United Kingdom 353MW Fully Commissioned

login to improve information access

There are three levels of access, Free, Freemium (requires a sign-up – for free – and password access) and “Full” (Password access).
You need Full access to use the ForeSEE interactive system, access reports, updates, notes, news and downloads. Sign up now!

Events overview for Galloper

Event Date Event Type Event Description Event Source
Subscribers only field Subscribers only field Subscribers only field Subscribers only field
Freemium Only 2041 Decommissioning The main bulk of removing the turbine components w... Subscribers only field Subscribers only field
Freemium Only 2041 Decommissioning Galloper Wind Farm Limited (GWFL) stated in its De... Subscribers only field Subscribers only field
Freemium Only 2020 Other Update (December 2019): the base is expected to op... Subscribers only field Subscribers only field
Freemium Only 2020 Other Ofgem published the cost assessment for the Gallop... Subscribers only field Subscribers only field
Freemium Only 2020 Turbine The generator of turbine GN-D2B requires replaceme... Subscribers only field Subscribers only field
Freemium Only 2020 Ownership Change Spring Infrastructure Capital acquired Sumitomo Co... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine Rovco has completed the remotely operated underwat... Subscribers only field Subscribers only field
Freemium Only 2019 Foundation ROVCO are conducting ROV inspections of turbine po... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine Pacific Orca arrived on site to to provide heavy m... Subscribers only field Subscribers only field
Freemium Only 2019 Consultation The Marine Management Organisation (MMO) is hostin... Subscribers only field Subscribers only field
Freemium Only 2019 Following a consultation, BEIS has decided to prov... Subscribers only field Subscribers only field
Freemium Only 2018 Tender Process Ofgem has selected Diamond Transmission Partners a... Subscribers only field Subscribers only field
Freemium Only 2018 Other Construction has started on the £10m O&M base in H... Subscribers only field Subscribers only field
Freemium Only 2018 BEIS published the Draft HRA document relating to ... Subscribers only field Subscribers only field
Freemium Only 2018 Galloper was officially inaugurated by Innogy.... Subscribers only field Subscribers only field
Freemium Only 2018 Tender Process The Invitation to Tender (ITT) stage for the OFTO ... Subscribers only field Subscribers only field
Freemium Only 2018 Fully Commissioned The wind farm achieved full generation with all 56... Subscribers only field Subscribers only field
Freemium Only 2018 Ownership Change ESB acquired a 12.5% stake in the project from Mac... Subscribers only field Subscribers only field
Freemium Only 2017 Turbine Installation The final wind turbine was installed at Galloper O... Subscribers only field Subscribers only field
Freemium Only 2017 Turbine Installation 50 out of 56 turbines have been installed.... Subscribers only field Subscribers only field
Freemium Only 2017 Turbine Installation 38 of the 56 turbines have been installed.... Subscribers only field Subscribers only field
Freemium Only 2017 On 7th November 2017 innogy announced that working... Subscribers only field Subscribers only field
Freemium Only 2017 Generating Power The project generated power for the first time on ... Subscribers only field Subscribers only field
Freemium Only 2017 In January 2017 the Government submitted the South... Subscribers only field Subscribers only field
Freemium Only 2017 innogy placed the first German corporate Green Bon... Subscribers only field Subscribers only field
Freemium Only 2017 Turbine Installation Galloper reached the half-way mark, with 28 of 56 ... Subscribers only field Subscribers only field
Freemium Only 2017 Turbine Installation 24 of 56 turbines installed.... Subscribers only field Subscribers only field
Freemium Only 2017 Turbine Installation Bibby Wavemaster is now onsite it was chartered to... Subscribers only field Subscribers only field
Freemium Only 2017 Turbine Installation Fred. Olsen Windcarrier vessel Bold Tern will mob... Subscribers only field Subscribers only field
Freemium Only 2017 Array Cable Installation VBMS installed the 56th and final array cable for ... Subscribers only field Subscribers only field
Freemium Only 2017 Tender Process Ofgem announced a shortlist of bidders competing t... Subscribers only field Subscribers only field
Freemium Only 2017 Export Cable Installation From the 21st of June until September 2017 the ves... Subscribers only field Subscribers only field
Freemium Only 2017 Turbine Installation The vessel Pacific Orca installed the first of 56 ... Subscribers only field Subscribers only field
Freemium Only 2017 Turbine Installation The Pacific Orca arrived on site with the first se... Subscribers only field Subscribers only field
Freemium Only 2017 Offshore Substation The vessel Seajacks Hydra will position itself alo... Subscribers only field Subscribers only field
Freemium Only 2017 Offshore Substation The vessel Oleg Strashnov had installed the jacket... Subscribers only field Subscribers only field
Freemium Only 2017 Export Cable Installation Around this date the cable lay and burial from Siz... Subscribers only field Subscribers only field
Freemium Only 2017 Turbine Installation The vessel MV Pacific Orca left for the site and w... Subscribers only field Subscribers only field
Freemium Only 2017 The Pacific Orca arrived at the Port of Great Yarm... Subscribers only field Subscribers only field
Freemium Only 2017 Export Cable Installation The CLV Ndurance set up offshore from Sizewell bea... Subscribers only field Subscribers only field
Freemium Only 2017 Export Cable Installation The final phase of Galloper construction work at S... Subscribers only field Subscribers only field
Freemium Only 2017 Offshore Substation The vessel Oleg Strashnov arrived at the site to b... Subscribers only field Subscribers only field
Freemium Only 2017 Production and Procurement The substation topside was loaded on to the barge ... Subscribers only field Subscribers only field
Freemium Only 2017 Array Cable Installation The first of 56 array cables was installed by the ... Subscribers only field Subscribers only field
Freemium Only 2017 Foundation Installation The 56th and final turbine foundation was installe... Subscribers only field Subscribers only field
