LogIn Event Type: Operation - Service Agreement Expires
Service Agreement Expires The ten-year OEM service agreement is expected to expire.
Source: LogIn
correct
17-May-2018 Event Type: Planning - Financing Agreement
Financing Agreement Triodos Bank has invested in the Nordsee 1 offshore wind farm as a new lender due to a sell-down of Rabobank. The sub-investment is in the mid-double-digit million.
Source: LogIn
correct
03-Apr-2018 Event Type: Planning - Tender Process
Tender Process Nordsee One GmbH published a tender for recurring repair and maintenance services for the turbine nacelles and blades; deadline for submissions is 3rd April. The contract duration is 4 years.
Source: LogIn
correct
27-Feb-2018 Event Type: Planning - Tender Process
Tender Process Nordsee One GmbH published a tender for recurring repair and maintenance services for the turbine nacelles and blades; deadline for submissions is 3rd April. The contract duration is 4 years.
Source: LogIn
correct
20-Dec-2017 Event Type: Operation - Fully Commissioned
Fully Commissioned Nordsee One offshore wind farm started commercial operation on the 20th December 2017.
The project was fully commissioned on schedule and below its total budget of €1.2 billion.

Source: LogIn
correct
13-Oct-2017 Event Type: Other -
Other innogy placed the first German corporate Green Bond worth $850m on 13th Oct 2017. innogy’s inaugural Green Bond is an interest-bearing security, whose issue proceeds are used to refinance sustainable projects. The proceeds of innogy´s first Green Bond will be used to refinance four offshore projects in the UK and Germany. Direct communication with innogy confirmed these projects are:
Nordsee Ost (in operation, 295MW, GER, innogy SE share 100%)
Gwynt y Môr (in operation, 576 MW, UK, innogy SE share 50%)
Nordsee One (under construction, 332MW, GER, innogy SE share 15%)
Galloper (under construction, 336MW, UK, innogy SE share 25%)

