Subscribers only field |
Subscribers only field |
Subscribers only field |
Subscribers only field
|
Freemium Only 2041 |
Decommissioning |
The main bulk of removing the turbine components w... Subscribers only field |
Subscribers only field
|
Freemium Only 2041 |
Decommissioning |
Galloper Wind Farm Limited (GWFL) stated in its De... Subscribers only field |
Subscribers only field
|
Freemium Only 2021 |
Cable |
During an ROV inspection at Galloper, to assess th... Subscribers only field |
Subscribers only field
|
Freemium Only 2020 |
Other Approval |
The Crown Estate awarded the Agreement for Lease (... Subscribers only field |
Subscribers only field
|
Freemium Only 2020 |
Turbine |
Galloper has issued a temporary exclusion zone aro... Subscribers only field |
Subscribers only field
|
Freemium Only 2020 |
Other |
Update (December 2019): the base is expected to op... Subscribers only field |
Subscribers only field
|
Freemium Only 2020 |
Other |
Ofgem published the cost assessment for the Gallop... Subscribers only field |
Subscribers only field
|
Freemium Only 2020 |
Turbine |
The generator of turbine GN-D2B requires replaceme... Subscribers only field |
Subscribers only field
|
Freemium Only 2020 |
Ownership Change |
Spring Infrastructure Capital acquired Sumitomo Co... Subscribers only field |
Subscribers only field
|
Freemium Only 2019 |
Turbine |
Rovco has completed the remotely operated underwat... Subscribers only field |
Subscribers only field
|
Freemium Only 2019 |
Foundation |
ROVCO are conducting ROV inspections of turbine po... Subscribers only field |
Subscribers only field
|
Freemium Only 2019 |
Turbine |
Pacific Orca arrived on site to to provide heavy m... Subscribers only field |
Subscribers only field
|
Freemium Only 2019 |
Consultation |
The Marine Management Organisation (MMO) is hostin... Subscribers only field |
Subscribers only field
|
Freemium Only 2019 |
|
Following a consultation, BEIS has decided to prov... Subscribers only field |
Subscribers only field
|
Freemium Only 2018 |
Tender Process |
Ofgem has selected Diamond Transmission Partners a... Subscribers only field |
Subscribers only field
|
Freemium Only 2018 |
Other |
Construction has started on the £10m O&M base in H... Subscribers only field |
Subscribers only field
|
Freemium Only 2018 |
|
BEIS published the Draft HRA document relating to ... Subscribers only field |
Subscribers only field
|
Freemium Only 2018 |
|
Galloper was officially inaugurated by Innogy.... Subscribers only field |
Subscribers only field
|
Freemium Only 2018 |
Tender Process |
The Invitation to Tender (ITT) stage for the OFTO ... Subscribers only field |
Subscribers only field
|
Freemium Only 2018 |
Fully Commissioned |
The wind farm achieved full generation with all 56... Subscribers only field |
Subscribers only field
|
Freemium Only 2018 |
Ownership Change |
ESB acquired a 12.5% stake in the project from Mac... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Turbine Installation |
The final wind turbine was installed at Galloper O... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Turbine Installation |
50 out of 56 turbines have been installed.... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Turbine Installation |
38 of the 56 turbines have been installed.... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
|
On 7th November 2017 innogy announced that working... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Generating Power |
The project generated power for the first time on ... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
|
In January 2017 the Government submitted the South... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
|
innogy placed the first German corporate Green Bon... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Turbine Installation |
Galloper reached the half-way mark, with 28 of 56 ... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Turbine Installation |
24 of 56 turbines installed.... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Turbine Installation |
Bibby Wavemaster is now onsite it was chartered to... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Turbine Installation |
Fred. Olsen Windcarrier vessel Bold Tern will mob... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Array Cable Installation |
VBMS installed the 56th and final array cable for ... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Tender Process |
Ofgem announced a shortlist of bidders competing t... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Export Cable Installation |
From the 21st of June until September 2017 the ves... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Turbine Installation |
The vessel Pacific Orca installed the first of 56 ... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Offshore Substation |
The vessel Seajacks Hydra will position itself alo... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Turbine Installation |
The Pacific Orca arrived on site with the first se... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Offshore Substation |
The vessel Oleg Strashnov had installed the jacket... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Export Cable Installation |
Around this date the cable lay and burial from Siz... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Turbine Installation |
The vessel MV Pacific Orca left for the site and w... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
|
The Pacific Orca arrived at the Port of Great Yarm... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Export Cable Installation |
The CLV Ndurance set up offshore from Sizewell bea... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Export Cable Installation |
The final phase of Galloper construction work at S... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Offshore Substation |
The vessel Oleg Strashnov arrived at the site to b... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Production and Fabrication |
The substation topside was loaded on to the barge ... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Array Cable Installation |
The first of 56 array cables was installed by the ... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Foundation Installation |
The 56th and final turbine foundation was installe... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Production and Fabrication |
