Alpha Ventus
60 MW Fully Commissioned Germany
Updated weekly to include the latest news, your feedback and other data.
38 Countries, 1323 Windfarms, 9111 Stakeholders, 4314 Events, 824 Vessels, 154 Turbines NEW, 42 Ports,
Filter Projects by Country
Featured Ports
Featured Port
Able Seaton Port, United Kingdom Image of <%# Eval("PortName") %> Maximum Trenched Depth: 15 m
Entrance Width: 125 m
Spring Tidal Range: 4.6 m
Quay Length: 791 m
Quay Loading Capability: 60 tonnes/m2
Land for Development: 45 ha
More details...



Who is generating power
Who's Generating Power?
1.  United Kingdom - 3321.2000 MW
2.  Denmark - 871.4800 MW
3.  China - 559.5000 MW
More...
Whose Turbines are Generating?
Whose Turbines are Generating?
1.  Siemens Wind Power A/S (Siemens AG) - 3084.8000 MW
2.  Vestas Offshore A/S (Vestas Wind Systems A/S) - 1401.1200 MW
3.  REpower Systems AG (Suzlon Energy Limited) - 434.5000 MW
Loading Map
Equipment Available for Charter
Statistics for Alpha Ventus
General Information Name Alpha Ventus correct
Other names Borkum West I correct
Country name Germany correct
Region Exclusive Economic Zone (DolWin) (BSH Cluster 2 in Draft Network Plan) correct
Comments Also known as Borkum West I.
Wind Park made up of 6 Multibrid M5000 turbines (Rotor Diameter 116m, Hub Height 90m Total height 148m, Tripod) and 6 REpower turbines (Rotor Diameter 126m, Hub Height 92m Total height 155m, Jacket).
An added benefit of the wind farm is that colonies of oysters, crabs and anemones have begun to populate the turbine bases.
correct
Round (or category) correct
Development status Fully Commissioned correct
Comments on the status correct
Power & Turbines Notice any Errors? You can keep this an open resource by submitting corrections!
Project Capacity 60 MW correct
Turbine Model M5000-116 (Areva Wind), REpower 5M correct
Turbine Capacity 5 MW correct
Number of Turbines 12 correct
Total Turbine Height 150 m correct
Hub Height 92.00 m correct
Rotor Diameter 116 m correct
Foundation Various (Tripod and Jacket) correct
Windspeed 10 Year Mean Wind Speed (2000-2009) Available online now
Detailed wind speed data 6 hr/day/month historic data
Costs Stated Project Cost EUR(mill) 250.00 correct
Location & Environment Sea name North Sea correct
Centre latitude 54.010° correct
Centre longitude 6.606° correct
Area 4 km2 correct
Depth range (Chart Datum) 28 m - 30 m correct
Depth range stated by developer 33 m - 45 m correct
Distance From Shore (reported) 56 km correct
Distance From Shore (computed from centre) 56 km correct
Ports Installation base Wilhelmshaven/Bremerhaven correct
Ops and maintenance Eemshaven correct
Grid Converter platforms None correct
Offshore transformers Alpha Ventus Substation correct
Grid connection point Hagermarsch correct
Cable landing point Hilgenriedersiel correct
Export Cables
Please note that export cables connect the offshore transformer (substation) to either; shore or an offshore HVAC-HVDC converter station for onward transmission via HVDC cabling. Please see the converters page for planned converter stations and transmission cables.

The export cable length does not generally include the onshore component. The exception is when the onshore substation is close to shore.
Number of Export Cables 1 correct
Average length per cable 60 km correct
Transmission type (e.g. HVAC) HVAC correct
Nominal voltage 110 kV correct
Maximum voltage correct
Power rating correct
Number of cores 3 correct
Conductor type Cu correct
Section 240 mm2 correct
Insulation XLPE correct
Number fibre optics 48 correct
Minimum bend radius (MBR) correct
Burial depth correct
Comments correct
Onshore Cables (new) Number of onshore cables correct
Average length per cable correct
Comments correct
Array Cables Array cable length 16 km correct
Estimated cable length In purchased database
Transmission type (e.g. MVAC) MVAC correct
Nominal voltage 33 kV correct
Maximum voltage correct
Burial depth 0.6 m correct
Number of cores 3 correct
Conductor type Cu correct
Section 240 mm2 correct
Insulation correct
Power rating correct
Number of fibre optics 48 correct
Minimum bend radius (MBR) correct
Comments correct
Benefits Homes powered annually 33549 correct
CO2 reduced per year 67802 tonnes correct
SO2 reduced per year 1577 tonnes correct
Expected life 20.0 years correct
Other Website Visit correct

Events on Alpha Ventus
12
DateTypeDescriptionSourceCorrect
12-Oct-2010
Event Type: Operation - Service and Maintenance                                                                                                                                                                                                                            Operation - Service and Maintenance
The nacelles of the six Multibrid turbines were replaced due to overheating of the bearings. Visit correct
27-Apr-2010
Event Type: Operation - Fully Commissioned                                                                                                                                                                                                                                 Operation - Fully Commissioned
Fully commissioned. Visit correct
30-Nov-2009
Event Type: Installation - Cable installation                                                                                                                                                                                                                              Installation - Cable installation
Installation of the array cables finished in Autumn 2009. Visit correct
16-Nov-2009
Event Type: Installation - Turbine Installation                                                                                                                                                                                                                            Installation - Turbine Installation
The last turbine was installed of the 6 REpower 5MW turbines. Visit correct
30-Sep-2009
Event Type: Installation - Turbine Installation                                                                                                                                                                                                                            Installation - Turbine Installation
The first of six REpower 5MW turbines was installed. Visit correct
15-Jul-2009
Event Type: Installation - Turbine Installation                                                                                                                                                                                                                            Installation - Turbine Installation
The first of six Multibrid turbines installed. Visit correct
08-Jun-2009
Event Type: Installation - Foundation Installation                                                                                                                                                                                                                         Installation - Foundation Installation
Foundation Installation started for the REpower turbines Visit correct
Jun-2009
Event Type: Installation - Foundation Installation                                                                                                                                                                                                                         Installation - Foundation Installation
The last foundation for the Multibrid turbines was installed on June 1st Visit correct
17-Apr-2009
Event Type: Installation - Foundation Installation                                                                                                                                                                                                                         Installation - Foundation Installation
The first foundation for the Multibrid turbines started. Visit correct
Apr-2009
Event Type: Installation - Cable installation                                                                                                                                                                                                                              Installation - Cable installation
Installation of the array cables began in Spring 2009. Visit correct
12

Please click to add windfarm events via this link, providing approximate date etc. Possible events include consent submission, approval, installation, generating power etc.
Be the first to comment on Alpha Ventus offshore wind farm Please note, your comment will take 1 hour to appear.

Your Name * :  
Web Site (optional) : http://  
Comment * :  
* required