DolWin1 Converter

The DolWin1 project involves a 167-km long, 800mw DC link by TenneT. The onshore grid connection point is a new converter station in Dörpen West, Emsland which makes the overland route 90km which is slightly longer than the BorWin1 and BorWin2 projects. DolWin1 will get an additional 250m cable connecting it to the DolWin3 platform by mid-2017. The cable will be attached to each platform by a steel bridge about 30m in length.
4C Offshore | DolWin1
Name
DolWin1 Converter
Status
Operational
Latitude
53.997°
Longitude
6.421°