DateEventDescription 
LogIn Event Type: Operation - Service Agreement Expires
Service Agreement Expires OMM's 5 year cable repair and maintenance contract runs out.
Source: LogIn
correct
LogIn Event Type: Operation - Service Agreement Expires
Service Agreement Expires The five-year OEM service agreement will expire.
Source: LogIn
correct
15-Nov-2017 Event Type: Incident - Health and Safety
Health and Safety A fire broke out in the engine room of the wind farm service vessel World Calima whilst it was servicing the Nordsee Ost offshore wind farm. A distress signal was hailed at around 8:20am after the vessels' crew noticed heavy smoke. The fire was controlled with on-board resources by locking the engine room and flooding it with carbon dioxide. Another nearby wind farm service vessel, Windea Two assisted the World Calima, manoeuvring the vessel out of the wind farm to avoid a collision with the turbines. The rescue vessel, HERMANN MARWED arrived at 9.40am to assist. About 15 minutes later, a four-ship NATO naval unit followed. The rescuers determined that German mine-hunting boat Sulzbach-Rosenbergwould stay on the scene to assists with the vessels safe tow to shore. A daughter vessel of the HERMANN MARWEDE transferred the eight wind farm technicians and put them on the sea rescue cruiser. The vessels arrived in Helgoland at 4:45pm and the fire was confirmed to be extinguished.
Source: LogIn
correct
13-Oct-2017 Event Type: Other -
Other innogy placed the first German corporate Green Bond worth $850m on 13th Oct 2017. innogy’s inaugural Green Bond is an interest-bearing security, whose issue proceeds are used to refinance sustainable projects. The proceeds of innogy´s first Green Bond will be used to refinance four offshore projects in the UK and Germany. Direct communication with innogy confirmed these projects are:
Nordsee Ost (in operation, 295MW, GER, innogy SE share 100%)
Gwynt y Môr (in operation, 576 MW, UK, innogy SE share 50%)
Nordsee One (under construction, 332MW, GER, innogy SE share 15%)
Galloper (under construction, 336MW, UK, innogy SE share 25%)

