Latest event on Walney Phase 1

The Walney wind farm successfully restructured its debt to enable access to favourable interest rates in line with current market conditions. Read more

Latest Update: 23 January 2017

Developers/Owners/Operators Database in Excel | Add Your Organisation
RoleOrganisation 
Developer correct
Operator correct
Operator-Offshore Transmission correct
Owner
12.4% stake. A consortium of PGGM and Dutch Ampère Equity Fund, managed by Triodos Investment Management, have entered into an agreement with DONG Energy whereby the consortium acquires a 24.8% stake. DONG Energy will retain a 50.1% stake and SSE will retain the 25.1% stake it acquired from DONG Energy in December 2009.
Update: In December 2012, OPW (the PGGM and Ampere JV) refinances its 24.8% stake. Refinance provided by consortium of five banks providing senior debt of GBP 224m (GBP 45m coming from new UK Green Investment Bank)

Value: LogIn
correct
Owner
12.4% stake. A consortium of PGGM and Dutch Ampère Equity Fund, managed by Triodos Investment Management, have entered into an agreement with DONG Energy whereby the consortium acquires a 24.8% stake. DONG Energy will retain a 50.1% stake and SSE will retain the 25.1% stake it acquired from DONG Energy in December 2009.
Update: In December 2012, OPW (the PGGM and Ampere JV) refinances its 24.8% stake. Refinance provided by consortium of five banks providing senior debt of GBP 224m (GBP 45m coming from new UK Green Investment Bank)

Value: LogIn
correct
Owner correct
Owner correct
Owner-Offshore Transmission correct
Project Details for Walney Phase 1 Database in Excel
Name Walney Phase 1 correct
Other names correct
Country name United Kingdom correct
Region England, North West correct
Comments Cost is for the two sites (Walney 1 and 2) and excludes cost of connection to grid. The assessed transfer value of the Walney 1 project transmission assets is £105,411,350.

Project uses the met mast at Cirrus Shell Flats
correct
Round (or category) Round 2 correct
Development status Fully Commissioned correct
Comments on the status correct
Notice any Errors? You can keep this an open resource by submitting corrections!
Project capacity 183.6 MW correct
Turbine model SWT-3.6-107 (Siemens) correct
Turbine capacity 3.6 MW correct
Number of turbines 51 correct
Total turbine height 137 m correct
Hub height 83.50 m correct
Rotor diameter 107 m correct
Foundation Grounded: Monopile correct
10 year mean wind speed (2000-2009) Available online now
Stated project cost GBP(mill) 630.00 correct
Sea name Irish Sea correct
Centre latitude 54.041° correct
Centre longitude -3.514° correct
Area 28 km2 correct
Depth range (Chart Datum) 19 m - 23 m correct
Depth range stated by developer 19 m - 28 m correct
Distance from shore (reported) 14 km correct
Distance from shore (computed from centre) 19.3 km correct
Installation base Barrow and Mostyn correct
Ops and maintenance Barrow correct
Converter/Collector platforms None correct
Offshore transformers Walney Phase 1 Substation correct
Grid connection point Heysham correct
Cable landing point Heysham correct
Number of export cables 1 correct
Average length per cable 43 km correct
Transmission type (e.g. HVAC) HVAC correct
Nominal voltage 132 kV correct
Maximum voltage correct
Power rating 192 MVA correct
Number of cores 3 correct
Conductor type Cu correct
Section area 630 mm2 correct
Insulation XLPE correct
Number fibre optics 48 correct
Export minimum bend radius (MBR) 3 m correct
Burial depth 2 m correct
Comments Diameter 209mm, non-coilable correct
Number of onshore cables 3 correct
Average length per cable 2.7 km correct
Comments 3 single core, 132kV, 192MVA correct
Array cable length 46 km correct
Estimated cable length LogIn
Transmission type (e.g. MVAC) MVAC correct
Nominal voltage 33 kV correct
Maximum voltage correct
Burial depth 2 m correct
Number of cores 3 correct
Conductor type Cu correct
Section 150/500 mm2 correct
Insulation correct
Power rating correct
Number of fibre optics 40 correct
Minimum bend radius (MBR) correct
Comments ICC: 3 x 150 mm2, 33 kV + fibre optic cable (16 fibres). PCC: 3 x 500 mm2, 33 kV + fibre optic cable (24 fibres).  correct
Homes powered annually 130036 correct
CO2 reduced per year 262802 tonnes correct
SO2 reduced per year 6112 tonnes correct
Expected life 20.0 years correct
Website Visit correct

Call +44 (0)1502 307 037 for more information

Keep on top of the market. Perform analysis. Make informed decisions.

