Add new windfarm events, providing approximate date etc. Possible events include consent submission, approval, installation, generating power etc.
Events on Gode Wind 1 and 2 Database in Excel
12
DateEventDescription 
LogIn Event Type: Operation - Service Agreement Expires
Service Agreement Expires The five-year OEM service agreement is set to expire around this date.
Source: LogIn
correct
26-Jun-2017 Event Type: Other -
Other The wind farm was inaugurated at the Royal Danish Embassy in Berlin.
Source: LogIn
correct
10-Jan-2017 Event Type: Incident - Health and Safety
Health and Safety An unexploded WWII sea mine was discovered floating near the Gode Wind 2 site. The mine was recovered by the vessel Mellum and taken towards land where it was destroyed.
Source: LogIn
correct
08-Jan-2017 Event Type: Operation - Fully Commissioned
Fully Commissioned Due to an onshore cable fault, DolWin2 (and hence Gode Wind 1 and 2) cables were reconnected on 8th January 2017, the reconnection took place more than 11 weeks earlier than the expected date of 27 March 2017.
Source: LogIn
correct
25-Oct-2016 Event Type: Other -
Other DONG Energy announced that it has successfully commissioned its 1,000th offshore wind turbine. The turbine is installed at the Gode Wind 2 project site.
Source: LogIn
correct
30-Sep-2016 Event Type: Other -
Other Full commissioning of Gode Wind 1 and 2 was expected to complete during Q3 2016 (more specifically Gode Wind 1 will be commissioned in Q3 2016, while Gode Wind 2 is to be commissioned in Q2 2016). This won't happen until DolWin2 has been fully commissioned, meaning the project's fully commissioned date will be delayed until Spring 2017.
Source: LogIn
correct
28-Jun-2016 Event Type: Other -
Other Repeated failure with DolWin Beta's connection means the switching on of AC138 and AC139 (Gode Wind 2) has been postponed until the fault has been rectified.
Once DolWin Beta's connection is restored, DONG Energy will continue its 240 hour testing phase. Delays caused by TenneT in installing and commissioning the offshore transmission assets resulted in the postponement of first power and turbine commissioning. Compensations for lost production will be covered by TenneT.