The first batch of array cables loaded on to the c... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Production and Fabrication |
Heerema Fabrication moved the substation topside o... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Tender Process |
Ofgem invited companies to submit bids to own and ... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Production and Fabrication |
The jacket for the substation platform was loaded ... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Foundation Installation |
The 28th of 56 foundations was installed on schedu... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Foundation Installation |
A total of eight monopiles and transition pieces h... Subscribers only field |
Subscribers only field
|
Freemium Only 2017 |
Grid Connection Available |
National Grid will provide a 348MW grid connection... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Other |
Completion of the onshore substation construction ... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Foundation Installation |
GeoSea's DP2 Innovation installed the first of 56 ... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Production and Fabrication |
The first set of monopiles were loaded on to the t... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Other Application Submitted |
Galloper Wind Farm Ltd has confirmed it was pursui... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Tender Process |
Ofgem published the Preliminary Information Memora... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Export Cable Installation |
For 14 days the vessel Ndeavor will be engaging in... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Export Cable Installation |
The vessel Ndurance arrived at the substation site... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Export Cable Installation |
The vessel Ndurance began export cable installatio... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Production and Fabrication |
The first sections of the monopiles arrived at Sif... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
PreTesting |
The cable installation vessel Ndurance arrived in ... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Site Investigation |
The vessel RV Discovery began a survey on the expo... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Site Investigation |
UXO survey on array cable routes is planned for th... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Site Investigation |
Investigation and clearance of UXO for the export ... Subscribers only field |
Subscribers only field
|
Freemium Only 2016 |
Onshore Construction Starts |
Directional Drilling works at Sizewell for install... Subscribers only field |
Subscribers only field
|
Freemium Only 2015 |
Production and Fabrication |
Fabrication and onshore construction of the compon... Subscribers only field |
Subscribers only field
|
Freemium Only 2015 |
Other Approval |
A public consultation was held regarding the draft... Subscribers only field |
Subscribers only field
|
Freemium Only 2015 |
Financial Close |
A new partnership heralds a green light for the co... Subscribers only field |
Subscribers only field
|
Freemium Only 2015 |
PreTesting |
The vessel INNOVATION arrived on site to perform t... Subscribers only field |
Subscribers only field
|
Freemium Only 2015 |
Financing Agreement |
The EIB approved the £425 million loan.... Subscribers only field |
Subscribers only field
|
Freemium Only 2015 |
Site Investigation |
UXO survey on export cable route was planned for t... Subscribers only field |
Subscribers only field
|
Freemium Only 2015 |
Financing Agreement |
The European Investment Bank put a proposed EIB fi... Subscribers only field |
Subscribers only field
|
Freemium Only 2015 |
|
RWE is 'continuing to make significant progress wi... Subscribers only field |
Subscribers only field
|
Freemium Only 2015 |
|
RWE has stated that good progress is being made on... Subscribers only field |
Subscribers only field
|
Freemium Only 2014 |
|
A Galloper spokesperson informed 4C Offshore that ... Subscribers only field |
Subscribers only field
|
Freemium Only 2014 |
|
From SSE's interim results for the six months to 3... Subscribers only field |
Subscribers only field
|
Freemium Only 2014 |
|
RWE decided not to continue with the project, in M... Subscribers only field |
Subscribers only field
|
Freemium Only 2014 |
Other Approval |
Galloper received planning consent from Suffolk Co... Subscribers only field |
Subscribers only field
|
Freemium Only 2014 |
|
From an Interim Management Statement released 22/0... Subscribers only field |
Subscribers only field
|
Freemium Only 2014 |
|
SSE has announced that it will not participate in ... Subscribers only field |
Subscribers only field
|
Freemium Only 2014 |
Tender Process |
It was announced that Lowestoft Port would be used... Subscribers only field |
Subscribers only field
|
Freemium Only 2014 |
Feasibility Study |
The FEED was finalised in Q1.... Subscribers only field |
Subscribers only field
|
Freemium Only 2013 |
Other Application Submitted |
A list of qualifying applicants and projects for t... Subscribers only field |
Subscribers only field
|
Freemium Only 2013 |
|
SSE announced that the planned capacity has been r... Subscribers only field |
Subscribers only field
|
Freemium Only 2013 |
Consent Authorised |
The Secretary of State granted development consent... Subscribers only field |
Subscribers only field
|
Freemium Only 2013 |
Site Investigation |
A geophysical survey was carried out by the MW Con... Subscribers only field |
Subscribers only field
|
Freemium Only 2012 |
Other Approval |
Galloper and EDF Energy made an agreement over lan... Subscribers only field |
Subscribers only field
|
Freemium Only 2012 |
Geotechnical Site Investigation |
Geotechnical site investigation took place.... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Other Approval |
The Infrastructure Planning Commission (IPC) forma... Subscribers only field |
Subscribers only field
|
Freemium Only 2011 |
Consent Application Submitted |
A Development Consent Order (DCO) was submitted to... Subscribers only field |
Subscribers only field
|
Freemium Only 2009 |
Other Approval |
Grid connection secured with National Grid.... Subscribers only field |
Subscribers only field
|