CONTACT US

More information?

Receive monthly updates with our Offshore Windfarm Subscription and gain access to even more detailed information on; cabling, converters, costs, foundations, substations, turbines.

Filter :
123
StatusName
Decommissioned Beatrice Demonstration Beatrice Demonstration
Decommissioned Blyth Blyth
Fully Commissioned Barrow Barrow
Fully Commissioned Burbo Bank Burbo Bank
Fully Commissioned Greater Gabbard Greater Gabbard
Fully Commissioned Gunfleet Sands Gunfleet Sands
Fully Commissioned Gunfleet Sands 3 - Demonstration Project Gunfleet Sands 3 - Demonstration Project
Fully Commissioned Gwynt y Môr Gwynt y Môr
Fully Commissioned Humber Gateway Humber Gateway
Fully Commissioned Hunterston Test Centre - Mitsubishi 7MW (onshore) Hunterston Test Centre - Mitsubishi 7MW (onshore)
Fully Commissioned Hunterston Test Centre - Siemens 6MW (onshore) Hunterston Test Centre - Siemens 6MW (onshore)
Fully Commissioned Hunterston Test Centre (onshore) Hunterston Test Centre (onshore)
Fully Commissioned Inner Dowsing Inner Dowsing
Fully Commissioned Kentish Flats Kentish Flats
Fully Commissioned Kentish Flats Extension Kentish Flats Extension
Fully Commissioned Levenmouth demonstration turbine Levenmouth demonstration turbine
Fully Commissioned Lincs Lincs
Fully Commissioned London Array London Array
Fully Commissioned Lynn Lynn
Fully Commissioned North Hoyle North Hoyle
Fully Commissioned Ormonde Ormonde
Fully Commissioned Rhyl Flats Rhyl Flats
Fully Commissioned Robin Rigg Robin Rigg
Fully Commissioned Scroby Sands Scroby Sands
Fully Commissioned Sheringham Shoal Sheringham Shoal
Fully Commissioned Teesside Teesside
Fully Commissioned Thanet Thanet
Fully Commissioned Walney Phase 1 Walney Phase 1
Fully Commissioned Walney Phase 2 Walney Phase 2
Fully Commissioned Wave Hub Wave Hub
Fully Commissioned West of Duddon Sands West of Duddon Sands
Fully Commissioned Westermost Rough Westermost Rough
Partial Generation/Under Construction Burbo Bank Extension Burbo Bank Extension
Partial Generation/Under Construction Dudgeon Dudgeon
Under Construction Galloper Galloper
Under Construction Race Bank Race Bank
Under Construction Rampion Rampion
Pre-Construction Aberdeen Offshore Wind Farm (EOWDC) Aberdeen Offshore Wind Farm (EOWDC)
Pre-Construction Beatrice Beatrice
Pre-Construction Blyth Offshore Demonstrator Project - Array 2 Blyth Offshore Demonstrator Project - Array 2
Pre-Construction East Anglia ONE East Anglia ONE
Pre-Construction Hornsea Project One Hornsea Project One
Pre-Construction Hywind Scotland Pilot Park Hywind Scotland Pilot Park
Pre-Construction Walney Extension Walney Extension
Consent Authorised Blyth Offshore Demonstrator Project - Array 3A & 4 Blyth Offshore Demonstrator Project - Array 3A & 4
Consent Authorised Dogger Bank - Creyke Beck A Dogger Bank - Creyke Beck A
Consent Authorised Dogger Bank - Creyke Beck B Dogger Bank - Creyke Beck B
Consent Authorised Dogger Bank - Teesside A Dogger Bank - Teesside A
Consent Authorised Dogger Bank - Teesside B Dogger Bank - Teesside B
Consent Authorised Dounreay Trì Dounreay Trì
123
Please LogIn to follow projects
Find quick and easy project and company information with our online search tool