DateEventDescription 
LogIn Event Type: Decommissioning - Decommissioning
Decommissioning The expected minimum designated service life of the offshore wind farm and its transmission assets is 20 years.
Source: LogIn
correct
LogIn Event Type: Other -
Other OFGEM confirmed that Rampion successfully applied for the 'enabling financial decisions grace period'. Under the grace period extension, ROC accreditation and commissioning of 20% of the project is required by the end of March LogIn. Rampion holds a 15-year Power Purchase Agreement.
Source: LogIn
correct
LogIn Event Type: Operation - Fully Commissioned
Fully Commissioned Offshore construction and commissioning is expected to complete by March LogIn.
Source: LogIn
correct
LogIn Event Type: Planning - Tender Process
Tender Process It is currently envisaged that a Preferred Bidder for Rampion's offshore transmission assets will be appointed in December LogIn.
Source: LogIn
correct
LogIn Event Type: Operation - Generating Power
Generating Power First power from the project is anticipated during Q3 LogIn.
Source: LogIn
correct
LogIn Event Type: Installation - Cable installation
Cable installation Installation of the second phase of 62 inter-array cables will commence, with completion by the summer.
Source: LogIn
correct
LogIn Event Type: Installation - Offshore Substation
Offshore Substation During Q2 LogIn the substation topside will be installed by the vessel Rambiz.
Source: LogIn
correct
LogIn Event Type: Inspection, Maintenance & Repair - Export Cable
Export Cable During Q2 LogIn one of the export cables is scheduled to be jointed after a section was cut out and removed during the laying process.
Source: LogIn
correct
10-Mar-2017 Event Type: Installation - Turbine Installation
Turbine Installation The MPI Discovery installed the first turbine at the site. The vessel carried eight nacelles, eight towers and 24 turbine blades.
Source: LogIn
correct
08-Mar-2017 Event Type: Installation - Turbine Installation
Turbine Installation The MPI Discovery arrived on site to begin turbine installation.
Source: LogIn
correct
Mar-2017 Event Type: Planning - Tender Process
Tender Process Ofgem announced the shortlist of bidders that will compete to own and operate the Rampion transmission link: Balfour Beatty Investments, Equitix, Diamond Transmission Partners, Mari Energy Transmission and Transmission Capital Partners.
Source: LogIn
correct
02-Feb-2017 Event Type: Installation - Other
Other During the winter months the main site activity was the tensioning of the foundation bolts. The vessels Windcat 10, Windcat 17 and MPI Discovery carried out the work.
Source: LogIn
correct
12-Dec-2016 Event Type: Installation - Cable installation
Cable installation During the week starting 12th December VBMS completed the installation of two 16km long 150kV HVAC export cables.
VBMS extended the pre drilled ducts by 480m each. This allowed the CLV Stemat Spirit to lay the cables.