Source: LogIn
correct
19-May-2016 Event Type: Installation - Turbine Installation
Turbine Installation Installation of all 97 turbines complete.
Source: LogIn
correct
04-Apr-2016 Event Type: Installation - Turbine Installation
Turbine Installation Installation of 76th Siemens SWT-6.0-154 turbine. 21 left to install.
Source: LogIn
correct
26-Feb-2016 Event Type: Installation - Array Cable Installation
Array Cable Installation CT Offshore installed the last array cable. The project team installed 97 array cables using their new purpose built subsea trencher ROV, the CTO 107-1100, operating from the CLV Sia.
Source: LogIn
correct
11-Feb-2016 Event Type: Operation - Generating Power
Generating Power The Gode Wind 2 section of the wind farm began transporting power to DolWin2 offshore converter and then the German national grid according to TenneT's transparency overview.
Source: LogIn
correct
29-Jan-2016 Event Type: Installation - Turbine Installation
Turbine Installation Installation of 48 of the Siemens SWT-6.0-154 turbines has been completed.
Source: LogIn
correct
29-Jan-2016 Event Type: Installation - Array Cable Installation
Array Cable Installation Installation of 93 array cables by CT Offshore.
Source: LogIn
correct
22-Dec-2015 Event Type: Installation - Export Cable Installation
Export Cable Installation Ocean Installer announced they won a contract for the recovery of 2 pre-laid HVAC export cables in the 500m zone of the substation. The contract also includes the relay of the cable, installation of the centralizer cable protection system and pull-in to the offshore substation.
Source: LogIn
correct
30-Nov-2015 Event Type: Installation - Turbine Installation
Turbine Installation 36 turbines installed, with installation of 37th ongoing.
Source: LogIn
correct
22-Sep-2015 Event Type: Installation - Foundation Installation
Foundation Installation FoundOcean has completed grouting of the 97 XL monopile foundations and is the latest wind farm to fix its foundations using the MasterFlow 9500 material from BASF. The MasterFlow 9500 was chosen due to its mechanical properties which includes high early strengths, volume stability and longterm durability.
Source: LogIn
correct
16-Sep-2015 Event Type: Installation - Foundation Installation
Foundation Installation The final foundation was installed. The 97 monopiles and transition pieces took around five months to complete.
Source: LogIn
correct
08-Aug-2015 Event Type: Installation - Turbine Installation
Turbine Installation The first turbine was installed in the early hours.
Source: LogIn
correct
03-Aug-2015 Event Type: Installation - Turbine Installation
Turbine Installation The SEA CHALLENGER began load out of the first batch of 6MW turbines.
Source: LogIn
correct
03-Jul-2015 Event Type: Installation - Foundation Installation
Foundation Installation GeoSea had successfully installed all 42 foundations in the Gode Wind 2 section and 8 monopiles in Gode Wind 1.
Source: LogIn
correct
29-Jun-2015 Event Type: Installation - Other
Other A2SEA's SEA CHALLENGER began mobilisation in Esbjerg, Denmark. Mobilisation works will include installing sea fastenings for turbine components, an extension of the main crane boom and installation of a helideck.
Source: LogIn
correct
22-Jun-2015 Event Type: Installation - Offshore Substation
Offshore Substation Installation of the offshore substations for Gode Wind 1 and 2 was completed. This is the first time DONG Energy has installed two platforms for one site.
Source: LogIn
correct
22-Jun-2015 Event Type: Installation - Foundation Installation
Foundation Installation 42 monopile foundations and transition pieces were installed.
Source: LogIn
correct
12-Jun-2015 Event Type: Installation - Array Cable Installation
Array Cable Installation Total of three array cables installed at Gode Wind 2 site.
Source: LogIn
correct
08-Jun-2015 Event Type: Installation - Array Cable Installation
Array Cable Installation The array cable installation and burial operations began on 09/06/2015. CT Offshore used the vessel SIA and their new trencher ROV CTO 107-1100. The first array cables were installed within the Gode Wind 2 section.
Source: LogIn
correct
14-Apr-2015 Event Type: Installation - Foundation Installation
Foundation Installation Offshore construction for Gode Wind 1 and 2 started with the installation of the first monopile.
Source: LogIn
correct
21-Mar-2015 Event Type: Engineering - Production and Procurement
Production and Procurement At 04:40 am on 21/03/2015, the first loadout of four anode cages and transition pieces for Gode Wind 1 and 2 offshore wind farm were finished in approximately 16 hours.
Source: LogIn
correct
19-Dec-2014 Event Type: Engineering - Production and Procurement
Production and Procurement The first transition pieces have been fabricated and are lining up at the harbour at Bladt Industries' facilities in Aalborg. 13 of the total 97 transition pieces for Gode Wind 1 and 2 were upended.
Source: LogIn
correct
18-Nov-2013 Event Type: Planning - Financial Close
Financial Close DONG announced its intention to build Gode Wind 1 and 2 with construction representing a total investment of approximately 2.2 billion EUR.
Source: LogIn
correct
31-Jul-2013 Event Type: Planning - Other Approval
Other Approval An Amendment Notice was published by BSH following a decision to allow Gode Wind II to be split in to Gode Wind 2 and Gode Wind 4, each consisting of 42 turbines and one substation.
Source: LogIn
correct
12
Add new windfarm events, providing approximate date etc. Possible events include consent submission, approval, installation, generating power etc.

Call +44 (0)1502 307 037 for more information

Keep on top of the market. Perform analysis. Make informed decisions.

CONTACT US

More information?

Receive monthly updates with our Offshore Windfarm Subscription and gain access to even more detailed information on; cabling, converters, costs, foundations, substations, turbines.

