United Kingdom 300MW Fully Commissioned

login to improve information access

There are three levels of access, Free, Freemium (requires a sign-up – for free – and password access) and “Full” (Password access).
You need Full access to use the ForeSEE interactive system, access reports, updates, notes, news and downloads. Sign up now!

Events overview for Thanet

Event Date Event Type Event Description Event Source
Subscribers only field Subscribers only field Subscribers only field Subscribers only field
Freemium Only 2021 Turbine Jack-up vessel J/U WIND arrived on site to support... Subscribers only field Subscribers only field
Freemium Only 2021 Turbine Ziton's Jack up vessel Wind will be carrying out l... Subscribers only field Subscribers only field
Freemium Only 2021 Export Cable Thanet Offshore Wind Limited (TOWL) (subsidiary of... Subscribers only field Subscribers only field
Freemium Only 2021 Site Investigation According to Thanet Offshore Wind Limited an UXO c... Subscribers only field Subscribers only field
Freemium Only 2021 Export Cable Installation Update (March 2019): Vattenfall has submitted a ma... Subscribers only field Subscribers only field
Freemium Only 2021 Performance Monitoring The Offshore Renewables Joint Industry Programme (... Subscribers only field Subscribers only field
Freemium Only 2021 Turbine Hochtief vessel Odin (now JB - 119) replaced three... Subscribers only field Subscribers only field
Freemium Only 2021 Turbine J/U WIND provided operations and maintenance suppo... Subscribers only field Subscribers only field
Freemium Only 2021 Turbine J/U WIND provided operations and maintenance suppo... Subscribers only field Subscribers only field
Freemium Only 2021 Turbine The vessel J/U Wind supported heavy maintenance wo... Subscribers only field Subscribers only field
Freemium Only 2021 Turbine Jack up vessel J/U WIND is to carry out maintenanc... Subscribers only field Subscribers only field
Freemium Only 2021 Turbine Jack up vessel J/U WIND was on site carrying out h... Subscribers only field Subscribers only field
Freemium Only 2021 Turbine Jack up J/U WIND supported heavy maintenance work.... Subscribers only field Subscribers only field
Freemium Only 2021 Turbine J/U WIND arrived to support heavy maintenance work... Subscribers only field Subscribers only field
Freemium Only 2021 Vattenfall has submitted an O&M Marine Licence req... Subscribers only field Subscribers only field
Freemium Only 2021 Ofgem has accepted an exceptional event claim subm... Subscribers only field Subscribers only field
Freemium Only 2021 Turbine J/U WIND carried out heavy maintenance work on the... Subscribers only field Subscribers only field
Freemium Only 2021 Site Investigation According to Thanet Offshore Wind Limited it is an... Subscribers only field Subscribers only field
Freemium Only 2021 Export Cable The second export cable failed due to an electrica... Subscribers only field Subscribers only field
Freemium Only 2021 Export Cable An outage is planned for four weeks across Septemb... Subscribers only field Subscribers only field
Freemium Only 2021 Performance Monitoring From March 2015 to March 2016 Thanet OFTO only had... Subscribers only field Subscribers only field
Freemium Only 2021 Consent Authorised Principal cause for delays in consenting: Fish (sp... Subscribers only field Subscribers only field
Freemium Only 2021 Turbine Installation The first of the 100 turbines was installed.... Subscribers only field Subscribers only field
Freemium Only 2021 Foundation Installation First foundation was installed.... Subscribers only field Subscribers only field
Freemium Only 2021 Generating Power Although the project was not complete (73 of 100 t... Subscribers only field Subscribers only field
Freemium Only 2021 Foundation Installation The 100th and last foundation was installed.... Subscribers only field Subscribers only field
Freemium Only 2021 Export Cable Installation Export cable installation commences.... Subscribers only field Subscribers only field
Freemium Only 2021 Other First transition piece was installed.... Subscribers only field Subscribers only field
Freemium Only 2021 Array Cable Installation First array cable was installed.... Subscribers only field Subscribers only field
Freemium Only 2021 Met Mast/LiDAR 43m met mast installed on the sub station.... Subscribers only field Subscribers only field
Freemium Only 2021 Turbine Installation The 100th and last turbine was installed.... Subscribers only field Subscribers only field
Freemium Only 2021 Fully Commissioned The wind farm was completed and the official launc... Subscribers only field Subscribers only field
Freemium Only 2021 Consent Application Submitted Consent application submitted.... Subscribers only field Subscribers only field
Freemium Only 2021 Export Cable An export cable fault needed to be fixed. During t... Subscribers only field Subscribers only field
Freemium Only 2021 Array Cable Installation Replacement of two array cables using the vessel O... Subscribers only field Subscribers only field
Freemium Only 2021 Financing Agreement It was confirmed that the Environmental Investment... Subscribers only field Subscribers only field
Freemium Only 2021 Array Cable Installation Array cable installation completed.... Subscribers only field Subscribers only field
Freemium Only 2021 Turbine A further 12 turbines on site were replaced.... Subscribers only field Subscribers only field
Freemium Only 2021 Turbine Three turbines were replaced under the Vestas warr... Subscribers only field Subscribers only field
Freemium Only 2021 Foundation Rock dumping took place on site.... Subscribers only field Subscribers only field
Freemium Only 2021 Export Cable Export cable repair work began on this day and is ... Subscribers only field Subscribers only field
Freemium Only 2021 Grid Connection Agreed 300MW of grid connection supplied by the National ... Subscribers only field Subscribers only field
Freemium Only 2021 Foundation Installation 59 of the foundations were installed, with a furth... Subscribers only field Subscribers only field
Freemium Only 2021 Offshore Substation The substation installation began and took 15 days... Subscribers only field Subscribers only field
Freemium Only 2021 Export Cable Installation Export cable installation completed.... Subscribers only field Subscribers only field
Freemium Only 2021 Array Cable Over the course of two months, replacement of two ... Subscribers only field Subscribers only field
Freemium Only 2021 After 4 years Balfour Beatty were chosen as the su... Subscribers only field Subscribers only field
Freemium Only 2021 Balfour Beatty successfully purchased the Thanet O... Subscribers only field Subscribers only field
Freemium Only 2021 Balfour Beatty sold 80% of their stake in Thanet O... Subscribers only field Subscribers only field
Freemium Only 2021 Export Cable In February a fault in export cable One meant that... Subscribers only field Subscribers only field
Freemium Only 2021 Export Cable The cable has still not been fixed. A total of 150... Subscribers only field Subscribers only field
Freemium Only 2021 Export Cable Cable recovery started on 24th April 2015 and was ... Subscribers only field Subscribers only field
Freemium Only 2021 Turbine Service Agreement Expires Suspected five-year OEM service agreement expired.... Subscribers only field Subscribers only field