United Kingdom 183.6MW Fully Commissioned

login to improve information access

There are three levels of access, Free, Freemium (requires a sign-up – for free – and password access) and “Full” (Password access).
You need Full access to use the ForeSEE interactive system, access reports, updates, notes, news and downloads. Sign up now!

Events overview for Walney Phase 1

Event Date Event Type Event Description Event Source
Subscribers only field Subscribers only field Subscribers only field Subscribers only field
Freemium Only 2020 Turbine Update - delayed to 17th January.
MPI Resolution ... Subscribers only field
Subscribers only field
Freemium Only 2019 Ownership Change PGGM has acquired a 9.9 percent stake in the park ... Subscribers only field Subscribers only field
Freemium Only 2019 Turbine J/U WIND SERVER carried out component exchanges at... Subscribers only field Subscribers only field
Freemium Only 2018 Export Cable The power outage has been lifted following issues ... Subscribers only field Subscribers only field
Freemium Only 2018 Export Cable A power outage is still in force at turbine posit... Subscribers only field Subscribers only field
Freemium Only 2018 Export Cable A power outage occurred at the Walney 2 wind farm ... Subscribers only field Subscribers only field
Freemium Only 2017 Foundation The HBC Achiever will enter the wind farm from Bar... Subscribers only field Subscribers only field
Freemium Only 2017 Other A Bathymetric survey that covered all 102 turbines... Subscribers only field Subscribers only field
Freemium Only 2017 The Walney wind farm successfully restructured its... Subscribers only field Subscribers only field
Freemium Only 2017 Turbine The jack up vessel J/U WIND SERVER carried out a c... Subscribers only field Subscribers only field
Freemium Only 2016 Export Cable A geophysical survey of the nearshore export cable... Subscribers only field Subscribers only field
Freemium Only 2016 Turbine WIND SERVER completed the component exchanges at t... Subscribers only field Subscribers only field
Freemium Only 2016 Turbine The jack up vessel WIND SERVER has arrived and is ... Subscribers only field Subscribers only field
Freemium Only 2016 Site Investigation The vessel PRINCE MADOG is undertaking an environm... Subscribers only field Subscribers only field
Freemium Only 2016 Export Cable The vessel DEEP VOLANS that was on site surveying ... Subscribers only field Subscribers only field
Freemium Only 2016 Other Blue Transmission Walney 1 Limited reported transm... Subscribers only field Subscribers only field
Freemium Only 2016 Export Cable The vessel DEEP VOLANS and DEEP PURPLE began a geo... Subscribers only field Subscribers only field
Freemium Only 2016 Foundation Divers began inspection of the offshore substation... Subscribers only field Subscribers only field
Freemium Only 2016 Turbine A programme of turbine ladder cleaning maintenance... Subscribers only field Subscribers only field
Freemium Only 2016 Export Cable The vessel VALKYRIE began a survey along the expor... Subscribers only field Subscribers only field
Freemium Only 2016 Turbine The vessel J/U WIND SERVER arrived to exchange com... Subscribers only field Subscribers only field
Freemium Only 2016 Foundation A maintenance program involving the inspections of... Subscribers only field Subscribers only field
Freemium Only 2016 Array Cable Jack up vessel VIDAR (now Vole au Vent) support an... Subscribers only field Subscribers only field
Freemium Only 2016 Array Cable Jack up vessel VIDAR (now Vole au Vent) support an... Subscribers only field Subscribers only field
Freemium Only 2015 Environmental and Seabed Monitoring The vessel Fugro Seeker started a seabed survey.... Subscribers only field Subscribers only field
Freemium Only 2015 Turbine The offshore work vessel 'Offshore Wielingen' arri... Subscribers only field Subscribers only field
Freemium Only 2015 Turbine SEA CHALLENGER carried out maintenance/component c... Subscribers only field Subscribers only field
Freemium Only 2015 Performance Monitoring In the period of April 2014 to March 2015 the offs... Subscribers only field Subscribers only field
Freemium Only 2015 The MMO awarded Blue Transmission a marine licence... Subscribers only field Subscribers only field
Freemium Only 2014 Export Cable The 12m Catamaran ‘MTS XPLORER’ is undertaking Geo... Subscribers only field Subscribers only field
Freemium Only 2014 Site Investigation Geophysical surveys of the project site and the ex... Subscribers only field Subscribers only field
Freemium Only 2014 Site Investigation Bird surveys were carried out at Ormonde and Walne... Subscribers only field Subscribers only field
Freemium Only 2014 Environmental and Seabed Monitoring Benthic survey was undertaken for approximately 6 ... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Infield survey operations and, turbine and foundat... Subscribers only field Subscribers only field
Freemium Only 2014 Environmental and Seabed Monitoring Bird surveys were conducted from this date until 1... Subscribers only field Subscribers only field
Freemium Only 2014 Other Infield survey and turbine and foundation inspecti... Subscribers only field Subscribers only field
Freemium Only 2014 Export Cable Some parts of the export cable are only shallow bu... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine Component replacement on some of the turbines has ... Subscribers only field Subscribers only field
Freemium Only 2014 Turbine The turbine component replacement program started ... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine The maintenance work on C02, D01, B10 and A11 has ... Subscribers only field Subscribers only field
Freemium Only 2013 Turbine Worked started to exchange some major turbine comp... Subscribers only field Subscribers only field
Freemium Only 2013 Array Cable The burial of the replacement array cable has now ... Subscribers only field Subscribers only field
Freemium Only 2013 Array Cable The replacement array cable was installed and jett... Subscribers only field Subscribers only field
Freemium Only 2013 Array Cable Remedial work to array cabling between a turbine a... Subscribers only field Subscribers only field