Filter :
1234
StatusName
Decommissioned Hooksiel Hooksiel
Fully Commissioned Alpha Ventus Alpha Ventus
Fully Commissioned Amrumbank West Amrumbank West
Fully Commissioned BARD Offshore 1 BARD Offshore 1
Fully Commissioned Borkum Riffgrund 1 Borkum Riffgrund 1
Fully Commissioned Breitling Breitling
Fully Commissioned Butendiek Butendiek
Fully Commissioned DanTysk DanTysk
Fully Commissioned EnBW Baltic 1 EnBW Baltic 1
Fully Commissioned EnBW Baltic 2 EnBW Baltic 2
Fully Commissioned ENOVA Offshore Project Ems Emden ENOVA Offshore Project Ems Emden
Fully Commissioned Global Tech I Global Tech I
Fully Commissioned Gode Wind 1 and 2 Gode Wind 1 and 2
Fully Commissioned Meerwind Süd/Ost Meerwind Süd/Ost
Fully Commissioned Nordergründe Nordergründe
Fully Commissioned Nordsee One Nordsee One
Fully Commissioned Nordsee Ost Nordsee Ost
Fully Commissioned Riffgat Riffgat
Fully Commissioned Sandbank Sandbank
Fully Commissioned Trianel Windpark Borkum I Trianel Windpark Borkum I
Fully Commissioned Veja Mate Veja Mate
Fully Commissioned Wikinger Wikinger
Partial Generation/Under Construction Merkur Merkur
Under Construction Arkona Arkona
Under Construction Borkum Riffgrund 2 Borkum Riffgrund 2
Under Construction Hohe See Hohe See
Under Construction OWP Albatros OWP Albatros
Under Construction Trianel Windpark Borkum II Trianel Windpark Borkum II
Pre-Construction Deutsche Bucht Deutsche Bucht
Pre-Construction GICON Schwimmendes Offshore Fundament (SOF) Pilot GICON Schwimmendes Offshore Fundament (SOF) Pilot
Consent Authorised Arcadis Ost 1 Arcadis Ost 1
Consent Authorised Baltic Eagle Baltic Eagle
Consent Authorised Borkum Riffgrund West 2 Borkum Riffgrund West 2
Consent Authorised Borkum Riffgrund West I Borkum Riffgrund West I
Consent Authorised Deutsche Bucht Pilot Park Deutsche Bucht Pilot Park
Consent Authorised EnBW He Dreiht EnBW He Dreiht
Consent Authorised Gode Wind 3 Gode Wind 3
Consent Authorised Gode Wind 4 Gode Wind 4
Consent Authorised Kaskasi Kaskasi
Consent Authorised OWP West OWP West
Consent Authorised Wikinger Süd Wikinger Süd
Consent Application Submitted Gennaker Gennaker
Concept/Early Planning GICON® SOF 6-8MW Test Turbine GICON® SOF 6-8MW Test Turbine
Concept/Early Planning ReaLCoE (Robust, Reliable and Large Offshore Wind Energy Converters for Clean, Low Cost and Competitive Electricity) ReaLCoE (Robust, Reliable and Large Offshore Wind Energy Converters for Clean, Low Cost and Competitive Electricity)
Development Zone Darß - priority area for wind energy Darß - priority area for wind energy
Development Zone German Central Tender 2022 (Assumed North Sea) German Central Tender 2022 (Assumed North Sea)
Development Zone German Central Tender 2023 (Assumed Baltic Sea) German Central Tender 2023 (Assumed Baltic Sea)
Development Zone German Central Tender 2024 (Assumed North Sea) German Central Tender 2024 (Assumed North Sea)
Development Zone German Central Tender 2025 (Assumed North Sea) German Central Tender 2025 (Assumed North Sea)
Development Zone German Central Tender 2026 (Assumed North Sea) German Central Tender 2026 (Assumed North Sea)
1234
Please LogIn to follow projects
Find quick and easy project and company information with our online search tool

Keep on top of the market. Perform analysis. Make informed decisions.

This page is intended to be viewed online and may not be printed without a valid subscription.

Please view this page at https://www.4coffshore.com/windfarms/events.aspx?windfarmID=de13.