Latest event on Sheringham Shoal

Statkraft plan to complete the divestment of its share by the end of 2017. Read more

Latest Update: 31 December 2017

You can help keep this an open resource by submitting new information. Simply click on the correct pencil icon.
Developers/Owners/Operators Database in Excel | Add your Organisation
RoleOrganisation 
Developer correct
Operator correct
Operator-Offshore Transmission correct
Owner correct
Owner correct
Owner correct
Owner correct
Owner-Offshore Transmission correct
Project Details for Sheringham Shoal
General Information Name Sheringham Shoal correct
Other names correct
Country name United Kingdom correct
Region England, East of England correct
Comments correct
Round (or category) Round 2 correct
Development status Fully Commissioned correct
Power & Turbines Project capacity 316.8 MW correct
Turbine model SWT-3.6-107 (Siemens) correct
Turbine capacity 3.6 MW correct
Number of turbines 88 correct
Total turbine height 135.2 m correct
Hub height 81.75 m correct
Rotor diameter 107 m correct
Foundation Grounded: Monopile correct
Windspeed 10 year mean wind speed (2000-2009) Available online now
Costs Stated project cost NOK(mill) 10000.00 correct
Location & Environment Sea name North Sea, Southern North Sea (Humber) correct
Centre latitude 53.136° correct
Centre longitude 1.147° correct
Area 35 km2 correct
Depth range (Chart Datum) 14 m - 23 m correct
Depth range stated by developer 15 m - 22 m correct
Distance from shore (reported) 23 km correct
Distance from shore (computed from centre) 21.4 km correct
Ports Installation base Great Yarmouth correct
Ops and maintenance Wells-next-the-sea correct
Grid Converter/Collector platforms None correct
Offshore transformers Sheringham Shoal 1 Substation, Sheringham Shoal 2 Substation correct
Grid connection point Salle correct
Cable landing point Weybourne correct
Export Cables
Please note that export cables connect the offshore transformer (substation) to either; shore or an offshore HVAC-HVDC converter station for onward transmission via HVDC cabling. Please see the converters page for planned converter stations and transmission cables.

The export cable length does not generally include the onshore component. The exception is when the onshore substation is close to shore.
Number of export cables 2 correct
Average length per cable 22 km correct
Transmission type (e.g. HVAC) AC correct
Nominal voltage 132 kV correct
Maximum voltage 145 kV correct
Power rating 176 MVA correct
Number of cores 3 correct
Conductor type Cu correct
Section area 630 (2x21km)/1000 (2x0.2km) mm2 correct
Insulation XLPE correct
Number fibre optics correct
Export minimum bend radius (MBR) correct
Burial depth 1 m correct
Comments The length of the cables is 21km and 23km

Land cable is 21.2km
correct
Onshore Cables Number of onshore cables 6 correct
Average length per cable 21.3 km correct
Comments 145kV, trenches being around 2.2m wide and 1.6m deep correct
Array Cables Array cable length 81 km correct
Estimated cable length LogIn
Transmission type (e.g. MVAC) MVAC correct
Nominal voltage 33 kV correct
Maximum voltage 36 kV correct
Burial depth 1 m correct
Number of cores 3 correct
Conductor type Cu correct
Section 400 (26 km)/185 (56km) mm2 correct
Insulation XLPE correct
Power rating correct
Number of fibre optics correct
Minimum bend radius (MBR) correct
Comments There will be two different types of infield cables connecting the turbines and the offshore substations. Type one (27kg/m) has a total length of 26 kilometres and will be used to connect the turbines closest to the substations, while type two (18kg/m) has a total length of 56 kilometres and will connect the turbines further out. correct
Benefits Homes powered annually 224375 correct
CO2 reduced per year 453462 tonnes correct
SO2 reduced per year 10546 tonnes correct
Expected life 25.0 years correct
Other Website Visit correct

Call +44 (0)1502 307 037 for more information

Keep on top of the market. Perform analysis. Make informed decisions.

CONTACT US

More information?