Source: LogIn
correct
22-Nov-2016 Event Type: Installation - Cable installation
Cable installation The vessel Fugro Saltire completed cable burial by this date using Fugro's high performance Q1400 subsea trenching system. The installation and burial of 60 cables marks the completion of phase one as the programme prepares for a winter break - three more cables were installed and buried than previously planned. Both Fugro Symphony and Fugro Saltire will return next spring to complete the remaining 62 cables.
Source: LogIn
correct
09-Nov-2016 Event Type: Installation - Foundation Installation
Foundation Installation The jack-up vessel MPI Discovery and Pacific Orca have collectively completed installation of Rampion's 116 monopile foundations. MPI Discovery installed 69 foundations whilst the Pacific Orca installed the remaining 47.
Source: LogIn
correct
Nov-2016 Event Type: Failure - Export Cable
Export Cable During November a section of one of the export cables was removed while it was being installed. The section is scheduled to be jointed in Q2 2017.
Source: LogIn
correct
31-Oct-2016 Event Type: Installation - Cable installation
Cable installation By this date the vessel Fugro Symphony had laid 60 strings of array cables and had moved off site for the winter period.
Source: LogIn
correct
24-Oct-2016 Event Type: Installation - Foundation Installation
Foundation Installation The vessel MPI Discovery had installed 60 foundations while the ORCA installed 39 foundations. 102 of 116 foundations installed.
Source: LogIn
correct
16-Oct-2016 Event Type: Installation - Foundation Installation
Foundation Installation The vessel MPI Discovery had installed 59 foundations while the ORCA installed 36 foundations. 98 of 116 foundations installed.
Source: LogIn
correct
13-Oct-2016 Event Type: Installation - Cable installation
Cable installation Export cable installation vessel Stemat Spirit arrived at the nearshore area of the cable route and began cable installation.
Source: LogIn
correct
10-Oct-2016 Event Type: Planning - Tender Process
Tender Process Ofgem published the Preliminary Information Memorandum report that revealed the Initial Transfer Values for projects included in TR5, of which one was Rampion. Rampion's transmission assets were valued at £313.1 million. Collectively, the five offshore transmission links included in TR5 hold an estimated value of £2 billion and a total generation capacity of 2.3GW making it the largest tender round to date.
Source: LogIn
correct
10-Oct-2016 Event Type: Installation - Foundation Installation
Foundation Installation The vessel MPI Discovery had installed 57 foundations while the ORCA installed 34 foundations. 94 of 116 foundations installed.
Source: LogIn
correct
10-Oct-2016 Event Type: Planning - Tender Process
Tender Process Ofgem has announced that the Offshore Transmission Owner (OFTO) Tender Round Five (TR5) will start on 10th October 2016 with Race Bank, Rampion and Dudgeon. The projects Galloper and Walney Extension will follow in March 2017. TR5 will enable bidders to compete to own the transmission assets of five offshore wind farm projects with an approximate total generation capacity of 2.3GW.
The wind farms that will have their transmission systems up for tender will be the 402MW Dudgeon Offshore Wind Farm (OWF), 340MW Galloper OWF, 565MW Race Bank OWF, 400.2MW Rampion OWF and 659MW Walney Extension OWF.
Each transmission system is constructed by the wind farm developer and Ofgem will then administer the tender process for each project, which will result in the appointment of an OFTO to own and operate those systems.
Rampion's transmission assets have been valued at £313.3m.

Source: LogIn
correct
03-Oct-2016 Event Type: Installation - Foundation Installation
Foundation Installation The vessel MPI Discovery had installed 54 foundations while the ORCA installed 32 foundations. 89 of 116 foundations installed.
Source: LogIn
correct
24-Sep-2016 Event Type: Installation - Foundation Installation
Foundation Installation The vessel MPI Discovery had installed 51 foundations while the ORCA installed 28 foundations. 82 of 116 foundations installed.
Source: LogIn
correct
20-Sep-2016 Event Type: Installation - Offshore Substation
Offshore Substation The vessel Rambiz installed the substation's jacket foundation.
Source: LogIn
correct
16-Sep-2016 Event Type: Installation - Cable installation
Cable installation The vessel Fugro Saltire has arrived on the site and buried 4 of the array cable strings.
Source: LogIn
correct
16-Sep-2016 Event Type: Installation - Foundation Installation
Foundation Installation The vessel MPI Discovery had installed 48 foundations while the ORCA installed 25 foundations. 76 of 116 foundations installed.
Source: LogIn
correct
08-Sep-2016 Event Type: Installation - Cable installation
Cable installation By this date the vessel Fugro Symphony had laid 15 strings of array cables. H01-I01, I02-H02, J02-I02, G02-H01, F03-G02, J02-I01, F04-F03, H02-G03, G03-H03, H03-I03, I03-J03, J03-K03, K03-L04, L04-K04 and K04-J04.
Source: LogIn
correct
08-Sep-2016 Event Type: Installation - Foundation Installation
Foundation Installation The vessel MPI Discovery had installed 44 foundations while the ORCA installed 21 foundations. 68 of 116 foundations installed.
Source: LogIn
correct
123
Add new windfarm events, providing approximate date etc. Possible events include consent submission, approval, installation, generating power etc.

