United Kingdom 270MW Fully Commissioned

login to improve information access

There are three levels of access, Free, Freemium (requires a sign-up – for free – and password access) and “Full” (Password access).
You need Full access to use the ForeSEE interactive system, access reports, updates, notes, news and downloads. Sign up now!

Events overview for Lincs

Event Date Event Type Event Description Event Source
Subscribers only field Subscribers only field Subscribers only field Subscribers only field
Freemium Only 2018 Lincs applied to the MMO for a license to remove a... Subscribers only field Subscribers only field
Freemium Only 2018 Turbine Service Agreement Expires The five-year OEM service agreement will expire.... Subscribers only field Subscribers only field
Freemium Only 2017 Turbine J/U WIND SERVER arrived on site to support heavy m... Subscribers only field Subscribers only field
Freemium Only 2017 Turbine Jack up vessel J/U WIND SERVER supported turbine m... Subscribers only field Subscribers only field
Freemium Only 2016 Foundation The vessel EGS Pioneer will carry out a survey on ... Subscribers only field Subscribers only field
Freemium Only 2016 Turbine Heavy lift jack up vessel Brave Tern carried out m... Subscribers only field Subscribers only field
Freemium Only 2015 Environmental and Seabed Monitoring The EGS vessel Wessex Explorer carryied out marine... Subscribers only field Subscribers only field
Freemium Only 2015 Environmental and Seabed Monitoring Diving works will commence at turbines LN04 and LN... Subscribers only field Subscribers only field
Freemium Only 2015 Turbine SEA CHALLENGER operated at three wind turbine loca... Subscribers only field Subscribers only field
Freemium Only 2015 Met Mast/LiDAR A turbine mounted Lidar from ZephIR Lidar was inst... Subscribers only field Subscribers only field
Freemium Only 2015 Performance Monitoring In the period of April 2014 to March 2015 the offs... Subscribers only field Subscribers only field
Freemium Only 2014 Centrica confirmed that it completed the sale of t... Subscribers only field Subscribers only field
Freemium Only 2014 Ofgem officially granted TV Lincs OFTO Limited a l... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Swire Blue Ocean's jack-up vessel Pacific Osprey a... Subscribers only field Subscribers only field
Freemium Only 2013 The Greater Wash Fishing Industry Group said that ... Subscribers only field Subscribers only field
Freemium Only 2013 Fully Commissioned Commissioning was fully completed.... Subscribers only field Subscribers only field
Freemium Only 2013 Generating Power The site was officially opened. Due to delays, pre... Subscribers only field Subscribers only field
Freemium Only 2013 Generating Power The 75th and final turbine was connected to the gr... Subscribers only field Subscribers only field
Freemium Only 2013 Generating Power Half of the turbines are generating power.... Subscribers only field Subscribers only field
Freemium Only 2013 Export Cable Export cable geophysical survey took place over a ... Subscribers only field Subscribers only field
Freemium Only 2013 Final Testing Ongoing commissioning works around turbines and ca... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation All 75 turbines were installed.... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation Construction update - 70/75 turbines installed. St... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation Construction update - 64/75 turbines installed. Co... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation Construction update: 55/75 turbines installation. ... Subscribers only field Subscribers only field
Freemium Only 2013 Array Cable Installation Array cable installation was completed on this day... Subscribers only field Subscribers only field
Freemium Only 2013 Array Cable Installation Some remaining array cable ends will be buried in ... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation Construction update: 45/75 turbines installed. Sta... Subscribers only field Subscribers only field
Freemium Only 2012 Turbine Installation Construction update: 40/75 turbines installed. Con... Subscribers only field Subscribers only field
Freemium Only 2012 Other Construction Update: 35/75 turbines installed, sec... Subscribers only field Subscribers only field
Freemium Only 2012 Turbine Installation Construction update: 35/75 turbines installed. Sta... Subscribers only field Subscribers only field
Freemium Only 2012 Turbine Installation Construction update: 30/75 turbines installed. Sta... Subscribers only field Subscribers only field
Freemium Only 2012 Array Cable Installation The array cabling installation was scheduled to fi... Subscribers only field Subscribers only field
Freemium Only 2012 Other Construction Update: 20/75 turbines installed, sec... Subscribers only field Subscribers only field
Freemium Only 2012 Turbine Installation 5 turbines had been installed.... Subscribers only field Subscribers only field
Freemium Only 2012 Generating Power First generation.... Subscribers only field Subscribers only field
Freemium Only 2012 Turbine Installation MPI Resolution arrived at the project site to comm... Subscribers only field Subscribers only field
Freemium Only 2012 Foundation Installation All foundations (monopiles and TPs) now installed.... Subscribers only field Subscribers only field
Freemium Only 2012 Export Cable Installation Approximately 8km of the export cable was installe... Subscribers only field Subscribers only field
Freemium Only 2012 Financing Agreement Gained non-recourse project facilities of £425m fr... Subscribers only field Subscribers only field
Freemium Only 2012 Foundation Installation Turbine Foundation Update: 75 of 75 monopiles inst... Subscribers only field Subscribers only field
Freemium Only 2012 Foundation Installation Construction Update: 51 of 75 foundations installe... Subscribers only field Subscribers only field
Freemium Only 2012 Array Cable Installation Update: 30% of array cables in place, and both off... Subscribers only field Subscribers only field
Freemium Only 2012 Foundation Installation The foundation installation was scheduled to finis... Subscribers only field Subscribers only field
Freemium Only 2012 Financing Agreement Reach financial close.... Subscribers only field Subscribers only field
Freemium Only 2012 Foundation Installation 48 of the foundations had been installed.... Subscribers only field Subscribers only field
Freemium Only 2011 Export Cable Installation 2 x export cables installed (but with some extra b... Subscribers only field Subscribers only field
Freemium Only 2011 Foundation Installation 41 foundations and transition pieces were installe... Subscribers only field Subscribers only field
Freemium Only 2011 Array Cable Installation The array cable installation began again starting ... Subscribers only field Subscribers only field
Freemium Only 2011 Offshore Substation The topside of the offshore substation was install... Subscribers only field Subscribers only field
Freemium Only 2011 Foundation Installation Installation of turbine's monopile foundations was... Subscribers only field Subscribers only field
Freemium Only 2011 Offshore Substation Installation of substation's jacket foundation was... Subscribers only field Subscribers only field
Freemium Only 2011 Export Cable Installation The export cabling installation was scheduled to b... Subscribers only field Subscribers only field
Freemium Only 2011 Offshore Substation Installation work was started on the substation's ... Subscribers only field Subscribers only field
Freemium Only 2010 Financing Agreement The European Investment Bank (EIB) to provide up t... Subscribers only field Subscribers only field
Freemium Only 2010 Onshore Construction Starts Onshore construction started.... Subscribers only field Subscribers only field
Freemium Only 2009 Financial Close The final investment decision (FID) was received o... Subscribers only field Subscribers only field
Freemium Only 2008 Consent Authorised Consent given by UK Government for 50-year lease. ... Subscribers only field Subscribers only field
Freemium Only 2007 Consent Application Submitted Project approval submitted.... Subscribers only field Subscribers only field