Deutsche Bucht Deutsche Bucht
Pre-Construction Deutsche Bucht Pilot Park Deutsche Bucht Pilot Park
Pre-Construction GICON Schwimmendes Offshore Fundament (SOF) Pilot GICON Schwimmendes Offshore Fundament (SOF) Pilot
Consent Authorised Arcadis Ost 1 Arcadis Ost 1
Consent Authorised Baltic Eagle Baltic Eagle
Consent Authorised Borkum Riffgrund West 2 Borkum Riffgrund West 2
Consent Authorised Borkum Riffgrund West I Borkum Riffgrund West I
Consent Authorised EnBW He Dreiht EnBW He Dreiht
Consent Authorised Gode Wind 3 Gode Wind 3
Consent Authorised Gode Wind 4 Gode Wind 4
Consent Authorised Kaskasi Kaskasi
Consent Authorised OWP West OWP West
Consent Authorised Wikinger Süd Wikinger Süd
Consent Application Submitted Gennaker Gennaker
Concept/Early Planning GICON® SOF 6-8MW Test Turbine GICON® SOF 6-8MW Test Turbine
Concept/Early Planning ReaLCoE (Robust, Reliable and Large Offshore Wind Energy Converters for Clean, Low Cost and Competitive Electricity) ReaLCoE (Robust, Reliable and Large Offshore Wind Energy Converters for Clean, Low Cost and Competitive Electricity)
Development Zone Darß - priority area for wind energy Darß - priority area for wind energy
Development Zone German Central Tender 2022 (Assumed North Sea) German Central Tender 2022 (Assumed North Sea)
Development Zone German Central Tender 2023 (Assumed Baltic Sea) German Central Tender 2023 (Assumed Baltic Sea)
Development Zone German Central Tender 2024 (Assumed North Sea) German Central Tender 2024 (Assumed North Sea)
Development Zone German Central Tender 2025 (Assumed North Sea) German Central Tender 2025 (Assumed North Sea)
Development Zone German Central Tender 2026 (Assumed North Sea) German Central Tender 2026 (Assumed North Sea)
1234
Please LogIn to follow projects
Find quick and easy project and company information with our online search tool

Keep on top of the market. Perform analysis. Make informed decisions.

This page is intended to be viewed online and may not be printed without a valid subscription.

Please view this page at https://www.4coffshore.com/windfarms/events.aspx?windfarmID=de19.