Call +44 (0)1502 307 037 for more information

Keep on top of the market. Perform analysis. Make informed decisions.

CONTACT US

Did you know?

You get monthly updates with our Offshore Windfarm Subscription and receive even more detailed information about: turbines costs foundations substations converters cabling

Filter :
123
StatusName
Decommissioned Beatrice Demonstration Beatrice Demonstration
Decommissioned Blyth Blyth
Fully Commissioned Barrow Barrow
Fully Commissioned Burbo Bank Burbo Bank
Fully Commissioned Greater Gabbard Greater Gabbard
Fully Commissioned Gunfleet Sands Gunfleet Sands
Fully Commissioned Gunfleet Sands 3 - Demonstration Project Gunfleet Sands 3 - Demonstration Project
Fully Commissioned Gwynt y Môr Gwynt y Môr
Fully Commissioned Humber Gateway Humber Gateway
Fully Commissioned Hunterston Test Centre - Mitsubishi 7MW (onshore) Hunterston Test Centre - Mitsubishi 7MW (onshore)
Fully Commissioned Hunterston Test Centre - Siemens 6MW (onshore) Hunterston Test Centre - Siemens 6MW (onshore)
Fully Commissioned Hunterston Test Centre (onshore) Hunterston Test Centre (onshore)
Fully Commissioned Inner Dowsing Inner Dowsing
Fully Commissioned Kentish Flats Kentish Flats
Fully Commissioned Kentish Flats Extension Kentish Flats Extension
Fully Commissioned Levenmouth demonstration turbine Levenmouth demonstration turbine
Fully Commissioned Lincs Lincs
Fully Commissioned London Array London Array
Fully Commissioned Lynn Lynn
Fully Commissioned North Hoyle North Hoyle
Fully Commissioned Ormonde Ormonde
Fully Commissioned Rhyl Flats Rhyl Flats
Fully Commissioned Robin Rigg Robin Rigg
Fully Commissioned Scroby Sands Scroby Sands
Fully Commissioned Sheringham Shoal Sheringham Shoal
Fully Commissioned Teesside Teesside
Fully Commissioned Thanet Thanet
Fully Commissioned Walney Phase 1 Walney Phase 1
Fully Commissioned Walney Phase 2 Walney Phase 2
Fully Commissioned Wave Hub Wave Hub
Fully Commissioned West of Duddon Sands West of Duddon Sands
Fully Commissioned Westermost Rough Westermost Rough
Partial Generation/Under Construction Burbo Bank Extension Burbo Bank Extension
Partial Generation/Under Construction Dudgeon Dudgeon
Under Construction Galloper Galloper
Under Construction Race Bank Race Bank
Under Construction Rampion Rampion
Pre-Construction Aberdeen Offshore Wind Farm (EOWDC) Aberdeen Offshore Wind Farm (EOWDC)
Pre-Construction Beatrice Beatrice
Pre-Construction Blyth Offshore Demonstrator Project - Array 2 Blyth Offshore Demonstrator Project - Array 2
Pre-Construction East Anglia ONE East Anglia ONE
Pre-Construction Hornsea Project One Hornsea Project One
Pre-Construction Hywind Scotland Pilot Park Hywind Scotland Pilot Park
Pre-Construction Walney Extension Walney Extension
Consent Authorised Blyth Offshore Demonstrator Project - Array 3A & 4 Blyth Offshore Demonstrator Project - Array 3A & 4
Consent Authorised Dogger Bank - Creyke Beck A Dogger Bank - Creyke Beck A
Consent Authorised Dogger Bank - Creyke Beck B Dogger Bank - Creyke Beck B
Consent Authorised Dogger Bank - Teesside A Dogger Bank - Teesside A
Consent Authorised Dogger Bank - Teesside B Dogger Bank - Teesside B
Consent Authorised Dounreay Trì Dounreay Trì
123
Please LogIn to follow projects
Find quick and easy project and company information with our online search tool

This page is intended to be viewed online and may not be printed without a valid subscription.

Please view this page at http://www.4coffshore.com/windfarms/events.aspx?windfarmID=uk36.