TGS | Powered by 4C Offshore

4C is now TGS

We are excited to announce a significant milestone in 4C Offshore's journey. Our integration into the TGS family marks the beginning of a new era in offshore wind market intelligence.


Learn what this means for you!

Ofgem - 3 x NEW electricity interconnectors

4C Offshore | Chris Anderson
By: Chris Anderson 06/03/2015 OFGEM
Ofgem proposes approving three new electricity interconnectors
  • Three new interconnectors would provide 3.4GW of additional capacity  
  • Ofgem’s new regulatory framework is securing greater interconnection to further boost GB’s energy supply
  • Ofgem does not propose to take forward one project as it does not provide sufficient value for consumers

Ofgem is today consulting on proposals to approve the need for three new electricity interconnectors. These could be built by 2020 and provide around 3.4GW of electricity capacity.  

Two of the interconnectors (FAB Link and IFA2) will connect GB’s electricity system with France and one (Viking Link) with Denmark. More electricity interconnection can lower GB consumer bills by creating access to cheaper generation and further boost Britain’s energy supply. These three interconnectors are estimated to provide around £8 billion of benefits to GB consumers over 25 years.  

Ofgem is consulting on not progressing the application for an interconnector between GB and Ireland (Greenlink), as proposals did not demonstrate enough value for GB consumers.  

Martin Crouch, Ofgem’s senior partner for electricity transmission, said: “Ofgem is helping to deliver greater interconnection. These three interconnectors would further boost Britain’s energy security and reduce pressure on bills. To date, under our cap and floor regime, we are looking at adding around 5GW to Britain’s energy supply.”

Interconnectors are transmission cables that allow electricity to flow from one country to another and there are currently four interconnectors between GB and Europe, providing around 4GW of electricity capacity. This represents around 4% of Britain’s electricity supply.

FAB Link

The European Commission to be invested in key energy infrastructure to enhance security of supply across Europe. This included €75 million for UK projects with cross-border benefits, including electricity interconnection (enabling electricity to be transferred between countries), smart grid and gas storage projects. €40 million went to two projects, one of which was FABLINK.  

On the EU Award Energy Secretary Edward Davey said:

“This is excellent news for the UK and Europe. The Commission’s decision to fast-track funding is a real boost to getting these projects built. The €40 million awarded to interconnector projects linking the UK to Norway and France will help strengthen energy security and deliver lower energy bills.”

FABLink holds potential to connect to future tidal generation being developed off the Alderney coast.

IFA2

This is a joint venture between National Grid plc, and Frances counterpart  Réseau de Transport d'Electricité (RTE), the French Transmission System Operator. IFA2 is being developed as a 1000MW HVDC link. In England, it will connect to the transmission system at a 400kV substation at Chilling Lane (cable sealing-end compound for the Fawley-Chilling cables) in Hampshire. The submarine route has already been surveyed and is around 207km in length, so altogether the onshore & offshore cable route will be nearly 240km long.  

The UK landing point for the sub-sea cables is near Folkestone, Kent and the French landing point for the sub-sea cables is near Calais, from where underground cables connect to Les Mandarins converter station and then on to the French transmission system where it will connect to the transmission system at the Tourbe 400kV sub-station in North Normandy, some 28km inland

VIKING Link

Viking Link is an HVDC submarine power cable with a capacity range of 700MW to 1,400MW, currently in the early stages of planning and development with desk studies ongoing to establish feasible converter sites, onshore and offshore HVDC cable routes, and landing points. The interconnector is expected to be approximately 650km in offshore cable length.

It is likely to connect Bicker Fen, southwest of Boston, Lincolnshire in the UK, to Revsing in Denmark.  Bicker Fen was in the News recently over residents opposition to RWE's plans to build a substation in the area to connect Triton Knoll Offshore windfarm to the grid.  

It is likely to connect Bicker Fen, southwest of Boston, Lincolnshire in the UK, to Revsing in Denmark.  Bicker Fen was in the News recently over residents opposition to RWE's plans to build a substation in the area to connect Triton Knoll Offshore windfarm to the grid.  

Currently RWE are going through a period of consultation with statutory bodies, landowners and communities on the electrical system.

The Interconnector strengthens RWE's case in many respects, and if both projects (Triton Knoll and Viking Link) proceed to completion will make Bicker Fen a power hub bringing up to 2GW of Electricity to the region.  

There are five interconnectors which have been assessed under the first application window for the cap and floor regime. Through this approach, if developers’ revenues exceed the cap, then revenue above the cap is returned to consumers. If their revenues fall below the floor then consumers top up revenues to the level of the floor.

Developers are protected by the revenue floor from the full financial risks of the project, while consumers are protected by the revenue cap from underwriting excessive profits.

The provision of additional HVDC interconnections to the European power network offers a number of potential benefits to GB and the end consumer. The degree of benefit depends in some cases on the location of the interconnector, and the technology employed.

To meet carbon reduction targets, the UK needs to introduce significant volumes of low-carbon generation, such as offshore wind and tidal generation, to replace conventional generation that relies on burning coal and gas.

Interconnectors will also play a significant role in meeting the carbon reduction targets. The European Commission set a target of having interconnection capacity of a minimum of 10% of generation capacity by 2020 and proposals to increase this to 15% by 2030.

The annual UK Future Energy Scenarios (FES)1 published by National Grid is designed to provide a credible and plausible analysis of energy scenarios up to 2035 with additional analysis looking to 2050.

The key changes for the electricity sector are expected to be in the way electricity is generated as mentioned above and how it is consumed. In terms of consumption, the FES suggests that heat pumps and electric vehicles are likely to create new demand for electricity. These changes create a new electricity system landscape that is very different to what the UK have been used to managing.

The dynamic operation of the transmission system is largely dependent on the type of generation connected to it, as well as the nature of demand on it. Some of the key impacts of these changes to the system as reported by the System Operability Framework (SOF)2  are:

> A reduction in system inertia and system strength;
> A greater variability of power flows; and
> The ability to restore the system following a potential blackout.

The ability to deal with the impact of these changes is dependent on the range of products and services available to the NETSO. Our analysis as part of the SOF shows that the GB power system requires new tools for managing these changes in order to ensure economic, efficient and coordinated system operation.

The GB electricity system is classed as an islanded power system with few links (known as interconnection) to other power systems. The GB system currently has around 4GW of interconnection to Ireland (Moyle and East-West; 1GW in total), France (IFA link; 2GW), and to the Netherlands (BritNed; 1GW). These links are currently operating as merchant interconnectors and provide the capability for import/export of energy to different systems.

Traditionally interconnectors have been primarily intended to provide capacity for energy flows between different synchronous areas. Interconnectors currently provide a range of services to the System Operator (SO) such as cross-border balancing, trading, and SO-SO trades for network/system support.

Details of the proposed interconnectors

Project Name Developers Connection Locations Capacity
FAB Link Transmission Investment and RTE (the French transmission system operator) Menuel in France and Exeter in Devon, England, via the island of Alderney. 1.4GW
IFA2 National Grid Interconnector Holdings (NGIH) and RTE Tourbe in France and Chilling in Hampshire, England 1GW
Viking Link NGIH and Energinet.dk (the Danish transmission system operator) Revsing in Denmark and Bicker Fen in Lincolnshire, England 1GW
Greenlink Element Power Great Island in Ireland and Pembroke in Wales 0.5GW











To see project details for each of the projects mentioned above click this link then select project for details

Premium

4C Offshore Premium, our most popular subscription, gives you full access to use the 4C Offshore WebApp which includes exclusive offshore wind, transmission and vessel reports, news and downloads.

Request a 30 minute Demo

Trending News!