Source: LogIn
correct
22-Sep-2017 Event Type: Installation - Turbine Installation
Turbine Installation All 54 turbines have now been installed. During the process the turbines were stored, pre-assembled and loaded onto the installation vessel“MPI Enterprise” from the Dutch base port located in Eemshaven.
Source: LogIn
correct
31-Aug-2017 Event Type: Installation - Turbine Installation
Turbine Installation 52 of the 54 turbines have been installed.
Source: LogIn
correct
09-Aug-2017 Event Type: Installation - Turbine Installation
Turbine Installation 44 of the 54 wind turbines have now been installed since installation began in March. Installation and commissioning continues simultaneously and is expected to be completed by the end of the year.
Source: LogIn
correct
28-Jun-2017 Event Type: Installation - Turbine Installation
Turbine Installation Turbine installation reaches halfway point. 27 of the 54 turbines have now been installed and generating power. Full commissioning expected by end of 2017
Source: LogIn
correct
15-Jun-2017 Event Type: Installation - Grid Connection Available
Grid Connection Available ABB handed the DolWin2 converter station over to TenneT during mid 2017. The completion of the grid connection was delayed due to a problem with an onshore cable. ABB finished cable repairs ahead of schedule but TenneT had to make sure the system was stable before proceeding with full commissioning.
Source: LogIn
correct
17-May-2017 Event Type: Installation - Turbine Installation
Turbine Installation A total of 20 of the 54 Senvion 6.2M126 wind turbines have been installed at the project.
Source: LogIn
correct
31-Mar-2017 Event Type: Operation - Generating Power
Generating Power The first kilowatt-hour was exported to the grid. The first 6.2M Senvion turbine was installed on 7th March.
Source: LogIn
correct
07-Mar-2017 Event Type: Installation - Turbine Installation
Turbine Installation The first Senvion 6.2M-126 turbine was installed by the MPI Enterprise. The construction activities will last until approximately Aug-2017.
Source: LogIn
correct
21-Sep-2016 Event Type: Other -
Other The operations and maintenance base at Norddeich was inaugurated. The Nordsee One team will monitor the project from this location.
Source: LogIn
correct
06-Sep-2016 Event Type: Installation - Array Cable Installation
Array Cable Installation Siem Offshore Contractors confirmed that all 70km of the inter-array grid cables at Nordsee One have now been installed, terminated, trenched and tested three weeks ahead of schedule.
Source: LogIn
correct
02-Sep-2016 Event Type: Installation - Export Cable Installation
Export Cable Installation The vessels Siem Aimery and Siem Moxie began the installation of the first export cable.
Source: LogIn
correct
22-Aug-2016 Event Type: Installation - Array Cable Installation
Array Cable Installation Siem completed the inter-array cable installation at the project site. The vessels Siem Aimery and Siem Moxie then moved on to installing the export cable.
Source: LogIn
correct
14-Jul-2016 Event Type: Installation - Offshore Substation
Offshore Substation The topside of the substation was placed on the foundation. The three day journey began in Aalborg, Denmark.
Source: LogIn
correct
08-Jul-2016 Event Type: Installation - Offshore Substation
Offshore Substation Nordsee One substation is ready to be sailed to its final destination in the German Bight. The substation was finished on time and on budget.
Source: LogIn
correct
31-May-2016 Event Type: Installation - Array Cable Installation
Array Cable Installation Siem Moxie arrived at the project site to carry out the array cable installation. The Siem Aimery arrived a day later to be part of the array cable installation, by providing cable pull-in, termination and testing.
Source: LogIn
correct
10-May-2016 Event Type: Installation - Offshore Substation
Offshore Substation The jacket foundation for the offshore substation, weighing more than 1,400 tons, has been successfully placed on the seabed. The foundation travelled from Aalborg in Denmark from where it set sail for a five-day journey across the North Sea to the port of Eemshaven in the Netherlands. The 50m tall foundation was anchored with four piles on the four pedestals at the bottom of the sea: each pile weighs over 240 tons and has a length of over 67m.
Source: LogIn
correct
03-May-2016 Event Type: Installation - Offshore Substation
Offshore Substation The heavy lift vessel Rambiz 3000 arrived on site to install the substation's jacket foundation.
Source: LogIn
correct
16-Apr-2016 Event Type: Installation - Foundation Installation
Foundation Installation All 54 foundations, including monopiles and transition pieces were installed six weeks ahead of schedule. Each monopile is around 70 metres tall and weighs approximately 900 tons.
Source: LogIn
correct
07-Mar-2016 Event Type: Installation - Foundation Installation
Foundation Installation GeoSea installed the 27th monopile and corresponding transition piece.
Source: LogIn
correct
23-Jan-2016 Event Type: Installation - Foundation Installation
Foundation Installation Tenth foundation completed.
Source: LogIn
correct
14-Dec-2015 Event Type: Installation - Foundation Installation
Foundation Installation The first monopile was installed months ahead of the indicative timetable. Original offshore construction was expected to begin in the first quarter of 2016.
Source: LogIn
correct
21-Nov-2015 Event Type: Planning - Tender Process
Tender Process Nordsee One GmbH put out a tender for "Maintenance and inspection of all structural works on one offshore substation incl. jacket foundation, and 54 wind turbine generators' monopile foundations". The contract will be a fixed term of 5 years commencing in November 2017.
Source: LogIn
correct
19-Mar-2015 Event Type: Planning - Financial Close
Financial Close Northland Power Inc and RWE Innogy announced that the EUR 1.2bn Nordsee One Wind Farm has reached financial close. Approximately 70% of the project’s required costs will be provided from an €840 million non-recourse secured construction and term loan and related loan facilities from ten international commercial lenders. Reflecting the strength of Nordsee One, the financing was oversubscribed. The lending group includes ABN AMRO, Bank of Montreal, Commerzbank, Export Development Canada, Helaba, KfW IPEX, National Bank of Canada, Natixis, Rabobank and The Bank of Tokyo-Mitsubishi. Originally due in 2012 the decision to build the project was then scheduled for 2013. The reason for the delay was that the developer was waiting for the government to confirm who will pay for connection delays.
Nordsee One will opt for the Accelerated Model regarding subsidy payments for the wind farm's power generation. The project will receive: €194/MWh for the first eight years, €154/MWh for an additional 1.6 years, then the greater of the local market price of €39/MWh for remaining 9.6 to 20 years of operation. The additional 1.6 years of €154/MWh is an extension of subsidy calculated according to Nordsee One's distance between the system and coast (for every full nautical mile over twelve) and water depth (for each full metre exceeding 20 metres).

Source: LogIn
correct
05-Mar-2015 Event Type: Planning - Financing Agreement
Financing Agreement Northland has raised $231m through a public offering and $50m through a private placement. Part of the proceeds will be used to fund a portion of Northland's investments in the Nordsee One project.
Source: LogIn
correct
12
Add new windfarm events, providing approximate date etc. Possible events include consent submission, approval, installation, generating power etc.

