Latest event on Rhyl Flats

Innogy will be carrying out maintenance operations including heavy lifting at three locations. Operations will commence on or around 8th October 2017 and will take approximately 14 days to complete. Wind Server will carry out the work. The work took longer than expected due to bad weather. The vessel is due arrive at Burbo Bank to carry out maintenance on 3rd November. Read more

Latest Update: 08 October 2017

You can help keep this an open resource by submitting new information. Simply click on the correct pencil icon.
Developers/Owners/Operators Database in Excel | Add your Organisation
RoleOrganisation 
Developer
correct
Operator
correct
Operator correct
Owner correct
Owner correct
Owner correct
Project Details for Rhyl Flats
General Information Name Rhyl Flats correct
Other names correct
Country name United Kingdom correct
Region Wales, North correct
Comments correct
Round (or category) Round 1 correct
Development status Fully Commissioned correct
Power & Turbines Project capacity 90 MW correct
Turbine model SWT-3.6-107 (Siemens) correct
Turbine capacity 3.6 MW correct
Number of turbines 25 correct
Total turbine height 133.5 m correct
Hub height 80.00 m correct
Rotor diameter 107 m correct
Foundation Grounded: Monopile correct
Windspeed 10 year mean wind speed (2000-2009) Available online now
Costs Stated project cost GBP(mill) 190.00 correct
Location & Environment Sea name Irish Sea correct
Centre latitude 53.379° correct
Centre longitude -3.647° correct
Area 10 km2 correct
Depth range (Chart Datum) 4 m - 11 m correct
Depth range stated by developer 6 m - 12 m correct
Distance from shore (reported) 8 km correct
Distance from shore (computed from centre) 10.7 km correct
Ports Installation base Mostyn correct
Ops and maintenance Mostyn correct
Grid Converter/Collector platforms None correct
Offshore transformers None correct
Grid connection point Towyn correct
Cable landing point Towyn correct
Export Cables
Please note that export cables connect the offshore transformer (substation) to either; shore or an offshore HVAC-HVDC converter station for onward transmission via HVDC cabling. Please see the converters page for planned converter stations and transmission cables.

The export cable length does not generally include the onshore component. The exception is when the onshore substation is close to shore.
Number of export cables 3 correct
Average length per cable 10.5 km correct
Transmission type (e.g. HVAC) AC correct
Nominal voltage 33 kV correct
Maximum voltage 36 kV correct
Power rating correct
Number of cores 3 correct
Conductor type Cu correct
Section area 630 mm2 correct
Insulation correct
Number fibre optics correct
Export minimum bend radius (MBR) correct
Burial depth correct
Comments correct
Onshore Cables Number of onshore cables 3 correct
Average length per cable 2 km correct
Comments 3x33kV, each circuit just under 2km correct
Array Cables Array cable length 18 km correct
Estimated cable length LogIn
Transmission type (e.g. MVAC) MVAC correct
Nominal voltage 33 kV correct
Maximum voltage 36 kV correct
Burial depth correct
Number of cores 3 correct
Conductor type Cu correct
Section 185/630 mm2 correct
Insulation correct
Power rating correct
Number of fibre optics correct
Minimum bend radius (MBR) correct
Comments correct
Benefits Homes powered annually 63743 correct
CO2 reduced per year 128825 tonnes correct
SO2 reduced per year 2996 tonnes correct
Expected life correct
Other Website Visit correct

Call +44 (0)1502 307 037 for more information

Keep on top of the market. Perform analysis. Make informed decisions.

CONTACT US

More information?

Receive monthly updates with our Offshore Windfarm Subscription and gain access to even more detailed information on; cabling, converters, costs, foundations, substations, turbines.

Filter :
123
StatusName
Decommissioned Beatrice Demonstration Beatrice Demonstration
Decommissioned Blyth Blyth
Fully Commissioned Barrow Barrow
Fully Commissioned Blyth Offshore Demonstrator Project - Array 2 Blyth Offshore Demonstrator Project - Array 2
Fully Commissioned Burbo Bank Burbo Bank
Fully Commissioned Burbo Bank Extension Burbo Bank Extension
Fully Commissioned Dudgeon Dudgeon
Fully Commissioned Galloper Galloper
Fully Commissioned Greater Gabbard Greater Gabbard
Fully Commissioned Gunfleet Sands Gunfleet Sands
Fully Commissioned Gunfleet Sands 3 - Demonstration Project Gunfleet Sands 3 - Demonstration Project
Fully Commissioned Gwynt y Môr Gwynt y Môr
Fully Commissioned Humber Gateway Humber Gateway
Fully Commissioned Hunterston Test Centre - Mitsubishi 7MW (onshore) Hunterston Test Centre - Mitsubishi 7MW (onshore)
Fully Commissioned Hunterston Test Centre - Siemens 6MW (onshore) Hunterston Test Centre - Siemens 6MW (onshore)
Fully Commissioned Hunterston Test Centre (onshore) Hunterston Test Centre (onshore)
Fully Commissioned Hywind Scotland Pilot Park Hywind Scotland Pilot Park
Fully Commissioned Inner Dowsing Inner Dowsing
Fully Commissioned Kentish Flats Kentish Flats
Fully Commissioned Kentish Flats Extension Kentish Flats Extension
Fully Commissioned Levenmouth demonstration turbine Levenmouth demonstration turbine
Fully Commissioned Lincs Lincs
Fully Commissioned London Array London Array
Fully Commissioned Lynn Lynn
Fully Commissioned North Hoyle North Hoyle
Fully Commissioned Ormonde Ormonde
Fully Commissioned Race Bank Race Bank
Fully Commissioned Rhyl Flats Rhyl Flats
Fully Commissioned Robin Rigg Robin Rigg
Fully Commissioned Scroby Sands Scroby Sands
Fully Commissioned Sheringham Shoal Sheringham Shoal
Fully Commissioned Teesside Teesside
Fully Commissioned Thanet Thanet
Fully Commissioned Walney Phase 1 Walney Phase 1
Fully Commissioned Walney Phase 2 Walney Phase 2
Fully Commissioned Wave Hub Wave Hub
Fully Commissioned West of Duddon Sands West of Duddon Sands
Fully Commissioned Westermost Rough Westermost Rough
Partial Generation/Under Construction Rampion Rampion
Partial Generation/Under Construction Walney Extension Walney Extension
Under Construction Aberdeen Offshore Wind Farm (EOWDC) Aberdeen Offshore Wind Farm (EOWDC)
Under Construction Beatrice Beatrice
Under Construction East Anglia ONE East Anglia ONE
Under Construction Hornsea Project One Hornsea Project One
Pre-Construction Hornsea Project Two Hornsea Project Two
Consent Authorised Blyth Offshore Demonstrator Project - Array 3A & 4 Blyth Offshore Demonstrator Project - Array 3A & 4
Consent Authorised Dogger Bank - Creyke Beck A Dogger Bank - Creyke Beck A
Consent Authorised Dogger Bank - Creyke Beck B Dogger Bank - Creyke Beck B
Consent Authorised Dogger Bank - Teesside A Dogger Bank - Teesside A
Consent Authorised Dounreay Trì Dounreay Trì
123
Please LogIn to follow projects
Find quick and easy project and company information with our online search tool

Keep on top of the market. Perform analysis. Make informed decisions.

This page is intended to be viewed online and may not be printed without a valid subscription.

Please view this page at http://www.4coffshore.com/windfarms/windfarms.aspx?windfarmID=uk19.