We are excited to announce a significant milestone in 4C Offshore's journey. Our integration into the TGS family marks the beginning of a new era in offshore wind market intelligence.
Through a pre-qualification system the applicants - on the basis of clearly defined conditions - pre-qualify, so that a short list of those parties who may participate will be formed ready for Invitation to Tender in early 2016. Furthermore, in order for TenneT to develop a Dutch North Sea Grid three other offshore grid connections ready to connect future offshore wind farms will be tendered. The requirements: five standardised substations of 700 MW connecting a total of 3450 MW of offshore wind (agreed in the Dutch Energy Agreement) will be realised by 2023.