Port Esbjerg unveils digital wind solution for offshore wind logistics

4C Offshore | Tom Russell
By: Tom Russell 18/01/2023 Port Esbjerg

Port Esbjerg announced it is using a digital twin system that can calculate efficient methods for deploying offshore wind installations. It claims the digital tool will have a dramatic effect on the port’s wind capacity, as the port will be able to triple its annual shipping capacity for offshore wind installations from 1.5 GW to 4.5 GW.


The US company Moffatt & Nichol developed the digital twin for Port Esbjerg. The program is fed data, enabling it to analyse all port processes related to the shipping of offshore wind installations, using a 1:1 simulation of the port. Everything from storage locations of wind components and space requirements to the impact of high tide and much more. In this way, all processes are optimised.


“Working with the digital twin is a gamechanger. We can make much better decisions using that tool. It means that we can triple our capacity at Port Esbjerg without expanding by a single square metre,”
Port Esbjerg CEO Dennis Jul Pedersen said.


“We’re now the first port in the world to have a digital twin for offshore wind. However, it could play a huge role in the deployment of wind installations across the whole of Europe in the coming years. There’s a lack of space at most wind ports in Europe, so we need to pull the ports out of our spreadsheets and create more digital twins instead,”
said Jul Pedersen.


Working with digital twins to optimise, for example, container operations is nothing new. However, the deployment of wind installations tends to be more complex than other port processes, so optimising the design of these processes is extra important. There are many activities going on at the same time. For example, ships arrive from different countries bringing specialist equipment.

The capacity at Esbjerg is expected to steadily increase from 1.5 GW to 4.5 GW per year by 2025, when the required changes will have been completed. This will include, for example, the rebuilding of various access roads.

“It’s a great achievement that we’ve accomplished together, and one that we can definitely use here in the United States and elsewhere in Europe. The number of offshore wind installations we can push through in the future is truly impressive,”
said Joshua Singer, a Marine Structure Engineer who was the project manager on the development of the digital twin.


“The ability to digitally develop the port and physically see the project happening gives you the opportunity to identify issues and efficiencies before any significant capital investments are made, and that’s a hugely powerful tool for the offshore wind industry,”
adds Singer.

Jul Pedersen claims that the prospects of the project are even greater than just making port operations more efficient.


“Just imagine what we can achieve when we get suppliers entered into our digital twin. With nacelles from Cuxhaven and blades from Hull. There’s no reason to think we’ll stop at 4.5 GW, and the same goes for increasing capacity in the rest of Europe. And that’s before we even start expanding the ports,”
Jul Pedersen emphasises.