Freemium Only 2017 Production and Procurement The first batch of array cables loaded on to the c... Subscribers only field Subscribers only field
Freemium Only 2017 Production and Procurement Heerema Fabrication moved the substation topside o... Subscribers only field Subscribers only field
Freemium Only 2017 Tender Process Ofgem invited companies to submit bids to own and ... Subscribers only field Subscribers only field
Freemium Only 2017 Production and Procurement The jacket for the substation platform was loaded ... Subscribers only field Subscribers only field
Freemium Only 2017 Foundation Installation The 28th of 56 foundations was installed on schedu... Subscribers only field Subscribers only field
Freemium Only 2017 Foundation Installation A total of eight monopiles and transition pieces h... Subscribers only field Subscribers only field
Freemium Only 2017 Grid Connection Available National Grid will provide a 348MW grid connection... Subscribers only field Subscribers only field
Freemium Only 2016 Other Completion of the onshore substation construction ... Subscribers only field Subscribers only field
Freemium Only 2016 Foundation Installation GeoSea's DP2 Innovation installed the first of 56 ... Subscribers only field Subscribers only field
Freemium Only 2016 Production and Procurement The first set of monopiles were loaded on to the t... Subscribers only field Subscribers only field
Freemium Only 2016 Other Application Submitted Galloper Wind Farm Ltd has confirmed it was pursui... Subscribers only field Subscribers only field
Freemium Only 2016 Tender Process Ofgem published the Preliminary Information Memora... Subscribers only field Subscribers only field
Freemium Only 2016 Export Cable Installation For 14 days the vessel Ndeavor will be engaging in... Subscribers only field Subscribers only field
Freemium Only 2016 Export Cable Installation The vessel Ndurance arrived at the substation site... Subscribers only field Subscribers only field
Freemium Only 2016 Export Cable Installation The vessel Ndurance began export cable installatio... Subscribers only field Subscribers only field
Freemium Only 2016 Production and Procurement The first sections of the monopiles arrived at Sif... Subscribers only field Subscribers only field
Freemium Only 2016 PreTesting The cable installation vessel Ndurance arrived in ... Subscribers only field Subscribers only field
Freemium Only 2016 Site Investigation The vessel RV Discovery began a survey on the expo... Subscribers only field Subscribers only field
Freemium Only 2016 Site Investigation UXO survey on array cable routes is planned for th... Subscribers only field Subscribers only field
Freemium Only 2016 Site Investigation Investigation and clearance of UXO for the export ... Subscribers only field Subscribers only field
Freemium Only 2016 Onshore Construction Starts Directional Drilling works at Sizewell for install... Subscribers only field Subscribers only field
Freemium Only 2015 Production and Procurement Fabrication and onshore construction of the compon... Subscribers only field Subscribers only field
Freemium Only 2015 Other Approval A public consultation was held regarding the draft... Subscribers only field Subscribers only field
Freemium Only 2015 Financial Close A new partnership heralds a green light for the co... Subscribers only field Subscribers only field
Freemium Only 2015 PreTesting The vessel INNOVATION arrived on site to perform t... Subscribers only field Subscribers only field
Freemium Only 2015 Financing Agreement The EIB approved the £425 million loan.... Subscribers only field Subscribers only field
Freemium Only 2015 Site Investigation UXO survey on export cable route was planned for t... Subscribers only field Subscribers only field
Freemium Only 2015 Financing Agreement The European Investment Bank put a proposed EIB fi... Subscribers only field Subscribers only field
Freemium Only 2015 RWE is 'continuing to make significant progress wi... Subscribers only field Subscribers only field
Freemium Only 2015 RWE has stated that good progress is being made on... Subscribers only field Subscribers only field
Freemium Only 2014 A Galloper spokesperson informed 4C Offshore that ... Subscribers only field Subscribers only field
Freemium Only 2014 From SSE's interim results for the six months to 3... Subscribers only field Subscribers only field
Freemium Only 2014 RWE decided not to continue with the project, in M... Subscribers only field Subscribers only field
Freemium Only 2014 Other Approval Galloper received planning consent from Suffolk Co... Subscribers only field Subscribers only field
Freemium Only 2014 From an Interim Management Statement released 22/0... Subscribers only field Subscribers only field
Freemium Only 2014 SSE has announced that it will not participate in ... Subscribers only field Subscribers only field
Freemium Only 2014 Tender Process It was announced that Lowestoft Port would be used... Subscribers only field Subscribers only field
Freemium Only 2014 Feasibility Study The FEED was finalised in Q1.... Subscribers only field Subscribers only field
Freemium Only 2013 Other Application Submitted A list of qualifying applicants and projects for t... Subscribers only field Subscribers only field
Freemium Only 2013 SSE announced that the planned capacity has been r... Subscribers only field Subscribers only field
Freemium Only 2013 Consent Authorised The Secretary of State granted development consent... Subscribers only field Subscribers only field
Freemium Only 2013 Site Investigation A geophysical survey was carried out by the MW Con... Subscribers only field Subscribers only field
Freemium Only 2012 Other Approval Galloper and EDF Energy made an agreement over lan... Subscribers only field Subscribers only field
Freemium Only 2012 Geotechnical Site Investigation Geotechnical site investigation took place.... Subscribers only field Subscribers only field
Freemium Only 2011 Other Approval The Infrastructure Planning Commission (IPC) forma... Subscribers only field Subscribers only field
Freemium Only 2011 Consent Application Submitted A Development Consent Order (DCO) was submitted to... Subscribers only field Subscribers only field
Freemium Only 2009 Other Approval Grid connection secured with National Grid.... Subscribers only field Subscribers only field