General Information Converter/Collector Name DolWin5 Converter correct
Status Planned correct
Latitude 54.019 ° correct
Longitude 6.294 ° correct
Comments The project will connect at Halbemond. correct
Foundation Foundation Type Grounded: correct
Foundation Weight correct
Foundation Comments correct
Topside Topside Weight correct
Topside Dimensions (LxWxH) correct
Helideck correct
Electrical Specifications Power 900 MW correct
DC Voltage Level correct
AC Voltage Level correct
Number of Transformers correct
Other Equipment correct
Transmission Cable Cable Name Cluster 1 Converter 1 to Cloppenburg correct
Number of Transmission Cables 2 correct
Minimum Cable Length 115 km correct
Depth Buried correct
Nominal Voltage correct
Conductor Type HVDC correct
Section correct
Insulation correct
Cost of the Transmission Cable correct
Cost Description correct
Comments on the Transmission Cable The route traverses from the EEZ to the Territorial Sea through Gate II. The total on and offshore length is 230km, with grid connection point in Cloppenburg. correct

Call +44 (0)1502 307 037 for more information

Keep on top of the market. Perform analysis. Make informed decisions.

CONTACT US
Keep on top of the market. Perform analysis. Make informed decisions.

This page is intended to be viewed online and may not be printed without a valid subscription.

Please view this page at https://www.4coffshore.com/transmission/converter-details.aspx?cid=93.