United Kingdom 62.1MW Fully Commissioned

login to improve information access

There are three levels of access, Free, Freemium (requires a sign-up – for free – and password access) and “Full” (Password access).
You need Full access to use the ForeSEE interactive system, access reports, updates, notes, news and downloads. Sign up now!

Events overview for Teesside

Event Date Event Type Event Description Event Source
Subscribers only field Subscribers only field Subscribers only field Subscribers only field
Freemium Only 2018 Other EDS HV Group has completed on-load tap changer (OL... Subscribers only field Subscribers only field
Freemium Only 2018 Turbine Service Agreement Expires EDF EN Services (EDF) has taken taken over the ope... Subscribers only field Subscribers only field
Freemium Only 2017 Turbine A gearbox exchange is planned to commence in mid a... Subscribers only field Subscribers only field
Freemium Only 2015 Environmental and Seabed Monitoring A geophysical survey commenced at Teesside. The wo... Subscribers only field Subscribers only field
Freemium Only 2014 Fully Commissioned The project was officially inaugurated. It had bee... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine The site has been shut down in order to investigat... Subscribers only field Subscribers only field
Freemium Only 2013 Generating Power 22 of 27 turbines were producing power and the rem... Subscribers only field Subscribers only field
Freemium Only 2013 Generating Power All 27 turbines were installed with 13 of them in ... Subscribers only field Subscribers only field
Freemium Only 2013 Other Scour protection installed on 11 turbines.... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation All 27 turbines have been erected. The turbines co... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation 25 of 27 turbines have been completely installed, ... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation 21/27 turbines erected one with rotor to fit, five... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation The first three wind turbines started to generate ... Subscribers only field Subscribers only field
Freemium Only 2013 Generating Power The first three wind turbines started to generate ... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation Construction update - 10 turbines installed.... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation Construction Update:
7/27 turbines installed. Co... Subscribers only field
Subscribers only field
Freemium Only 2013 Turbine Installation The first turbine has been installed there are sti... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Installation Turbine installation has started with the first to... Subscribers only field Subscribers only field
Freemium Only 2013 Foundation Installation Turbine installation activities have now started w... Subscribers only field Subscribers only field
Freemium Only 2012 Array Cable Installation Installation of the array cable was completed.... Subscribers only field Subscribers only field
Freemium Only 2012 Turbine Installation EDF announced that turbine installation would begi... Subscribers only field Subscribers only field
Freemium Only 2012 Turbine Installation All of the foundations, transition pieces, array c... Subscribers only field Subscribers only field
Freemium Only 2012 Foundation Installation Contractor Van Oord has completed the transition p... Subscribers only field Subscribers only field
Freemium Only 2012 Export Cable Installation Installation of the export cable is complete.... Subscribers only field Subscribers only field
Freemium Only 2012 Other Update: 9/27 Transition Pieces installed (Vessel J... Subscribers only field Subscribers only field
Freemium Only 2012 Foundation Installation Transition piece installation started but there we... Subscribers only field Subscribers only field
Freemium Only 2012 Array Cable Installation Array cable installation began in August 2012.... Subscribers only field Subscribers only field
Freemium Only 2012 Export Cable Installation Export cable installation began.... Subscribers only field Subscribers only field
Freemium Only 2012 Foundation Installation Transition piece installation started.... Subscribers only field Subscribers only field
Freemium Only 2012 Foundation Installation Installation of the monopile foundations has been ... Subscribers only field Subscribers only field
Freemium Only 2012 Foundation Installation 26 of the 27 monopile foundations have been instal... Subscribers only field Subscribers only field
Freemium Only 2012 Foundation Installation 23 of the 27 monopile foundations have been instal... Subscribers only field Subscribers only field
Freemium Only 2012 Foundation Installation 19 of the 27 monopile foundations have been instal... Subscribers only field Subscribers only field
Freemium Only 2012 Foundation Installation 17 of the 27 monopile foundations have been instal... Subscribers only field Subscribers only field
Freemium Only 2012 Foundation Installation 14 of the 27 monopile foundations have been instal... Subscribers only field Subscribers only field
Freemium Only 2012 Foundation Installation Ten of the 27 monopile foundations have been insta... Subscribers only field Subscribers only field
Freemium Only 2012 Foundation Installation Eight of the 27 monopile foundations have been ins... Subscribers only field Subscribers only field
Freemium Only 2012 Foundation Installation Seven of the 27 monopile foundations have been ins... Subscribers only field Subscribers only field
Freemium Only 2012 Foundation Installation Two of the 27 monopile foundations have been insta... Subscribers only field Subscribers only field
Freemium Only 2012 Foundation Installation The first foundation was installed.... Subscribers only field Subscribers only field
Freemium Only 2010 Financial Close The final investment decision was made in 2010.... Subscribers only field Subscribers only field
Freemium Only 2008 Geotechnical Site Investigation Ground investigation works was carried out by Soil... Subscribers only field Subscribers only field
Freemium Only 2007 Consent Authorised Principal cause for delays in consenting: Local Pl... Subscribers only field Subscribers only field
Freemium Only 2003 Consent Application Submitted Consent application was submitted.... Subscribers only field Subscribers only field