Events overview for Gemini

Event Date Event Type Event Description Event Source
Subscribers only field Subscribers only field Subscribers only field Subscribers only field
Freemium Only 2019 Turbine SkySpecs carried out inspections of the wind turbi... Subscribers only field Subscribers only field
Freemium Only 2018 Northland Power with WNF (the Dutch branch of the ... Subscribers only field Subscribers only field
Freemium Only 2018 Turbine Seajacks Hydra arrived on site to carry out heavy ... Subscribers only field Subscribers only field
Freemium Only 2018 Ownership Change On 26th April 2018 a Luxembourg investment vehicle... Subscribers only field Subscribers only field
Freemium Only 2018 Turbine J/U WIND SERVER worked on the site supporting turb... Subscribers only field Subscribers only field
Freemium Only 2017 Other The offshore wind farm was inaugurated by John Bra... Subscribers only field Subscribers only field
Freemium Only 2017 Fully Commissioned Northland Power Inc confirmed that the 600MW Gemin... Subscribers only field Subscribers only field
Freemium Only 2016 Generating Power All 150 wind turbines produced power simultaneousl... Subscribers only field Subscribers only field
Freemium Only 2016 Other After only six months the onshore base at Eemshave... Subscribers only field Subscribers only field
Freemium Only 2016 Generating Power All 150 wind turbines are connected to the grid an... Subscribers only field Subscribers only field
Freemium Only 2016 Turbine Installation Installation of the last of the 150 Siemens SWT-4.... Subscribers only field Subscribers only field
Freemium Only 2016 Turbine Installation Installation of the 100th Siemens SWT-4.0-130 turb... Subscribers only field Subscribers only field
Freemium Only 2016 Turbine Installation Gemini celebrated installation of the 75th Siemens... Subscribers only field Subscribers only field
Freemium Only 2016 Turbine Installation Gemini celebrated installation of the 50th Siemens... Subscribers only field Subscribers only field
Freemium Only 2016 Array Cable Installation Cable lay vessel Nexus finished laying the 150 inf... Subscribers only field Subscribers only field
Freemium Only 2016 Array Cable Installation Jan Steen arrived back on site to re-commence arra... Subscribers only field Subscribers only field
Freemium Only 2016 Generating Power The first turbines are installed and producing pow... Subscribers only field Subscribers only field
Freemium Only 2016 Turbine Installation Installation of the first Siemens 4MW turbine was ... Subscribers only field Subscribers only field
Freemium Only 2016 Turbine Installation Aeolus left Esbjerg with six turbines on board and... Subscribers only field Subscribers only field
Freemium Only 2016 Other FoundOcean completed the grouting of the foundatio... Subscribers only field Subscribers only field
Freemium Only 2015 Export Cable Installation Fugro recently completed the burial of the export ... Subscribers only field Subscribers only field
Freemium Only 2015 Array Cable Installation 100 array cables have been laid since the start of... Subscribers only field Subscribers only field
Freemium Only 2015 Foundation Installation All 150 foundations and transition pieces are now ... Subscribers only field Subscribers only field
Freemium Only 2015 Offshore Substation Van Oord successfully installed the second substat... Subscribers only field Subscribers only field
Freemium Only 2015 Foundation Installation 80 monopile foundations and 77 transition pieces w... Subscribers only field Subscribers only field
Freemium Only 2015 Offshore Substation The first offshore transformer station was placed ... Subscribers only field Subscribers only field
Freemium Only 2015 Offshore Substation The FICG consortium of Cofely Fabricom, Iemants an... Subscribers only field Subscribers only field
Freemium Only 2015 Other Installation of Tekmar Energy's TekLink cable prot... Subscribers only field Subscribers only field
Freemium Only 2015 Foundation Installation The second jacket foundation for the offshore subs... Subscribers only field Subscribers only field
Freemium Only 2015 Foundation Installation The first jacket foundation for the offshore subst... Subscribers only field Subscribers only field
Freemium Only 2015 Foundation Installation The jacket foundations that will support the offsh... Subscribers only field Subscribers only field
Freemium Only 2015 Export Cable Installation Main offshore export cable work started in July.... Subscribers only field Subscribers only field
Freemium Only 2015 Foundation Installation The vessel Aeolus successfully installed the first... Subscribers only field Subscribers only field
Freemium Only 2015 Other Grouting for the project began in June.... Subscribers only field Subscribers only field
Freemium Only 2015 Production and Procurement Component fabrication is well underway and making ... Subscribers only field Subscribers only field
Freemium Only 2015 Construction - Seabed Preparation Shallow water cable works started in March 2015 wi... Subscribers only field Subscribers only field
Freemium Only 2014 Other Gemini onshore substation was started.... Subscribers only field Subscribers only field
Freemium Only 2014 Financial Close Financial close occurred for the EUR2.8 billion pr... Subscribers only field Subscribers only field
Freemium Only 2014 Onshore Construction Starts On the day that the financial close was announced ... Subscribers only field Subscribers only field
Freemium Only 2014 Financing Agreement Accessed its term facility for the full $250 milli... Subscribers only field Subscribers only field
Freemium Only 2014 Other Approval DELTA has agreed to purchase 85% of the power with... Subscribers only field Subscribers only field
Freemium Only 2014 Financing Agreement Northland Power increased its corporate credit fac... Subscribers only field Subscribers only field
Freemium Only 2014 Production and Procurement NKT Cables commenced production of the export cabl... Subscribers only field Subscribers only field
Freemium Only 2014 Financing Agreement The project has received EUR 1,094 million in seni... Subscribers only field Subscribers only field
Freemium Only 2014 Financing Agreement Financial close is now being executed after a deal... Subscribers only field Subscribers only field
Freemium Only 2013 Consent Authorised Due to complete re-design of the project, which re... Subscribers only field Subscribers only field
Freemium Only 2013 Financing Agreement 200 million EUR subordinated loan has been fully s... Subscribers only field Subscribers only field
Freemium Only 2013 Ownership Change The owners of the project have been announced and ... Subscribers only field Subscribers only field
Freemium Only 2013 Financing Agreement European Investment Bank approves a loan of EUR 50... Subscribers only field Subscribers only field
Freemium Only 2012 Financing Agreement European Investment Bank (EIB) currently appraisin... Subscribers only field Subscribers only field
Freemium Only 2012 Financing Agreement Typhoon, who are still in the process of raising t... Subscribers only field Subscribers only field
Freemium Only 2012 Tender Process Siemens Wind Power were selected as the preferred ... Subscribers only field Subscribers only field
Freemium Only 2012 Other Approval The government has extended the length of the perm... Subscribers only field Subscribers only field
Freemium Only 2011 Ownership Change Buitengaats, Clearcamp and ZeeEnergie fully acquir... Subscribers only field Subscribers only field
Freemium Only 2010 Financing Agreement SDE Grant Awarded. The agreements for Buitengaats ... Subscribers only field Subscribers only field
Freemium Only 2010 Other Approval Implementing agreement signed.... Subscribers only field Subscribers only field
Freemium Only 2009 Consent Authorised Consent was authorised.... Subscribers only field Subscribers only field
Freemium Only 2009 Consent Application Submitted Application submitted. Typhoon Offshore starts dev... Subscribers only field Subscribers only field