Source: LogIn
correct
29-Sep-2016 Event Type: Planning - Other Approval
Other Approval DNV GL awarded innogy SE with the project certificate for its project at the WindEnergy Hamburg exhibition. The certification was carried out according to the German Federal Maritime and Hydrographic Agency (BSH – Bundesamt für Seeschifffahrt und Hydrographie) standard, and covers all stages of the project development from design planning to commissioning.
Source: LogIn
correct
13-May-2016 Event Type: Operation - Performance Monitoring
Performance Monitoring Nordsee Ost has fed 1TWh into the grid since it began operation.
Source: LogIn
correct
24-Nov-2015 Event Type: Operation - Performance Monitoring
Performance Monitoring Due to strong winds of up to 27m/s, the wind farm has managed to export full capacity for the first time. Nordsee Ost produced 6,500 MWh of energy in just a single day, enough power to support 320,000 households.
Source: LogIn
correct
25-Jun-2015 Event Type: Failure - Turbine
Turbine Just one month following its official inauguration, Nordsee Ost has been temporarily disconnected after a blade broke off one of the Senvion 6.2M126 turbines. The rotor blades are over 60 metres long and built from glass fibre and reinforced plastic, weighing several tonnes each. Half of the turbines were put back into operation following recovery of the blade; the exact cause of the damage is unknown.
Source: LogIn
correct
11-May-2015 Event Type: Operation - Fully Commissioned
Fully Commissioned Nordsee Ost was officially inaugurated on this day. The energy ministers of the G7 attended the inauguration.
Source: LogIn
correct
29-Dec-2014 Event Type: Operation - Generating Power
Generating Power HelWin1 grid connection was completed and Nordsee Ost exported 288MW of power to shore.
Source: LogIn
correct
26-Dec-2014 Event Type: Installation - Turbine Installation
Turbine Installation The 48th and final turbine was installed over the Christmas period. The installation project used two installation vessels simultaneously. Total turbine installation activities (excluding the blades) took a total of 20 weeks, one less than expected. 33 turbines were installed by the single blade technique, for the remaining 15 full rotor assembly was undertaken onshore, in which installation activities overran by 12 weeks (32 as opposed to the originally planned 20).
Source: LogIn
correct
19-Dec-2014 Event Type: Operation - Generating Power
Generating Power The first of the projects 48 wind turbines commenced trial operation and is feeding electricity to HelWin Alpha. Only one Senvion turbine is left to be installed.
Source: LogIn
correct
13-Oct-2014 Event Type: Installation - Turbine Installation
Turbine Installation 24 of 48 turbines were completed, also all of the remaining towers and nacelles had been installed, and were awaiting rotor stars..
Source: LogIn
correct
24-Sep-2014 Event Type: Installation - Turbine Installation
Turbine Installation A total of 19 turbines have been installed in just ten weeks. The additional 29 turbines for Nordsee Ost are pre-assembled apart from the blades.
Source: LogIn
correct
09-Sep-2014 Event Type: Installation - Turbine Installation
Turbine Installation 15 turbines were installed.
Source: LogIn
correct
21-Jul-2014 Event Type: Installation - Offshore Substation
Offshore Substation The 1,800 ton offshore substation topside was installed to the foundation. The next phase will include connecting the substation to the array and export cabling.
Source: LogIn
correct
15-Jul-2014 Event Type: Installation - Offshore Substation
Offshore Substation The offshore substation was ready for departure from the yard and it was installed soon after.
Source: LogIn
correct
Jul-2014 Event Type: Installation - Turbine Installation
Turbine Installation The first Senvion turbine was installed during this week. The hubs, rotor blades, nacelles, towers and other platform components are being pre-assembled as much as possible in the CT1 base harbour in Bremerhaven ready for loading onto the installation vessels. Five pieces were taken to the offshore site at a time.
Source: LogIn
correct
13-Jun-2014 Event Type: Installation - Array Cable Installation
Array Cable Installation The 60km of array cabling was installed. The cabling was installed in two campaigns with 30km installed last year and 30km installed in this year. Each loop of the cabling links up 12 foundations. The array cables were hooked up to the substation in August. Array cable installation was originally scheduled to be completed by April 2014.
Source: LogIn
correct
Jun-2014 Event Type: Planning - Grid Connection Other
Grid Connection Other The grid connection was put back to mid-2014 due to technical and economic problems. Originally the unconditional grid offer was for before 13/11/2012.
Source: LogIn
correct
19-May-2014 Event Type: Installation - Turbine Installation
Turbine Installation First four 240-tonnes tubular steel towers, with associated hubs and nacelles, were loaded onto the installation vessel Victoria Mathias (now known as the MPI Enterprise).
Source: LogIn
correct
14-Mar-2014 Event Type: Installation - Foundation Installation
Foundation Installation All of the foundations were installed (48 turbines and 1 substation).
Source: LogIn
correct
14-Mar-2014 Event Type: Installation - Foundation Installation
Foundation Installation FoundOcean completed the grouting of the 48 turbines. The amount of cement used for the 48 turbines and the one substation was 2,400 tonnes.
Source: LogIn
correct
14-Feb-2014 Event Type: Installation - Foundation Installation
Foundation Installation A number of ammunitions will need to be destroyed under controlled explosions. A total of 36 devices were located on the site and some will have to be removed before the final two foundations can be installed. 24 of the ammunitions are thought of as non hazardous and will be salvaged rather than detonated.
Source: LogIn
correct
31-Jan-2014 Event Type: Installation - Foundation Installation
Foundation Installation Initial scheduling stated foundation installation would be completed by the end of 2013, however this slipped into Q1 2014.
Source: LogIn
correct
22-Jan-2014 Event Type: Installation - Offshore Substation
Offshore Substation The 400 tonne top was placed on the bottom of the substation, during preparations made onshore. Now installation of two transformers, weighing 160 tonnes each, and internal equipping of the substation will commence.
Source: LogIn
correct
10-Jan-2014 Event Type: Installation - Foundation Installation
Foundation Installation Victoria Mathias is currently installing the jacket foundations. Until now 40 of the 48 foundations have been installed successfully.
Source: LogIn
correct
18-Dec-2013 Event Type: Installation - Foundation Installation
Foundation Installation Due to a period of bad weather, foundation installation slipped into January.
Source: LogIn
correct
30-Oct-2013 Event Type: Installation - Foundation Installation
Foundation Installation Foundation installation was ongoing. Installation vessel Victoria Mathias is still on track to install the last foundation by the end of the year.
Source: LogIn
correct
05-Sep-2013 Event Type: Installation - Array Cable Installation
Array Cable Installation In total 25 (of 52) array cables were installed within a month and ahead of schedule. The work stopped and continued as planned in Q2 2014.
Source: LogIn
correct
12
Add new windfarm events, providing approximate date etc. Possible events include consent submission, approval, installation, generating power etc.

