Events on Formosa 1 OWF Phase 2

As an Offshore Wind Farm Subscriber, you can follow this project to add it to your dashboard.

Follow this project
Taiwan 120MW Fully Commissioned

login to improve information access

There are three levels of access, Free, Freemium (requires a sign-up – for free – and password access) and “Full” (Password access).
You need Full access to use the ForeSEE interactive system, access reports, updates, notes, news and downloads. Sign up now!

Events overview for Formosa 1 OWF Phase 2

Event Date Event Type Event Description Event Source
Subscribers only field Subscribers only field Subscribers only field Subscribers only field
Freemium Only 2019 Generating Power started commercial operation on 27 December 2019 (... Subscribers only field Subscribers only field
Freemium Only 2019 Other Jan de Nul announced that it had completed its EPC... Subscribers only field Subscribers only field
Freemium Only 2019 Final Testing Correll Services completed the termination and tes... Subscribers only field Subscribers only field
Freemium Only 2019 Final Testing Correll Services has completed its high voltage fi... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine Installation Turbine installation was completed on 9th October ... Subscribers only field Subscribers only field
Freemium Only 2019 Generating Power Formosa 1 Phase 2 generated its first power on Thu... Subscribers only field Subscribers only field
Freemium Only 2019 Foundation Installation Jan De Nul has completed installation of all 20 fo... Subscribers only field Subscribers only field
Freemium Only 2019 Production and Procurement Jumbo completed shipment of transition pieces for ... Subscribers only field Subscribers only field
Freemium Only 2019 Export Cable Installation The three export cables have all been installed, w... Subscribers only field Subscribers only field
Freemium Only 2019 Other Construction update: the Seaway Yudin is currently... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine Installation First turbines was installed by Seajacks Zaratan... Subscribers only field Subscribers only field
Freemium Only 2019 Export Cable Installation The Willem de Vlamingh has begun installing the ex... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine Installation Update: 25th July: first turbine installed.

Upd... Subscribers only field
Subscribers only field
Freemium Only 2019 Array Cable Installation Array cable installation is nearing completion. Th... Subscribers only field Subscribers only field
Freemium Only 2019 Foundation Installation Construction Update: Seaway Yudin is currently ins... Subscribers only field Subscribers only field
Freemium Only 2019 Array Cable Installation The vessel Willem de Vlamingh arrived on site to b... Subscribers only field Subscribers only field
Freemium Only 2019 Foundation Installation Update 31st May: The first foundation and TP was i... Subscribers only field Subscribers only field
Freemium Only 2019 Other Seajacks Zaratan has arrived Taichung Port ready t... Subscribers only field Subscribers only field
Freemium Only 2019 Production and Procurement Turbine nacelles have also arrived in Taichung... Subscribers only field Subscribers only field
Freemium Only 2019 Construction - Seabed Preparation Pre lay grapnel runs along cable routes are underw... Subscribers only field Subscribers only field
Freemium Only 2019 A groundbreaking ceremony was held in Miaoli Count... Subscribers only field Subscribers only field
Freemium Only 2019 Production and Procurement Seajacks Zaratan (turbine installation vessel) has... Subscribers only field Subscribers only field
Freemium Only 2019 Production and Procurement The first shipment of monopiles has arrived at Tai... Subscribers only field Subscribers only field
Freemium Only 2019 Production and Procurement The first turbine components arrived, transported ... Subscribers only field Subscribers only field
Freemium Only 2019 Production and Procurement First Subsea delivered beach landing Cable Protect... Subscribers only field Subscribers only field
Freemium Only 2019 Production and Procurement The 20 foundation monopiles, built for the Formosa... Subscribers only field Subscribers only field
Freemium Only 2019 Ownership Change The European Commission has approved the sale of a... Subscribers only field Subscribers only field
Freemium Only 2019 Seajacks Zaratan is on its way to Netherlands to p... Subscribers only field Subscribers only field
Freemium Only 2019 The project completed a TWD18.7 billion project fi... Subscribers only field Subscribers only field
Freemium Only 2019 FairWind has signed a letter of intent with Siemen... Subscribers only field Subscribers only field
Freemium Only 2018 Site Investigation Deep and IOVTEC conducted a UXO survey onsite, the... Subscribers only field Subscribers only field
Freemium Only 2018 Muehlhan Wind Service will support 20x6MW Siemens ... Subscribers only field Subscribers only field
Freemium Only 2018 Subsidy/PPA Conditionally Secured Haineng Wind Power signed a PPA with Taipower. The... Subscribers only field Subscribers only field
Freemium Only 2018 Palfinger Marine signs a contract with Siemens Gam... Subscribers only field Subscribers only field
Freemium Only 2018 Mott MacDonald is reviewing the design of the proj... Subscribers only field Subscribers only field
Freemium Only 2018 Financial Close Reached financial close receiving support from fin... Subscribers only field Subscribers only field
Freemium Only 2018 Ørsted has taken final investment decision for the... Subscribers only field Subscribers only field
Freemium Only 2018 Financing Agreement  Ørsted’s Board of Directors has approved the inve... Subscribers only field Subscribers only field
Freemium Only 2017 Financing Agreement Developers sign power purchase agreement with Taip... Subscribers only field Subscribers only field
Freemium Only 2017 Other Approval Project has been approval from Environmental Prote... Subscribers only field Subscribers only field
Freemium Only 2017 Tender Process Winners of foundation(EPCI), turbine and cables te... Subscribers only field Subscribers only field
Freemium Only 2017 Ownership Change In January 2017 DONG Energy (35%) and Macquarie Ca... Subscribers only field Subscribers only field
Freemium Only 2016 Strategy or Policy Development TAIWAN OFFSHORE WIND STRATEGY UPDATE
Analysis by ... Subscribers only field
Subscribers only field
Freemium Only 2015 Tender Process ZPMC and Swancor sign framework agreement for supp... Subscribers only field Subscribers only field
Freemium Only 2015 Strategy or Policy Development Project at FEED (Front End Engineering Design) sta... Subscribers only field Subscribers only field
Freemium Only 2013 Other Approval EIA approved.... Subscribers only field Subscribers only field
Freemium Only 2013 Other Approval TGC signed the Grant Scheme (The Offshore Wind Pow... Subscribers only field Subscribers only field
Freemium Only 2013 Financing Agreement Runner up in the Offshore Wind Grant scheme by the... Subscribers only field Subscribers only field