Receive monthly updates with our Offshore Windfarm Subscription and gain access to even more detailed information on; cabling, converters, costs, foundations, substations, turbines.

Filter :
123
StatusName
Decommissioned Beatrice Demonstration Beatrice Demonstration
Decommissioned Blyth Blyth
Fully Commissioned Barrow Barrow
Fully Commissioned Blyth Offshore Demonstrator Project - Array 2 Blyth Offshore Demonstrator Project - Array 2
Fully Commissioned Burbo Bank Burbo Bank
Fully Commissioned Burbo Bank Extension Burbo Bank Extension
Fully Commissioned Dudgeon Dudgeon
Fully Commissioned Galloper Galloper
Fully Commissioned Greater Gabbard Greater Gabbard
Fully Commissioned Gunfleet Sands Gunfleet Sands
Fully Commissioned Gunfleet Sands 3 - Demonstration Project Gunfleet Sands 3 - Demonstration Project
Fully Commissioned Gwynt y Môr Gwynt y Môr
Fully Commissioned Humber Gateway Humber Gateway
Fully Commissioned Hunterston Test Centre - Mitsubishi 7MW (onshore) Hunterston Test Centre - Mitsubishi 7MW (onshore)
Fully Commissioned Hunterston Test Centre - Siemens 6MW (onshore) Hunterston Test Centre - Siemens 6MW (onshore)
Fully Commissioned Hunterston Test Centre (onshore) Hunterston Test Centre (onshore)
Fully Commissioned Hywind Scotland Pilot Park Hywind Scotland Pilot Park
Fully Commissioned Inner Dowsing Inner Dowsing
Fully Commissioned Kentish Flats Kentish Flats
Fully Commissioned Kentish Flats Extension Kentish Flats Extension
Fully Commissioned Levenmouth demonstration turbine Levenmouth demonstration turbine
Fully Commissioned Lincs Lincs
Fully Commissioned London Array London Array
Fully Commissioned Lynn Lynn
Fully Commissioned North Hoyle North Hoyle
Fully Commissioned Ormonde Ormonde
Fully Commissioned Race Bank Race Bank
Fully Commissioned Rhyl Flats Rhyl Flats
Fully Commissioned Robin Rigg Robin Rigg
Fully Commissioned Scroby Sands Scroby Sands
Fully Commissioned Sheringham Shoal Sheringham Shoal
Fully Commissioned Teesside Teesside
Fully Commissioned Thanet Thanet
Fully Commissioned Walney Phase 1 Walney Phase 1
Fully Commissioned Walney Phase 2 Walney Phase 2
Fully Commissioned Wave Hub Wave Hub
Fully Commissioned West of Duddon Sands West of Duddon Sands
Fully Commissioned Westermost Rough Westermost Rough
Partial Generation/Under Construction Rampion Rampion
Partial Generation/Under Construction Walney Extension Walney Extension
Under Construction Aberdeen Offshore Wind Farm (EOWDC) Aberdeen Offshore Wind Farm (EOWDC)
Under Construction Beatrice Beatrice
Under Construction East Anglia ONE East Anglia ONE
Under Construction Hornsea Project One Hornsea Project One
Pre-Construction Hornsea Project Two Hornsea Project Two
Consent Authorised Blyth Offshore Demonstrator Project - Array 3A & 4 Blyth Offshore Demonstrator Project - Array 3A & 4
Consent Authorised Dogger Bank - Creyke Beck A Dogger Bank - Creyke Beck A
Consent Authorised Dogger Bank - Creyke Beck B Dogger Bank - Creyke Beck B
Consent Authorised Dogger Bank - Teesside A Dogger Bank - Teesside A
Consent Authorised Dounreay Trì Dounreay Trì
123
Please LogIn to follow projects
Find quick and easy project and company information with our online search tool

Keep on top of the market. Perform analysis. Make informed decisions.

This page is intended to be viewed online and may not be printed without a valid subscription.

Please view this page at http://www.4coffshore.com/windfarms/windfarms.aspx?windfarmID=uk27.