Call +44 (0)1502 307 037 for more information

Keep on top of the market. Perform analysis. Make informed decisions.

CONTACT US

More information?

Receive monthly updates with our Offshore Windfarm Subscription and gain access to even more detailed information on; cabling, converters, costs, foundations, substations, turbines.

Filter :
1234
StatusName
Decommissioned Hooksiel Hooksiel
Fully Commissioned Alpha Ventus Alpha Ventus
Fully Commissioned Amrumbank West Amrumbank West
Fully Commissioned BARD Offshore 1 BARD Offshore 1
Fully Commissioned Borkum Riffgrund 1 Borkum Riffgrund 1
Fully Commissioned Breitling Breitling
Fully Commissioned Butendiek Butendiek
Fully Commissioned DanTysk DanTysk
Fully Commissioned EnBW Baltic 1 EnBW Baltic 1
Fully Commissioned EnBW Baltic 2 EnBW Baltic 2
Fully Commissioned ENOVA Offshore Project Ems Emden ENOVA Offshore Project Ems Emden
Fully Commissioned Global Tech I Global Tech I
Fully Commissioned Gode Wind 1 and 2 Gode Wind 1 and 2
Fully Commissioned Meerwind Süd/Ost Meerwind Süd/Ost
Fully Commissioned Nordergründe Nordergründe
Fully Commissioned Nordsee One Nordsee One
Fully Commissioned Nordsee Ost Nordsee Ost
Fully Commissioned Riffgat Riffgat
Fully Commissioned Sandbank Sandbank
Fully Commissioned Trianel Windpark Borkum I Trianel Windpark Borkum I
Fully Commissioned Veja Mate Veja Mate
Fully Commissioned Wikinger Wikinger
Partial Generation/Under Construction Merkur Merkur
Under Construction Arkona Arkona
Under Construction Borkum Riffgrund 2 Borkum Riffgrund 2
Under Construction Hohe See Hohe See
Under Construction OWP Albatros OWP Albatros
Pre-Construction Deutsche Bucht Deutsche Bucht
Pre-Construction GICON Schwimmendes Offshore Fundament (SOF) Pilot GICON Schwimmendes Offshore Fundament (SOF) Pilot
Pre-Construction Trianel Windpark Borkum II Trianel Windpark Borkum II
Consent Authorised Arcadis Ost 1 Arcadis Ost 1
Consent Authorised Baltic Eagle Baltic Eagle
Consent Authorised Borkum Riffgrund West 2 Borkum Riffgrund West 2
Consent Authorised Borkum Riffgrund West I Borkum Riffgrund West I
Consent Authorised Deutsche Bucht Pilot Park Deutsche Bucht Pilot Park
Consent Authorised EnBW He Dreiht EnBW He Dreiht
Consent Authorised Gode Wind 3 Gode Wind 3
Consent Authorised Gode Wind 4 Gode Wind 4
Consent Authorised Kaskasi Kaskasi
Consent Authorised OWP West OWP West
Consent Authorised Wikinger Süd Wikinger Süd
Consent Application Submitted Gennaker Gennaker
Concept/Early Planning GICON® SOF 6-8MW Test Turbine GICON® SOF 6-8MW Test Turbine
Concept/Early Planning ReaLCoE (Robust, Reliable and Large Offshore Wind Energy Converters for Clean, Low Cost and Competitive Electricity) ReaLCoE (Robust, Reliable and Large Offshore Wind Energy Converters for Clean, Low Cost and Competitive Electricity)
Development Zone Darß - priority area for wind energy Darß - priority area for wind energy
Development Zone German Central Tender 2022 (Assumed North Sea) German Central Tender 2022 (Assumed North Sea)
Development Zone German Central Tender 2023 (Assumed Baltic Sea) German Central Tender 2023 (Assumed Baltic Sea)
Development Zone German Central Tender 2024 (Assumed North Sea) German Central Tender 2024 (Assumed North Sea)
Development Zone German Central Tender 2025 (Assumed North Sea) German Central Tender 2025 (Assumed North Sea)
Development Zone German Central Tender 2026 (Assumed North Sea) German Central Tender 2026 (Assumed North Sea)
1234
Please LogIn to follow projects
Find quick and easy project and company information with our online search tool

Keep on top of the market. Perform analysis. Make informed decisions.

This page is intended to be viewed online and may not be printed without a valid subscription.

Please view this page at https://www.4coffshore.com/windfarms/events.aspx?windfarmID=de06.