Freemium Only 2012 Financing Agreement OPW (the PGGM and Ampere JV) refinances its 24.8% ... Subscribers only field Subscribers only field
Freemium Only 2012 Financing Agreement GIB provided £45m as part of a debt package to ref... Subscribers only field Subscribers only field
Freemium Only 2012 Foundation Rock dumping was carried out around each turbine f... Subscribers only field Subscribers only field
Freemium Only 2011 Fully Commissioned The project became fully operational. Walney 1 was... Subscribers only field Subscribers only field
Freemium Only 2011 Generating Power All turbines are producing power.... Subscribers only field Subscribers only field
Freemium Only 2011 Financing Agreement Statkraft signed a Power Purchase Agreement (PPA) ... Subscribers only field Subscribers only field
Freemium Only 2011 Array Cable Installation All the array cables have been placed and connecte... Subscribers only field Subscribers only field
Freemium Only 2011 Generating Power The wind farm produced power for the first time.... Subscribers only field Subscribers only field
Freemium Only 2011 Array Cable Installation All of the array cables, apart from one, have been... Subscribers only field Subscribers only field
Freemium Only 2011 Turbine Installation Turbine installation complete.... Subscribers only field Subscribers only field
Freemium Only 2010 Turbine Installation Following favourable weather conditions, 42 turbin... Subscribers only field Subscribers only field
Freemium Only 2010 Array Cable Installation 23 array cables have been placed and pulled betwee... Subscribers only field Subscribers only field
Freemium Only 2010 Offshore Substation The offshore substation was energised.... Subscribers only field Subscribers only field
Freemium Only 2010 PreTesting Export cable and onshore substation were connected... Subscribers only field Subscribers only field
Freemium Only 2010 Export Cable The export cable was accidently cut and required r... Subscribers only field Subscribers only field
Freemium Only 2010 Turbine Installation 28 wind turbine generators have now been installed... Subscribers only field Subscribers only field
Freemium Only 2010 Array Cable Installation 11 array cables have been placed in the seabed.... Subscribers only field Subscribers only field
Freemium Only 2010 Grid Connection Agreed 182MW of grid connection was made available by the... Subscribers only field Subscribers only field
Freemium Only 2010 Offshore Substation The final commissioning of the substation will be ... Subscribers only field Subscribers only field
Freemium Only 2010 Export Cable Installation The export cable lay was finished by the Stemat Sp... Subscribers only field Subscribers only field
Freemium Only 2010 Array Cable Installation Seven array cables have now been installed at the ... Subscribers only field Subscribers only field
Freemium Only 2010 Turbine Installation 23 wind turbine generators have now been installed... Subscribers only field Subscribers only field
Freemium Only 2010 Turbine Installation 12 of the 51 turbines have now been installed.... Subscribers only field Subscribers only field
Freemium Only 2010 Turbine Installation Ten turbines were completed and installed. Install... Subscribers only field Subscribers only field
Freemium Only 2010 Array Cable Installation Five array cables have been installed by the cable... Subscribers only field Subscribers only field
Freemium Only 2010 Other The last transition piece was installed on 17th Au... Subscribers only field Subscribers only field
Freemium Only 2010 Foundation Installation Goliath placed the last of the 51 transition piece... Subscribers only field Subscribers only field
Freemium Only 2010 Array Cable Installation Array cable installation began around August 2010,... Subscribers only field Subscribers only field
Freemium Only 2010 Export Cable Installation The export cable was initially planned to consist ... Subscribers only field Subscribers only field
Freemium Only 2010 Foundation Installation 35 monopiles and 33 transition pieces are currentl... Subscribers only field Subscribers only field
Freemium Only 2010 Turbine Installation The first turbine was installed around 1pm by the ... Subscribers only field Subscribers only field
Freemium Only 2010 Turbine Installation Turbine installation began. Installation vessel Kr... Subscribers only field Subscribers only field
Freemium Only 2010 Export Cable Installation Start of export cable installation.... Subscribers only field Subscribers only field
Freemium Only 2010 Foundation Installation 25 monopiles and 21 transition pieces have been su... Subscribers only field Subscribers only field
Freemium Only 2010 Offshore Substation The offshore substation installation started and a... Subscribers only field Subscribers only field
Freemium Only 2010 Foundation Installation The substation foundation installation started and... Subscribers only field Subscribers only field
Freemium Only 2010 Foundation Installation 21 monopiles have been installed in the seabed, as... Subscribers only field Subscribers only field
Freemium Only 2010 Foundation Installation Six transition pieces have been installed.... Subscribers only field Subscribers only field
Freemium Only 2010 Foundation Installation The first transition piece was installed.... Subscribers only field Subscribers only field
Freemium Only 2010 Foundation Installation Following favourable weather conditions, a total o... Subscribers only field Subscribers only field
Freemium Only 2010 Foundation Installation The first foundation was installed.... Subscribers only field Subscribers only field
Freemium Only 2010 Offshore Construction Starts Official start of construction.... Subscribers only field Subscribers only field
Freemium Only 2009 Financial Close Final Investment Decision (FID) made by the DONG E... Subscribers only field Subscribers only field
Freemium Only 2007 Consent Authorised Principal cause for delays in consenting: Birds (p... Subscribers only field Subscribers only field
Freemium Only 2006 Consent Application Submitted Consent application submitted.... Subscribers only field Subscribers only field