Events on Thornton Bank phase III Database in Excel
DateEventDescription 
LogIn Event Type: Operation - Service Agreement Expires
Service Agreement Expires The ten-year OEM service agreement will expire.
Source: LogIn
correct
05-Sep-2016 Event Type: Other -
Other C-Power announced they will be partnering with Sirris/OWI-Lab and Vrije Universiteit Brussel to monitor the foundation structures at the wind farm. This will enable C-Power to keep track of the ageing process and plan maintenance work in an informed way.
Source: LogIn
correct
18-Sep-2013 Event Type: Operation - Fully Commissioned
Fully Commissioned Thornton Bank offshore wind farm officially inaugurated by Belgian Prime Minister.
Source: LogIn
correct
17-Sep-2013 Event Type: Installation - Export Cable Installation
Export Cable Installation The export cable, onshore cable and offshore substation for all the Thornton Bank phases was completed.
Source: LogIn
correct
Sep-2013 Event Type: Operation - Generating Power
Generating Power The project was planned to be in production from September 2013.
Source: LogIn
correct
03-Jul-2013 Event Type: Installation - Turbine Installation
Turbine Installation The final turbine was installed.
Source: LogIn
correct
24-Jun-2013 Event Type: Installation - Turbine Installation
Turbine Installation Construction update: 17 of 18 turbines installed.
Source: LogIn
correct
17-Jun-2013 Event Type: Installation - Turbine Installation
Turbine Installation Construction update: 14 of 18 turbines are installed.
Source: LogIn
correct
10-Jun-2013 Event Type: Installation - Turbine Installation
Turbine Installation Construction update: 13 of 18 turbines installed.
Source: LogIn
correct
05-May-2013 Event Type: Installation - Turbine Installation
Turbine Installation Construction update: 7 of 18 turbines installed.
Source: LogIn
correct
13-Mar-2013 Event Type: Installation - Turbine Installation
Turbine Installation The first Senvion 6.2M126 turbine was installed.
Source: LogIn
correct
08-Mar-2013 Event Type: Installation - Turbine Installation
Turbine Installation The Goliath and Vagant arrived on site to commence turbine installation; Goliath will be performing the installation activities whilst Vagant will provide accommodation for the crew.
Source: LogIn
correct
17-Sep-2012 Event Type: Installation - Array Cable Installation
Array Cable Installation Array cable installation for Area A is complete. The burial of these cables started on 09/08/2012 and all the cable strings between the offshore transformer station and the wind turbines got a first burial pass. The surveys of the burial depths are complete and where necessary some remedial burial works will be executed.
Source: LogIn
correct
28-Jun-2012 Event Type: Installation - Array Cable Installation
Array Cable Installation Array cable installation for Area A started on 28/06/2012.
Source: LogIn
correct
16-Jun-2012 Event Type: Installation - Array Cable Installation
Array Cable Installation All infield cables for area A were loaded on the ship in Karlskrona ready for shipment to Zeebrugge.
Source: LogIn
correct
29-May-2012 Event Type: Installation - Foundation Installation
Foundation Installation All foundations in Area A successfully installed and grouted. All 18 jackets in area A were installed in 3 months with the completion date 2 months ahead of the master schedule.
Source: LogIn
correct
Mar-2012 Event Type: Installation - Foundation Installation
Foundation Installation The Rambiz started installation of foundations in Area A on the 1st March.
Source: LogIn
correct
21-Aug-2011 Event Type: Installation - Foundation Installation
Foundation Installation All pin-piling for the jacket foundations completed. 196 piles driven into the sea bed in 4 and a half months.
Source: LogIn
correct
Apr-2011 Event Type: Installation - Offshore Construction Starts
Offshore Construction Starts Foundation piling started in April in area A. Steel piles of 40-50m were driven into the seabed by a hammer installation mounted on the jack up platform Buzzard.
Source: LogIn
correct
23-Dec-2010 Event Type: Planning - Financing Agreement
Financing Agreement Eneco signed power purchase agreement for the generated electricity.
Source: LogIn
correct
25-Nov-2010 Event Type: Planning - Financial Close
Financial Close Financial Close. EUR 1billion to finance 2nd and 3rd phases. Financed by group of seven lenders together with export credit agencies Euler Hermes and EKF, plus the EIB
Source: LogIn
correct
14-Apr-2004 Event Type: Planning - Consent Authorised
Consent Authorised Environmental permit granted by the Minister responsible for the marine environment.
Source: LogIn
correct
27-Jun-2003 Event Type: Planning - Other Approval
Other Approval Concession granted 27/06/03 by the State Secretary of Energy.
Source: LogIn
correct
Add new windfarm events, providing approximate date etc. Possible events include consent submission, approval, installation, generating power etc.

Call +44 (0)1502 307 037 for more information

Keep on top of the market. Perform analysis. Make informed decisions.

CONTACT US

More information?

Receive monthly updates with our Offshore Windfarm Subscription and gain access to even more detailed information on; cabling, converters, costs, foundations, substations, turbines.

Filter :
Please LogIn to follow projects
Find quick and easy project and company information with our online search tool

Keep on top of the market. Perform analysis. Make informed decisions.

This page is intended to be viewed online and may not be printed without a valid subscription.

Please view this page at https://www.4coffshore.com/windfarms/events.aspx?windfarmID=be10.