Call +44 (0)1502 307 037 for more information

Keep on top of the market. Perform analysis. Make informed decisions.

CONTACT US

More information?

Receive monthly updates with our Offshore Windfarm Subscription and gain access to even more detailed information on; cabling, converters, costs, foundations, substations, turbines.

Filter :
1234
StatusName
Decommissioned Hooksiel Hooksiel
Fully Commissioned Alpha Ventus Alpha Ventus
Fully Commissioned Amrumbank West Amrumbank West
Fully Commissioned BARD Offshore 1 BARD Offshore 1
Fully Commissioned Borkum Riffgrund 1 Borkum Riffgrund 1
Fully Commissioned Breitling Breitling
Fully Commissioned Butendiek Butendiek
Fully Commissioned DanTysk DanTysk
Fully Commissioned EnBW Baltic 1 EnBW Baltic 1
Fully Commissioned EnBW Baltic 2 EnBW Baltic 2
Fully Commissioned ENOVA Offshore Project Ems Emden ENOVA Offshore Project Ems Emden
Fully Commissioned Global Tech I Global Tech I
Fully Commissioned Gode Wind 1 and 2 Gode Wind 1 and 2
Fully Commissioned Meerwind Süd/Ost Meerwind Süd/Ost
Fully Commissioned Nordergründe Nordergründe
Fully Commissioned Nordsee One Nordsee One
Fully Commissioned Nordsee Ost Nordsee Ost
Fully Commissioned Riffgat Riffgat
Fully Commissioned Sandbank Sandbank
Fully Commissioned Trianel Windpark Borkum I Trianel Windpark Borkum I
Fully Commissioned Veja Mate Veja Mate
Fully Commissioned Wikinger Wikinger
Partial Generation/Under Construction Merkur Merkur
Under Construction Arkona Arkona
Under Construction Borkum Riffgrund 2 Borkum Riffgrund 2
Under Construction Hohe See Hohe See
Under Construction OWP Albatros OWP Albatros
Pre-Construction Deutsche Bucht Deutsche Bucht
Pre-Construction GICON Schwimmendes Offshore Fundament (SOF) Pilot GICON Schwimmendes Offshore Fundament (SOF) Pilot
Pre-Construction Trianel Windpark Borkum II Trianel Windpark Borkum II
Consent Authorised Arcadis Ost 1 Arcadis Ost 1
Consent Authorised Baltic Eagle Baltic Eagle
Consent Authorised Borkum Riffgrund West 2 Borkum Riffgrund West 2
Consent Authorised Borkum Riffgrund West I Borkum Riffgrund West I
Consent Authorised Deutsche Bucht Pilot Park Deutsche Bucht Pilot Park
Consent Authorised EnBW He Dreiht EnBW He Dreiht
Consent Authorised Gode Wind 3 Gode Wind 3
Consent Authorised Gode Wind 4 Gode Wind 4
Consent Authorised Kaskasi Kaskasi
Consent Authorised OWP West OWP West
Consent Authorised Wikinger Süd Wikinger Süd
Consent Application Submitted Gennaker Gennaker
Concept/Early Planning GICON® SOF 6-8MW Test Turbine GICON® SOF 6-8MW Test Turbine
Concept/Early Planning ReaLCoE (Robust, Reliable and Large Offshore Wind Energy Converters for Clean, Low Cost and Competitive Electricity) ReaLCoE (Robust, Reliable and Large Offshore Wind Energy Converters for Clean, Low Cost and Competitive Electricity)
Development Zone Darß - priority area for wind energy Darß - priority area for wind energy
Development Zone German Central Tender 2022 (Assumed North Sea) German Central Tender 2022 (Assumed North Sea)
Development Zone German Central Tender 2023 (Assumed Baltic Sea) German Central Tender 2023 (Assumed Baltic Sea)
Development Zone German Central Tender 2024 (Assumed North Sea) German Central Tender 2024 (Assumed North Sea)
Development Zone German Central Tender 2025 (Assumed North Sea) German Central Tender 2025 (Assumed North Sea)
Development Zone German Central Tender 2026 (Assumed North Sea) German Central Tender 2026 (Assumed North Sea)
1234
Please LogIn to follow projects
Find quick and easy project and company information with our online search tool

Keep on top of the market. Perform analysis. Make informed decisions.

This page is intended to be viewed online and may not be printed without a valid subscription.

Please view this page at https://www.4coffshore.com/windfarms/events.aspx?windfarmID=de28.